ESSPEE TOWER
by BHATIA BUILDERS AND DEVELOPERS PVT LTDC · Borivali East, MumbaiAlso near Borivali West, Rajendra Nagar, Magathane
Possession date of ESSPEE TOWER: 30 November 2027, moved from 30 June 2021 (73 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800007805, and currently active. Its completion date has moved from June 2021 to November 2027: 73 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about ESSPEE TOWER?
How the possession date of ESSPEE TOWER has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT51800010207)
Reason the builder gave MahaRERA: “DUE TO COVID , LACK OF FUND AND LABOUR”
31 July 2027
Extended at the builder's request (MahaRERA application EXT51800017300)
Reason the builder gave MahaRERA: “DUE TO DELAY IN GETTING APPROVALS FROM AUTHORITY.”
30 November 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ESSPEE TOWER’s extension records on MahaRERA (P51800007805), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ESSPEE TOWER
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the November 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800007805
- Status
- Registered and active
- Builder
- BHATIA BUILDERS AND DEVELOPERS PVT LTDC
- Location
- Borivali East, Mumbai · 400066
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- November 2027
- Delay so far
- 73 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 30
- Sold or booked
- 20%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of ESSPEE TOWER, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ESSPEE TOWER-ESSPEE SQUARE | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- ESSPEE TOWER-ESSPEE SQUARE: covers 25 for esspee tower and upto plinth for esspee square
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ESSPEE TOWER every month.
ESSPEE TOWER: buildings, flats and land, as filed on MahaRERA
- Buildings: ESSPEE TOWER-ESSPEE SQUARE (37 floors, 30 units)
- Land: 4,550 sq m (about 1.1 acres) · sanctioned built-up 2,078 sq m · recreational space 460 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Bhatia Builders AND Developers PVT Ltdc has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 2 still being built, 1 past the promised date (typically 48 months late). 2 complaints on MahaRERA across 1 project.
Read Google reviews of ESSPEE TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ESSPEE TOWER: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ESSPEE TOWER
What is the possession date of ESSPEE TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ESSPEE TOWER in Borivali East, Mumbai is 30 November 2027 — 73 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ESSPEE TOWER?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ESSPEE TOWER's builder has filed on MahaRERA, the official one, is 30 November 2027, already 73 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ESSPEE TOWER extended?
According to GharKundli's check of MahaRERA records (updated November 2026), ESSPEE TOWER's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2022, giving the reason "DUE TO COVID , LACK OF FUND AND LABOUR"; to 31 July 2027, giving the reason "DUE TO DELAY IN GETTING APPROVALS FROM AUTHORITY.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of ESSPEE TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ESSPEE TOWER in Borivali East, Mumbai is P51800007805.
Is ESSPEE TOWER registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ESSPEE TOWER is registered as P51800007805 and its status is "Registered and active".
What is the construction status of ESSPEE TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), ESSPEE TOWER's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ESSPEE TOWER-ESSPEE SQUARE is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does ESSPEE TOWER have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ESSPEE TOWER safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), ESSPEE TOWER is registered on MahaRERA as P51800007805, its completion date has moved 73 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ESSPEE TOWER's possession date changes?
The latest dates are on ESSPEE TOWER's MahaRERA page (P51800007805). GharKundli's Kundli Watch sends a free WhatsApp update on ESSPEE TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ESSPEE TOWER have?
According to GharKundli's check of MahaRERA records (updated November 2026), ESSPEE TOWER has one building filed: ESSPEE TOWER-ESSPEE SQUARE with 37 floors and 30 units.
How big is the land of ESSPEE TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), ESSPEE TOWER stands on 4,550 sq m of land (about 1.1 acres), with 2,078 sq m of sanctioned built-up area and 460 sq m of recreational open space.
What is the track record of ESSPEE TOWER's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhatia Builders AND Developers PVT Ltdc has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 2 still being built, 1 past the promised date (typically 48 months late). 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ESSPEE TOWER?
Google Maps has reviews of ESSPEE TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ESSPEE TOWER?
ESSPEE TOWER by BHATIA BUILDERS AND DEVELOPERS PVT LTDC is in Borivali East, Mumbai (pincode 400066), near Borivali West, Rajendra Nagar, Magathane, Maharashtra, and is registered on MahaRERA as P51800007805, per GharKundli's check of MahaRERA records.
How many homes are in ESSPEE TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), ESSPEE TOWER has 30 homes in 1 tower registered on MahaRERA, and 20% of them are sold or booked.
When was ESSPEE TOWER registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ESSPEE TOWER was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ESSPEE TOWER?
No court cases are listed for ESSPEE TOWER on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of ESSPEE TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is BHATIA BUILDERS AND DEVELOPERS PVT LTDC, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ESSPEE TOWER
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400066
- Rustomjee Summit
- RAJENDRA NAGAR SWAGAT CHSL
- RAJENDRA NAGAR OMSAI CO-OPERATIVE HOUSING SOCIETY LIMITED
- MEGH MAHAL CHSL
- PARSHURAM HEIGHTS
- DTG ASHFORD
- H. Rishabraj AER
- Paras Darshan
Other projects by BHATIA BUILDERS AND DEVELOPERS PVT LTDC
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.