Vrundavan
by Yogesh Kishorbhai Dattani HUF · Besides Meet Abhas, Nashik
Possession: Vrundavan is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600021653. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Vrundavan?
How the possession date of Vrundavan has moved
30 September 2020
Completion date given when the project was registered
31 December 2022
Extended at the builder's request (MahaRERA application EXT51600012653)
Reason the builder gave MahaRERA: “Delay in receiving Occupancy Certificate from Competent Authority”
Source: Vrundavan’s extension records on MahaRERA (P51600021653), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vrundavan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600021653
- Status
- Completed
- Builder
- Yogesh Kishorbhai Dattani HUF
- Location
- Besides Meet Abhas, Nashik · 423105
- Project type
- Residential / Group Housing
- Registered on
- 19 Jul 2019
- Completion date at registration
- September 2020
- Latest completion date
- December 2022
- Delay so far
- 27 months
- Homes
- 12
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Vrundavan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Vrundavan | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vrundavan every month.
Vrundavan: buildings, flats and land, as filed on MahaRERA
- Buildings: Vrundavan (5 floors)
- Land: 710 sq m (about 0.2 acres) · sanctioned built-up 779 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Vrundavan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vrundavan: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Vrundavan
What is the possession date of Vrundavan?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Vrundavan in Besides Meet Abhas, Nashik is 31 December 2022 — 27 months later than 30 September 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Vrundavan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vrundavan's builder has filed on MahaRERA, the official one, is 31 December 2022, already 27 months later than the 30 September 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vrundavan extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Vrundavan's builder applied to MahaRERA to extend the completion date once: to 31 December 2022, giving the reason "Delay in receiving Occupancy Certificate from Competent Authority".
What is the RERA number of Vrundavan?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Vrundavan in Besides Meet Abhas, Nashik is P51600021653.
Is Vrundavan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Vrundavan is registered as P51600021653 and its status is "Completed".
What is the construction status of Vrundavan?
According to GharKundli's check of MahaRERA records (updated November 2026), Vrundavan's status on MahaRERA is "Completed". As filed by the builder, slab work on Vrundavan is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Vrundavan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Vrundavan safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Vrundavan is registered on MahaRERA as P51600021653, its MahaRERA status is "Completed", its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Vrundavan's possession date changes?
The latest dates are on Vrundavan's MahaRERA page (P51600021653). GharKundli's Kundli Watch sends a free WhatsApp update on Vrundavan every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vrundavan have?
According to GharKundli's check of MahaRERA records (updated November 2026), Vrundavan has one building filed: Vrundavan with 5 floors.
How big is the land of Vrundavan?
According to GharKundli's check of MahaRERA records (updated November 2026), Vrundavan stands on 710 sq m of land (about 0.2 acres), with 779 sq m of sanctioned built-up area.
Where can I read reviews of Vrundavan?
Google Maps has reviews of Vrundavan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Vrundavan?
Vrundavan by Yogesh Kishorbhai Dattani HUF is in Besides Meet Abhas, Nashik (pincode 423105), Maharashtra, and is registered on MahaRERA as P51600021653, per GharKundli's check of MahaRERA records.
How many homes are in Vrundavan?
According to GharKundli's check of MahaRERA records (updated November 2026), Vrundavan has 12 homes in 1 tower registered on MahaRERA.
When was Vrundavan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Vrundavan was registered on MahaRERA on 19 July 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Vrundavan?
No court cases are listed for Vrundavan on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Vrundavan?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Yogesh Kishorbhai Dattani HUF.
Check it yourself on MahaRERA
- How to check the possession date of Vrundavan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Malegaon
- SANKET HEIGHTS
- CAMP CENTRAL
- UNITY HEIGHTS
- Swaroop Residency
- Bachhav Empire
- SHREE SANKET EMPIRE
- HIRKANI HEIGHTS
- Sanket Luxuria
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.