Shakuntala Residency
by SHREE BALAJI INFRA ENTERPRISES · Igatpuri, Nashik 422403
What’s in the report? →Possession date of Shakuntala Residency (MahaRERA P51600018050): 30 March 2022, moved from 30 September 2020 (18 months later), and it has already passed. It has 14 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600018050. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51600018050, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (March 2022) has passed.
What do you want to know about Shakuntala Residency?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shakuntala Residency has moved
30 September 2020
Completion date given when the project was registered
30 September 2021
Extended at the builder's request (MahaRERA application EXT51600009177)
Reason the builder gave MahaRERA: “DUE TO PANDIMIC PROJECT STOPPED”
30 March 2022
Revised completion date on MahaRERA
Source: Shakuntala Residency’s extension records on MahaRERA (P51600018050), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shakuntala Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600018050
- Status
- Lapsed (registration period ended)
- Builder
- SHREE BALAJI INFRA ENTERPRISES
- Location
- Igatpuri, Nashik · 422403
- Project type
- Residential / Group Housing
- Registered on
- 10 Oct 2018
- Completion date at registration
- September 2020
- Latest completion date
- March 2022
- Delay so far
- 18 months
- Homes
- 14
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shakuntala Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHAKUNTALA RESIDENCY | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shakuntala Residency every 1–2 months.
Shakuntala Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: SHAKUNTALA RESIDENCY (5 floors)
- Land: 345 sq m (about 0.1 acres) · sanctioned built-up 569 sq m
- Land, as filed: 10 24 7 1 8 1 311 2
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shakuntala Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shakuntala Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shakuntala Residency
What is the possession date of Shakuntala Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shakuntala Residency in Igatpuri, Nashik is 30 March 2022 — 18 months later than 30 September 2020, the date given at registration. That date has already passed.
The date has already moved 18 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shakuntala Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shakuntala Residency's builder has filed on MahaRERA, the official one, is 30 March 2022, already 18 months later than the 30 September 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shakuntala Residency extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Shakuntala Residency's builder applied to MahaRERA to extend the completion date once: to 30 September 2021, giving the reason "DUE TO PANDIMIC PROJECT STOPPED".
What is the RERA number of Shakuntala Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shakuntala Residency in Igatpuri, Nashik is P51600018050.
Is Shakuntala Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shakuntala Residency is registered as P51600018050 and its status is "Lapsed (registration period ended)".
What is the current construction status of Shakuntala Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Shakuntala Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHAKUNTALA RESIDENCY is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Shakuntala Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Shakuntala Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Shakuntala Residency is registered on MahaRERA as P51600018050, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shakuntala Residency?
Shakuntala Residency isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shakuntala Residency?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shakuntala Residency: gharkundli.com/tools/property-cost-calculator
Has Shakuntala Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Shakuntala Residency isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 March 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Shakuntala Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shakuntala Residency's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 March 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Shakuntala Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Shakuntala Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shakuntala Residency's possession date changes?
The latest dates are on Shakuntala Residency's MahaRERA page (P51600018050). GharKundli's Kundli Watch sends a free WhatsApp update on Shakuntala Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shakuntala Residency have?
According to GharKundli's check of MahaRERA records (updated November 2026), Shakuntala Residency has one building filed: SHAKUNTALA RESIDENCY with 5 floors.
How big is the land of Shakuntala Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shakuntala Residency stands on 345 sq m of land (about 0.1 acres), with 569 sq m of sanctioned built-up area.
What are the reviews of Shakuntala Residency?
Google Maps has reviews of Shakuntala Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shakuntala Residency?
Shakuntala Residency by SHREE BALAJI INFRA ENTERPRISES is in Igatpuri, Nashik, pincode 422403, Maharashtra, and is registered on MahaRERA as P51600018050, per GharKundli's check of MahaRERA records. Its land is filed as 10 24 7 1 8 1 311 2. GharKundli lists all 47 MahaRERA projects in Igatpuri (422403).
How many flats are in Shakuntala Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shakuntala Residency has 14 homes in 1 tower registered on MahaRERA.
When was Shakuntala Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shakuntala Residency was registered on MahaRERA on 10 October 2018. GharKundli did not find a title report on the land on file there.
Does Shakuntala Residency have any legal issues or court cases?
No court cases are listed for Shakuntala Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Shakuntala Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE BALAJI INFRA ENTERPRISES.
Check it yourself on MahaRERA
- How to check the possession date of Shakuntala Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Igatpuri (422403)
- Manomay Natures Paradize
- Park Bellagio
- Indo Asian Signature
- Rosewood - I J and K Wing
- Western Hills
- Mysty Heaven
- Anandvann Phase II
- United Infinity
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.