VIDA 56
by Ananapurna Enterprises Partnership Firm & Other One · Pandit Colony, Nashik
Possession date of VIDA 56: 6 December 2026, moved from 7 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600023370, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VIDA 56?
How the possession date of VIDA 56 has moved
7 December 2025
Completion date given when the project was registered
6 December 2026
Extended at the builder's request (MahaRERA application EA04122518534)
Reason the builder gave MahaRERA:
“Respected Sir We unable to complete the project till 07/12/2025. We request you to please grant us extension till 06/12/2026. We are in process of completion of project. The project is not completed within time specified in registration due…” Read the full reason
“Respected Sir We unable to complete the project till 07/12/2025. We request you to please grant us extension till 06/12/2026. We are in process of completion of project. The project is not completed within time specified in registration due to financial crunch and less booking response in the project we need additional time to complete the pending development works in the project.”
Source: VIDA 56’s extension records on MahaRERA (P51600023370), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VIDA 56
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600023370
- Status
- Registered and active
- Builder
- Ananapurna Enterprises Partnership Firm & Other One
- Location
- Pandit Colony, Nashik · 422005
- Project type
- Residential / Group Housing
- Registered on
- 12 Dec 2019
- Completion date at registration
- December 2025
- Latest completion date
- December 2026
- Delay so far
- 12 months
- Homes
- 57
- Sold or booked
- 23%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of VIDA 56, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING A | 100% | 100% | 95% | 20% |
| BUILDING B | 100% | 100% | 95% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING A: covers 8 floors
- BUILDING B: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VIDA 56 every month.
VIDA 56: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING A (8 floors, 40 units) · BUILDING B (8 floors, 17 units)
- Land: 2,535 sq m (about 0.6 acres) · sanctioned built-up 8,110 sq m
The builder’s record and reviews
Ananapurna Enterprises Partnership Firm & Other One (a group of 2 linked companies) has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of VIDA 56 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VIDA 56: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VIDA 56
What is the possession date of VIDA 56?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VIDA 56 in Pandit Colony, Nashik is 6 December 2026 — 12 months later than 7 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for VIDA 56?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VIDA 56's builder has filed on MahaRERA, the official one, is 6 December 2026, already 12 months later than the 7 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VIDA 56 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), VIDA 56's builder applied to MahaRERA to extend the completion date once: to 6 December 2026, giving the reason "Respected Sir We unable to complete the project till 07/12/2025. We request you to please grant us extension till 06/12/2026. We are in process of completion of project. The project is not completed within time specified in registration due to financial crunch and less booking response in the project we need additional time to complete the pending development works in the project.".
What is the RERA number of VIDA 56?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VIDA 56 in Pandit Colony, Nashik is P51600023370.
Is VIDA 56 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VIDA 56 is registered as P51600023370 and its status is "Registered and active".
What is the construction status of VIDA 56?
According to GharKundli's check of MahaRERA records (updated October 2026), VIDA 56's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does VIDA 56 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is VIDA 56 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VIDA 56 is registered on MahaRERA as P51600023370, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VIDA 56's possession date changes?
The latest dates are on VIDA 56's MahaRERA page (P51600023370). GharKundli's Kundli Watch sends a free WhatsApp update on VIDA 56 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VIDA 56 have?
According to GharKundli's check of MahaRERA records (updated October 2026), VIDA 56 has 2 buildings filed: BUILDING A with 8 floors and 40 units; BUILDING B with 8 floors and 17 units.
How big is the land of VIDA 56?
According to GharKundli's check of MahaRERA records (updated October 2026), VIDA 56 stands on 2,535 sq m of land (about 0.6 acres), with 8,110 sq m of sanctioned built-up area.
What is the track record of VIDA 56's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ananapurna Enterprises Partnership Firm & Other One (a group of 2 linked companies) has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of VIDA 56?
Google Maps has reviews of VIDA 56 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VIDA 56?
VIDA 56 by Ananapurna Enterprises Partnership Firm & Other One is in Pandit Colony, Nashik (pincode 422005), Maharashtra, and is registered on MahaRERA as P51600023370, per GharKundli's check of MahaRERA records.
How many homes are in VIDA 56?
According to GharKundli's check of MahaRERA records (updated October 2026), VIDA 56 has 57 homes in 2 towers registered on MahaRERA, and 23% of them are sold or booked.
When was VIDA 56 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VIDA 56 was registered on MahaRERA on 12 December 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on VIDA 56?
No court cases are listed for VIDA 56 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of VIDA 56?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ananapurna Enterprises Partnership Firm & Other One.
Check it yourself on MahaRERA
- How to check the possession date of VIDA 56
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Nashik →
Other projects in Nashik
- Real Spaces
- Fortunes Emerald Park
- Laxmi Commercial Complex
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- SHIV KUNJ
- YUNUS RESIDENCY
- Quillion Residencies at Quillion Park - Phase 2
- SHREE VISHVA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.