VILAS VAIBHAV CHS
by TUVIN CONSTRUCTIONS LLP · Eksar (S) R/N, MumbaiAlso near Borivali West, Shimpoli, Vile Parle East
Possession date of VILAS VAIBHAV CHS: 30 April 2028, moved from 27 October 2022 (62 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800012414, and currently active. Its completion date has moved from October 2022 to April 2028: 62 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VILAS VAIBHAV CHS?
GharKundli’s full report on VILAS VAIBHAV CHS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800012414
- Status
- Registered and active
- Builder
- TUVIN CONSTRUCTIONS LLP
- Location
- Eksar (S) R/N, Mumbai · 400092
- Project type
- Residential / Group Housing
- Registered on
- 1 Sep 2017
- Completion date at registration
- October 2022
- Latest completion date
- April 2028
- Delay so far
- 62 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 35
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Appeals at the tribunal
- 4
- Title report on file
- Not found
Construction progress of VILAS VAIBHAV CHS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Vilash Vaibhave CHS-Redevelopment project | 100% | 69% | 30% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Vilash Vaibhave CHS-Redevelopment project: covers 13 floors
Latest CC order on MahaRERA: dated 16/07/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VILAS VAIBHAV CHS every month.
VILAS VAIBHAV CHS: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 413 – 483 | 12 |
| 2 BHK | 675 | 12 |
| 3 BHK | 939 | 11 |
- Buildings: Vilash Vaibhave CHS-Redevelopment project (13 floors, 35 units)
- Car parking: 20 covered, 9 open
- Land: 882 sq m (about 0.2 acres) · sanctioned built-up 2,373 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of VILAS VAIBHAV CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VILAS VAIBHAV CHS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VILAS VAIBHAV CHS
What is the possession date of VILAS VAIBHAV CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VILAS VAIBHAV CHS in Eksar (S) R/N, Mumbai is 30 April 2028 — 62 months later than 27 October 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for VILAS VAIBHAV CHS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VILAS VAIBHAV CHS's builder has filed on MahaRERA, the official one, is 30 April 2028, already 62 months later than the 27 October 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of VILAS VAIBHAV CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VILAS VAIBHAV CHS in Eksar (S) R/N, Mumbai is P51800012414.
Is VILAS VAIBHAV CHS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VILAS VAIBHAV CHS is registered as P51800012414 and its status is "Registered and active".
What is the construction status of VILAS VAIBHAV CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), VILAS VAIBHAV CHS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Vilash Vaibhave CHS-Redevelopment project is 69% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.
Does VILAS VAIBHAV CHS have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is VILAS VAIBHAV CHS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VILAS VAIBHAV CHS is registered on MahaRERA as P51800012414, its completion date has moved 62 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VILAS VAIBHAV CHS's possession date changes?
The latest dates are on VILAS VAIBHAV CHS's MahaRERA page (P51800012414). GharKundli's Kundli Watch sends a free WhatsApp update on VILAS VAIBHAV CHS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VILAS VAIBHAV CHS have?
According to GharKundli's check of MahaRERA records (updated October 2026), VILAS VAIBHAV CHS has one building filed: Vilash Vaibhave CHS-Redevelopment project with 13 floors and 35 units.
What are the flat sizes (carpet area) in VILAS VAIBHAV CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for VILAS VAIBHAV CHS: 1 BHK: 413 to 483 sq ft carpet (12 homes); 2 BHK: 675 sq ft carpet (12 homes); 3 BHK: 939 sq ft carpet (11 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does VILAS VAIBHAV CHS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 20 covered and 9 open car parking spaces for VILAS VAIBHAV CHS.
How big is the land of VILAS VAIBHAV CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), VILAS VAIBHAV CHS stands on 882 sq m of land (about 0.2 acres), with 2,373 sq m of sanctioned built-up area.
Where can I read reviews of VILAS VAIBHAV CHS?
Google Maps has reviews of VILAS VAIBHAV CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VILAS VAIBHAV CHS?
VILAS VAIBHAV CHS by TUVIN CONSTRUCTIONS LLP is in Eksar (S) R/N, Mumbai (pincode 400092), near Borivali West, Shimpoli, Vile Parle East, Maharashtra, and is registered on MahaRERA as P51800012414, per GharKundli's check of MahaRERA records.
How many homes are in VILAS VAIBHAV CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), VILAS VAIBHAV CHS has 35 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was VILAS VAIBHAV CHS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VILAS VAIBHAV CHS was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on VILAS VAIBHAV CHS?
No court cases are listed for VILAS VAIBHAV CHS on MahaRERA, and 4 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of VILAS VAIBHAV CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TUVIN CONSTRUCTIONS LLP.
Check it yourself on MahaRERA
- How to check the possession date of VILAS VAIBHAV CHS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
All projects in Borivali West (400092) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.