Possession date of Indira Appartment (MahaRERA P51600023089): 30 April 2027. It has 12 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600023089, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51600023089, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Indira Appartment?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Indira Appartment has moved

  1. 30 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Indira Appartment’s extension records on MahaRERA (P51600023089), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Indira Appartment

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600023089
Status
Registered and active
Builder
J K CONSTROTECH
Location
CIDCO Colony S.O (Nashik), Nashik · 422009
Project type
Others
Registered on
29 Nov 2019
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
12
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Indira Appartment, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
INDIRA APPARTMENT100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Indira Appartment every 1–2 months.

Indira Appartment: buildings, flats and land, as filed on MahaRERA

  • Buildings: INDIRA APPARTMENT (5 floors)
  • Land: 368 sq m (about 0.1 acres) · sanctioned built-up 459 sq m
  • Land, as filed: PLOT NO 34 878/4
  • Map: Get directions

The builder’s record and reviews

Ganraj Infra (a group of 5 linked companies) has 7 projects on MahaRERA since 2019, this one included. Of the 7 GharKundli has checked: 2 finished, all within the promised date; 4 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Indira Appartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Indira Appartment: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Indira Appartment

What is the possession date of Indira Appartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Indira Appartment in CIDCO Colony S.O (Nashik), Nashik is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Indira Appartment?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Indira Appartment's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Indira Appartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Indira Appartment in CIDCO Colony S.O (Nashik), Nashik is P51600023089.

Is Indira Appartment registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Indira Appartment is registered as P51600023089 and its status is "Registered and active".

What is the current construction status of Indira Appartment? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Indira Appartment's status on MahaRERA is "Registered and active". As filed by the builder, slab work on INDIRA APPARTMENT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Indira Appartment have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Indira Appartment safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Indira Appartment is registered on MahaRERA as P51600023089, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Indira Appartment?

Indira Appartment is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Indira Appartment?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Indira Appartment: gharkundli.com/tools/property-cost-calculator

Has Indira Appartment received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Indira Appartment is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Indira Appartment uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Indira Appartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Indira Appartment's possession date changes?

The latest dates are on Indira Appartment's MahaRERA page (P51600023089). GharKundli's Kundli Watch sends a free WhatsApp update on Indira Appartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Indira Appartment have?

According to GharKundli's check of MahaRERA records (updated November 2026), Indira Appartment has one building filed: INDIRA APPARTMENT with 5 floors.

How big is the land of Indira Appartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Indira Appartment stands on 368 sq m of land (about 0.1 acres), with 459 sq m of sanctioned built-up area.

What is the track record of Indira Appartment's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Ganraj Infra (a group of 5 linked companies) has 7 projects on MahaRERA since 2019, this one included. Of the 7 GharKundli has checked: 2 finished, all within the promised date; 4 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Indira Appartment?

Google Maps has reviews of Indira Appartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Indira Appartment?

Indira Appartment by J K CONSTROTECH (Ganraj) is in CIDCO Colony S.O (Nashik), Nashik, pincode 422009, Maharashtra, and is registered on MahaRERA as P51600023089, per GharKundli's check of MahaRERA records. Its land is filed as PLOT NO 34 878/4. GharKundli lists all 443 MahaRERA projects in CIDCO Colony (422009).

How many flats are in Indira Appartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Indira Appartment has 12 homes in 1 tower registered on MahaRERA.

When was Indira Appartment registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Indira Appartment was registered on MahaRERA on 29 November 2019. GharKundli did not find a title report on the land on file there.

Does Indira Appartment have any legal issues or court cases?

No court cases are listed for Indira Appartment on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Indira Appartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is J K CONSTROTECH, the company Ganraj files this project under.

All projects with possession due in 2027 in Nashik →

Other projects in CIDCO Colony (422009)

All 443 projects in CIDCO Colony (422009) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.