Possession date of NIRMAN VRINDAVAN GARDENS PHASE 3: 31 December 2025, moved from 28 February 2021 (58 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51600014656. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about NIRMAN VRINDAVAN GARDENS PHASE 3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NIRMAN VRINDAVAN GARDENS PHASE 3 has moved

  1. 28 February 2021

    Completion date given when the project was registered

  2. 31 December 2021

    Extended at the builder's request (MahaRERA application EXT51600005841)

    Reason the builder gave MahaRERA:
    “THERE ARE 6 BUILDINGS IN THIS PROJECT. BUILDING NOS B3 AND C1 ARE COMPLETE IN ALL RESPECTS AND APPLICATION HAS BEEN MADE FOR COMPLETION CERTIFICATE TO THE NASHIK MUNICIPAL CORPORATION. EVEN ARCHITECTS CERTIFICATE IS OBTAINED CERTIFYING THAT…” Read the full reason“THERE ARE 6 BUILDINGS IN THIS PROJECT. BUILDING NOS B3 AND C1 ARE COMPLETE IN ALL RESPECTS AND APPLICATION HAS BEEN MADE FOR COMPLETION CERTIFICATE TO THE NASHIK MUNICIPAL CORPORATION. EVEN ARCHITECTS CERTIFICATE IS OBTAINED CERTIFYING THAT THE BUILDING IS COMPLETE. SO NEED ONLY 3 MONTHS EXTENSION FOR THIS BUILDINGS TO OBTAIN COMPLETION CERTIFICATE. THE COMPLETION DATE FOR THIS BUILDINGS HAS BEEN MENTIONED AS 28.2.2020. THIRD BUILDING B1/3, NO EXTESION IS SOUGHT FOR THIS BUILDING.. FOR BUILDING B4, A1/2 AND D1 WE HAVE NOT MADE ANY BOOKINGS AND THE MINIMAL WORK HAS BEEN DONE. SINCE NO BOOKIN…”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51600013431)

    Reason the builder gave MahaRERA:
    “Dear Sir/Ma’am, We have commenced this project on 20/12/2017 and obtain RERA registration No. P51600014656 which states the period of Project 20/12/2017 to 28/02/2021. The project consists 6 wings consisiting of 174 flats and through oversi…” Read the full reason“Dear Sir/Ma’am, We have commenced this project on 20/12/2017 and obtain RERA registration No. P51600014656 which states the period of Project 20/12/2017 to 28/02/2021. The project consists 6 wings consisiting of 174 flats and through oversight we have obtain single registration number for the entire project instead of wing wise. However, during the period of project the world has been hit with the pandemic covid-19 and our hon’ble PM announced nationwide lockdown during the month of March 2020 and after that the whole economy suffers. As during the project period the covid-19 hits for two t…”

Source: NIRMAN VRINDAVAN GARDENS PHASE 3’s extension records on MahaRERA (P51600014656), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NIRMAN VRINDAVAN GARDENS PHASE 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600014656
Status
Lapsed (registration period ended)
Builder
NIRMAN ESTATE DEVELOPERS PVT LTD
Location
Kedar Nagar, Nashik · 422012
Project type
Others
Registered on
20 Dec 2017
Completion date at registration
February 2021
Latest completion date
December 2025
Delay so far
58 months
Homes
168
Sold or booked
63%
Towers
6
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of NIRMAN VRINDAVAN GARDENS PHASE 3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B30%100%100%100%
B40%100%100%100%
C10%100%100%100%
A1/20%0%0%0%
B1/30%100%100%100%
D10%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • B3: covers 9 floors
  • B4: covers 9 floors
  • C1: covers 9 floors
  • A1/2: covers 8 floors
  • B1/3: covers 8 floors
  • D1: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIRMAN VRINDAVAN GARDENS PHASE 3 every month.

NIRMAN VRINDAVAN GARDENS PHASE 3: buildings, flats and land, as filed on MahaRERA

  • Buildings: B3 (9 floors, 32 units) · B4 (9 floors, 32 units) · C1 (9 floors, 32 units) · A1/2 (8 floors, 28 units) · B1/3 (8 floors, 28 units) · D1 (7 floors, 22 units)
  • Land: 15,158 sq m (about 3.7 acres) · sanctioned built-up 8,211 sq m · recreational space 1,858 sq m
  • Boundaries filed include: 9 MTR COLONY ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of NIRMAN VRINDAVAN GARDENS PHASE 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NIRMAN VRINDAVAN GARDENS PHASE 3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NIRMAN VRINDAVAN GARDENS PHASE 3

