Alta Monte and Signet

by ERA REALTORS PRIVATE LIMITED · Kokanipada, Malad East, MumbaiAlso near Kurar Village, Dindoshi, Goregaon East

Possession date of Alta Monte and Signet: 31 December 2027, moved from 30 December 2024 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800010463, and currently active. 254 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Alta Monte and Signet?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Alta Monte and Signet has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT51800025763)

    Reason the builder gave MahaRERA:
    “a. The Developer have undertaken the redevelopment of larger property under the approved Slum Rehabilitation Scheme and the Allottees were aware of the complexities involved in the said Project, including its development potential, issue of…” Read the full reason“a. The Developer have undertaken the redevelopment of larger property under the approved Slum Rehabilitation Scheme and the Allottees were aware of the complexities involved in the said Project, including its development potential, issue of eligible/non-eligible slum dwellers, status of approvals etc That various slum dwellers as well as so called social workers had filed various litigations which caused loss of time and money to the Developer. It is submitted that several non-eligible slum dwellers in S.R. Scheme carried out “Dharna” agitation in front of the project gate from 23rd May 201…”
  3. 31 December 2027

    Extended at the builder's request (MahaRERA application EA04042620561)

    Reason the builder gave MahaRERA:
    “A. Discontinuation of Subvention Scheme: B. Economic downturn and Demonetization: C. Promoters Account became NPA: D. Force majeure (COVID 19 Pandemic): E. Dharna by Slum Dwellers F. Delay in Approvals G. New DP Rules H. Liquidity Crunch I.…” Read the full reason“A. Discontinuation of Subvention Scheme: B. Economic downturn and Demonetization: C. Promoters Account became NPA: D. Force majeure (COVID 19 Pandemic): E. Dharna by Slum Dwellers F. Delay in Approvals G. New DP Rules H. Liquidity Crunch I. Injunction Order”

Source: Alta Monte and Signet’s extension records on MahaRERA (P51800010463), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Alta Monte and Signet

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 254 complaints and 20 court cases, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800010463
Status
Registered and active
Builder
ERA REALTORS PRIVATE LIMITED
Location
Kokanipada, Malad East, Mumbai · 400097
Project type
Residential / Group Housing
Registered on
27 Aug 2017
Completion date at registration
December 2024
Latest completion date
December 2027
Delay so far
36 months
Homes
1,417
Sold or booked
97%
Towers
5
Complaints on MahaRERA
254
Court cases listed
20
Appeals at the tribunal
28
Title report on file
Not found

Construction progress of Alta Monte and Signet, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Alta Monte Tower B100%99%60%40%
Alta Monte Tower D North, West and South100%100%100%100%
Alta Monte Tower D3-12, 17-20, 25-27, 41-50 Floor East Wing100%100%100%100%
Alta Monte Tower D East Wing 13 to 16, 21 to 24, 28 to 40 Floors100%100%100%100%
Signet100%100%100%99%

Commencement certificate (CC), as filed on MahaRERA

  • Alta Monte Tower B: covers upto 51st upper floor
  • Alta Monte Tower D North, West and South: covers upto 53rd upper floor
  • Alta Monte Tower D3-12, 17-20, 25-27, 41-50 Floor East Wing: covers Up to top
  • Alta Monte Tower D East Wing 13 to 16, 21 to 24, 28 to 40 Floors: covers upto top
  • Signet: covers Up to top of 33rd upper floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Alta Monte and Signet every month.

Alta Monte and Signet: buildings, flats and land, as filed on MahaRERA

  • Buildings: Alta Monte Tower B (59 floors, 519 units) · Alta Monte Tower D North, West and South (61 floors, 232 units) · Alta Monte Tower D3-12, 17-20, 25-27, 41-50 Floor East Wing (36 floors, 27 units) · Alta Monte Tower D East Wing 13 to 16, 21 to 24, 28 to 40 Floors (31 floors, 51 units) · Signet (45 floors, 633 units)
  • Car parking: 853 covered
  • Land: 11,011 sq m (about 2.7 acres) · sanctioned built-up 1,11,324 sq m
  • Boundaries filed include: Western Express Highway
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Alta Monte and Signet →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Alta Monte and Signet: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Alta Monte and Signet

