by SETHIA INFRASTRUCTURE PVT LTD · Malad East, MumbaiAlso near Malad West Dely, Motilal Nagar

Possession date of SETHIA DARSHAN: 30 April 2027, moved from 30 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800011224, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SETHIA DARSHAN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SETHIA DARSHAN has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51800025549)

    Reason the builder gave MahaRERA:
    “Provided that the Authority may in reasonable circumstances, without default on the part of the promoter, based on the facts of each case, and for reasons to be recorded in writing, extend the registration granted to a project for such time…” Read the full reason“Provided that the Authority may in reasonable circumstances, without default on the part of the promoter, based on the facts of each case, and for reasons to be recorded in writing, extend the registration granted to a project for such time as it considers necessary, which shall, in aggregate, not exceed a period of one year:”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SETHIA DARSHAN’s extension records on MahaRERA (P51800011224), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SETHIA DARSHAN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints and 3 court cases, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800011224
Status
Registered and active
Builder
SETHIA INFRASTRUCTURE PVT LTD
Location
Malad East, Mumbai · 400097
Project type
Others
Registered on
31 Aug 2017
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
72
Sold or booked
75%
Towers
1
Complaints on MahaRERA
4
Court cases listed
3
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of SETHIA DARSHAN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SETHIA DARSHAN100%100%100%80%

Commencement certificate (CC), as filed on MahaRERA

  • SETHIA DARSHAN: covers 22nd floor including OHWT & LMR

Latest CC order on MahaRERA: dated 13/07/2023.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SETHIA DARSHAN every month.

SETHIA DARSHAN: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK558 – 79541
Shops152 – 73919
Other55816
1 BHK373 – 79515
  • Buildings: SETHIA DARSHAN (24 floors, 91 units)
  • Land: 1,447 sq m (about 0.4 acres) · sanctioned built-up 1,434 sq m
  • Boundaries filed include: 18 30 Road Line

The builder’s record and reviews

Sethia Infrastructure (a group of 7 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 35 months); 7 still being built, 5 past the promised date (typically 18 months late); 1 lapsed. 40 complaints on MahaRERA across 5 projects.

Read Google reviews of SETHIA DARSHAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SETHIA DARSHAN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SETHIA DARSHAN

What is the possession date of SETHIA DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SETHIA DARSHAN in Malad East, Mumbai is 30 April 2027 — 24 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SETHIA DARSHAN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SETHIA DARSHAN's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SETHIA DARSHAN extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SETHIA DARSHAN's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Provided that the Authority may in reasonable circumstances, without default on the part of the promoter, based on the facts of each case, and for reasons to be recorded in writing, extend the registration granted to a project for such time as it considers necessary, which shall, in aggregate, not exceed a period of one year:". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SETHIA DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SETHIA DARSHAN in Malad East, Mumbai is P51800011224.

Is SETHIA DARSHAN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SETHIA DARSHAN is registered as P51800011224 and its status is "Registered and active".

What is the construction status of SETHIA DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SETHIA DARSHAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SETHIA DARSHAN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SETHIA DARSHAN have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SETHIA DARSHAN safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SETHIA DARSHAN is registered on MahaRERA as P51800011224, its completion date has moved 24 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SETHIA DARSHAN's possession date changes?

The latest dates are on SETHIA DARSHAN's MahaRERA page (P51800011224). GharKundli's Kundli Watch sends a free WhatsApp update on SETHIA DARSHAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SETHIA DARSHAN have?

According to GharKundli's check of MahaRERA records (updated October 2026), SETHIA DARSHAN has one building filed: SETHIA DARSHAN with 24 floors and 91 units.

What are the flat sizes (carpet area) in SETHIA DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SETHIA DARSHAN: 2 BHK: 558 to 795 sq ft carpet (41 homes); Other: 558 sq ft carpet (16 homes); 1 BHK: 373 to 795 sq ft carpet (15 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of SETHIA DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SETHIA DARSHAN stands on 1,447 sq m of land (about 0.4 acres), with 1,434 sq m of sanctioned built-up area.

What is the track record of SETHIA DARSHAN's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Infrastructure (a group of 7 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 35 months); 7 still being built, 5 past the promised date (typically 18 months late); 1 lapsed. 40 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SETHIA DARSHAN?

Google Maps has reviews of SETHIA DARSHAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SETHIA DARSHAN?

SETHIA DARSHAN by SETHIA INFRASTRUCTURE PVT LTD is in Malad East, Mumbai (pincode 400097), near Malad West Dely, Motilal Nagar, Maharashtra, and is registered on MahaRERA as P51800011224, per GharKundli's check of MahaRERA records. Its boundaries filed there include 18 30 Road Line.

How many homes are in SETHIA DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SETHIA DARSHAN has 72 homes in 1 tower registered on MahaRERA, and 75% of them are sold or booked.

When was SETHIA DARSHAN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SETHIA DARSHAN was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SETHIA DARSHAN?

3 court cases are listed for SETHIA DARSHAN on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SETHIA DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SETHIA INFRASTRUCTURE PVT LTD.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400097

All 195 projects in Malad East (400097) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.