What is the possession date of NIRMAN VRINDAVAN GARDENS PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NIRMAN VRINDAVAN GARDENS PHASE 3 in Kedar Nagar, Nashik is 31 December 2025 — 58 months later than 28 February 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for NIRMAN VRINDAVAN GARDENS PHASE 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NIRMAN VRINDAVAN GARDENS PHASE 3's builder has filed on MahaRERA, the official one, is 31 December 2025, already 58 months later than the 28 February 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NIRMAN VRINDAVAN GARDENS PHASE 3 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN VRINDAVAN GARDENS PHASE 3's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2021, giving the reason "THERE ARE 6 BUILDINGS IN THIS PROJECT. BUILDING NOS B3 AND C1 ARE COMPLETE IN ALL RESPECTS AND APPLICATION HAS BEEN MADE FOR COMPLETION CERTIFICATE TO THE NASHIK MUNICIPAL CORPORATION. EVEN ARCHITECTS CERTIFICATE IS OBTAINED CERTIFYING THAT THE BUILDING IS COMPLETE. SO NEED ONLY 3 MONTHS EXTENSION FOR THIS BUILDINGS TO OBTAIN COMPLETION CERTIFICATE. THE COMPLETION DATE FOR THIS BUILDINGS HAS BEEN MENTIONED AS 28.2.2020. THIRD BUILDING B1/3, NO EXTESION IS SOUGHT FOR THIS BUILDING.. FOR BUILDING B4, A1/2 AND D1 WE HAVE NOT MADE ANY BOOKINGS AND THE MINIMAL WORK HAS BEEN DONE. SINCE NO BOOKIN…"; to 31 December 2025, giving the reason "Dear Sir/Ma’am, We have commenced this project on 20/12/2017 and obtain RERA registration No. P51600014656 which states the period of Project 20/12/2017 to 28/02/2021. The project consists 6 wings consisiting of 174 flats and through oversight we have obtain single registration number for the entire project instead of wing wise. However, during the period of project the world has been hit with the pandemic covid-19 and our hon’ble PM announced nationwide lockdown during the month of March 2020 and after that the whole economy suffers. As during the project period the covid-19 hits for two t…".

What is the RERA number of NIRMAN VRINDAVAN GARDENS PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NIRMAN VRINDAVAN GARDENS PHASE 3 in Kedar Nagar, Nashik is P51600014656.

Is NIRMAN VRINDAVAN GARDENS PHASE 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN VRINDAVAN GARDENS PHASE 3 is registered as P51600014656 and its status is "Lapsed (registration period ended)".

What is the construction status of NIRMAN VRINDAVAN GARDENS PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN VRINDAVAN GARDENS PHASE 3's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 6 towers. GharKundli's full report compares construction progress with the deadline.

Does NIRMAN VRINDAVAN GARDENS PHASE 3 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is NIRMAN VRINDAVAN GARDENS PHASE 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN VRINDAVAN GARDENS PHASE 3 is registered on MahaRERA as P51600014656, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 58 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NIRMAN VRINDAVAN GARDENS PHASE 3's possession date changes?

The latest dates are on NIRMAN VRINDAVAN GARDENS PHASE 3's MahaRERA page (P51600014656). GharKundli's Kundli Watch sends a free WhatsApp update on NIRMAN VRINDAVAN GARDENS PHASE 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NIRMAN VRINDAVAN GARDENS PHASE 3 have?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN VRINDAVAN GARDENS PHASE 3 has 6 buildings filed: B3 with 9 floors and 32 units; B4 with 9 floors and 32 units; C1 with 9 floors and 32 units; A1/2 with 8 floors and 28 units; B1/3 with 8 floors and 28 units; D1 with 7 floors and 22 units.

How big is the land of NIRMAN VRINDAVAN GARDENS PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN VRINDAVAN GARDENS PHASE 3 stands on 15,158 sq m of land (about 3.7 acres), with 8,211 sq m of sanctioned built-up area and 1,858 sq m of recreational open space.

Where can I read reviews of NIRMAN VRINDAVAN GARDENS PHASE 3?

Google Maps has reviews of NIRMAN VRINDAVAN GARDENS PHASE 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NIRMAN VRINDAVAN GARDENS PHASE 3?

NIRMAN VRINDAVAN GARDENS PHASE 3 by NIRMAN ESTATE DEVELOPERS PVT LTD is in Kedar Nagar, Nashik (pincode 422012), near Kamathwade, Ambad, Maharashtra, and is registered on MahaRERA as P51600014656, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9 MTR COLONY ROAD.

How many homes are in NIRMAN VRINDAVAN GARDENS PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN VRINDAVAN GARDENS PHASE 3 has 168 homes in 6 towers registered on MahaRERA, and 63% of them are sold or booked.

When was NIRMAN VRINDAVAN GARDENS PHASE 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN VRINDAVAN GARDENS PHASE 3 was registered on MahaRERA on 20 December 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on NIRMAN VRINDAVAN GARDENS PHASE 3?

No court cases are listed for NIRMAN VRINDAVAN GARDENS PHASE 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of NIRMAN VRINDAVAN GARDENS PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NIRMAN ESTATE DEVELOPERS PVT LTD, which has 2 other projects registered on MahaRERA.

Other projects in Nashik

All 36 projects in Ashok Nagar (422012) →

Other projects by NIRMAN ESTATE DEVELOPERS PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.