What is the possession date of Alta Monte and Signet?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Alta Monte and Signet in Kokanipada, Malad East, Mumbai is 31 December 2027 — 36 months later than 30 December 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Alta Monte and Signet?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Alta Monte and Signet's builder has filed on MahaRERA, the official one, is 31 December 2027, already 36 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Alta Monte and Signet extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Alta Monte and Signet's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "a. The Developer have undertaken the redevelopment of larger property under the approved Slum Rehabilitation Scheme and the Allottees were aware of the complexities involved in the said Project, including its development potential, issue of eligible/non-eligible slum dwellers, status of approvals etc That various slum dwellers as well as so called social workers had filed various litigations which caused loss of time and money to the Developer. It is submitted that several non-eligible slum dwellers in S.R. Scheme carried out “Dharna” agitation in front of the project gate from 23rd May 201…"; to 31 December 2027, giving the reason "A. Discontinuation of Subvention Scheme: B. Economic downturn and Demonetization: C. Promoters Account became NPA: D. Force majeure (COVID 19 Pandemic): E. Dharna by Slum Dwellers F. Delay in Approvals G. New DP Rules H. Liquidity Crunch I. Injunction Order".

What is the RERA number of Alta Monte and Signet?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Alta Monte and Signet in Kokanipada, Malad East, Mumbai is P51800010463.

Is Alta Monte and Signet registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Alta Monte and Signet is registered as P51800010463 and its status is "Registered and active".

What is the construction status of Alta Monte and Signet?

According to GharKundli's check of MahaRERA records (updated October 2026), Alta Monte and Signet's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 99% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does Alta Monte and Signet have complaints on MahaRERA?

254 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Alta Monte and Signet safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Alta Monte and Signet is registered on MahaRERA as P51800010463, its completion date has moved 36 months since registration and 254 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Alta Monte and Signet's possession date changes?

The latest dates are on Alta Monte and Signet's MahaRERA page (P51800010463). GharKundli's Kundli Watch sends a free WhatsApp update on Alta Monte and Signet every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Alta Monte and Signet have?

According to GharKundli's check of MahaRERA records (updated October 2026), Alta Monte and Signet has 5 buildings filed: Alta Monte Tower B with 59 floors and 519 units; Alta Monte Tower D North, West and South with 61 floors and 232 units; Alta Monte Tower D3-12, 17-20, 25-27, 41-50 Floor East Wing with 36 floors and 27 units; Alta Monte Tower D East Wing 13 to 16, 21 to 24, 28 to 40 Floors with 31 floors and 51 units; Signet with 45 floors and 633 units.

How much parking does Alta Monte and Signet have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 853 covered car parking spaces for Alta Monte and Signet.

How big is the land of Alta Monte and Signet?

According to GharKundli's check of MahaRERA records (updated October 2026), Alta Monte and Signet stands on 11,011 sq m of land (about 2.7 acres), with 1,11,324 sq m of sanctioned built-up area.

Where can I read reviews of Alta Monte and Signet?

Google Maps has reviews of Alta Monte and Signet written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 254 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Alta Monte and Signet?

Alta Monte and Signet by ERA REALTORS PRIVATE LIMITED is in Kokanipada, Malad East, Mumbai (pincode 400097), near Kurar Village, Dindoshi, Goregaon East, Maharashtra, and is registered on MahaRERA as P51800010463, per GharKundli's check of MahaRERA records. Its boundaries filed there include Western Express Highway.

How many homes are in Alta Monte and Signet?

According to GharKundli's check of MahaRERA records (updated October 2026), Alta Monte and Signet has 1,417 homes in 5 towers registered on MahaRERA, and 97% of them are sold or booked.

When was Alta Monte and Signet registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Alta Monte and Signet was registered on MahaRERA on 27 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Alta Monte and Signet?

20 court cases are listed for Alta Monte and Signet on MahaRERA, and 28 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Alta Monte and Signet?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ERA REALTORS PRIVATE LIMITED.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400097

All 195 projects in Malad East (400097) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.