Tanishq Residency
by PRATHAMESH DEVELOPERS (Titan) · Kurla, Mumbai 400070Also near Ghatkopar East, Ghatkopar west, Ghatkopar Kirol
What’s in the report? →Possession date of Tanishq Residency (MahaRERA P51800005734): 31 December 2025, moved from 30 December 2023 (24 months later), and it has already passed. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800005734. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800005734, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Tanishq Residency?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Tanishq Residency has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51800017997)
Reason the builder gave MahaRERA: “DELAY IN APPROVAL FROM THE GOVT DEPARTMENT . WE SHALL COMPLETE THE BUILDING WITHIN 1 YEAR.”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800025712)
Reason the builder gave MahaRERA:
“the project is almost completed and applied for the oc of the rehab portion. as the competent authority is SRA therefore the sale building oc shall be issued after the oc of the rehab wing is issued. We are positive about obtaining OC as so…” Read the full reason
“the project is almost completed and applied for the oc of the rehab portion. as the competent authority is SRA therefore the sale building oc shall be issued after the oc of the rehab wing is issued. We are positive about obtaining OC as soon as possible. we have obtained the necessary consent for the extension therefore kindly do the needful.”
Source: Tanishq Residency’s extension records on MahaRERA (P51800005734), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Tanishq Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800005734
- Status
- Lapsed (registration period ended)
- Builder
- PRATHAMESH DEVELOPERS
- Location
- Kurla, Mumbai · 400070
- Project type
- Others
- Registered on
- 11 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- December 2025
- Delay so far
- 24 months
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Tanishq Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| TANISHQ RESIDENCY - A WING | 100% | 100% | 70% | 40% |
| TANISHQ RESIDENCY - B WING | 100% | 100% | 70% | 40% |
| TANISHQ RESIDENCY - C WING | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tanishq Residency every 1–2 months.
Tanishq Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: TANISHQ RESIDENCY - A WING (16 floors) · TANISHQ RESIDENCY - B WING (16 floors) · TANISHQ RESIDENCY - C WING (16 floors)
- Land: 2,218 sq m (about 0.5 acres) · sanctioned built-up 6,732 sq m
- Boundaries filed include: MILIND NAGAR, KURLA CARSHED ROAD, PREMIER ROAD
- Land, as filed: 636 PT
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Maverick Realtors (a group of 9 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 21 GharKundli has checked: 7 finished, 2 within the promised date and 5 needed more time (typically 15 months); 11 still being built, 5 past the promised date (typically 48 months late); 3 lapsed. 8 complaints on MahaRERA across 5 projects.
Read Google reviews of Tanishq Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Tanishq Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Tanishq Residency
What is the possession date of Tanishq Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tanishq Residency in Kurla, Mumbai is 31 December 2025 — 24 months later than 30 December 2023, the date given at registration. That date has already passed.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Tanishq Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Tanishq Residency's builder has filed on MahaRERA, the official one, is 31 December 2025, already 24 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Tanishq Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Tanishq Residency's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "DELAY IN APPROVAL FROM THE GOVT DEPARTMENT . WE SHALL COMPLETE THE BUILDING WITHIN 1 YEAR."; to 31 December 2025, giving the reason "the project is almost completed and applied for the oc of the rehab portion. as the competent authority is SRA therefore the sale building oc shall be issued after the oc of the rehab wing is issued. We are positive about obtaining OC as soon as possible. we have obtained the necessary consent for the extension therefore kindly do the needful.".
What is the RERA number of Tanishq Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tanishq Residency in Kurla, Mumbai is P51800005734.
Is Tanishq Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tanishq Residency is registered as P51800005734 and its status is "Lapsed (registration period ended)".
What is the current construction status of Tanishq Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Tanishq Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Tanishq Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Tanishq Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Tanishq Residency is registered on MahaRERA as P51800005734, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Tanishq Residency?
Tanishq Residency isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Tanishq Residency?
For a flat in Tanishq Residency (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Tanishq Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Tanishq Residency isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Tanishq Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Tanishq Residency's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Tanishq Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Tanishq Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Tanishq Residency's possession date changes?
The latest dates are on Tanishq Residency's MahaRERA page (P51800005734). GharKundli's Kundli Watch sends a free WhatsApp update on Tanishq Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Tanishq Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Tanishq Residency has 3 buildings filed: TANISHQ RESIDENCY - A WING with 16 floors; TANISHQ RESIDENCY - B WING with 16 floors; TANISHQ RESIDENCY - C WING with 16 floors.
How big is the land of Tanishq Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Tanishq Residency stands on 2,218 sq m of land (about 0.5 acres), with 6,732 sq m of sanctioned built-up area.
What is the track record of Tanishq Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Maverick Realtors (a group of 9 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 21 GharKundli has checked: 7 finished, 2 within the promised date and 5 needed more time (typically 15 months); 11 still being built, 5 past the promised date (typically 48 months late); 3 lapsed. 8 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Tanishq Residency?
Google Maps has reviews of Tanishq Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Tanishq Residency?
Tanishq Residency by PRATHAMESH DEVELOPERS (Titan) is in Kurla, Mumbai, pincode 400070 (near Ghatkopar East, Ghatkopar west, Ghatkopar Kirol), Maharashtra, and is registered on MahaRERA as P51800005734, per GharKundli's check of MahaRERA records. Its boundaries filed there include MILIND NAGAR, KURLA CARSHED ROAD, PREMIER ROAD. Its land is filed as 636 PT. GharKundli lists all 92 MahaRERA projects in Kurla West (400070).
When was Tanishq Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tanishq Residency was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Does Tanishq Residency have any legal issues or court cases?
1 court case is listed for Tanishq Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Tanishq Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRATHAMESH DEVELOPERS, the company Titan files this project under, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Tanishq Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kurla West (400070)
- Sai Chamunda
- Deraiya Luxurio
- Sayba Arcadia
- Jai Shreeram Prasanna CHSL
- Dadamiya’s Man'souza Height
- Kalyan Kutir Co-operative Housing Society Limited
- Taiba Residency
- Anupam Villa CHSL
Other projects by PRATHAMESH DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.