by RISHIKESH BUILDERS AND DEVELOPERS · Devlali, Nashik

Possession date of TULASI BAUG: 31 December 2027, moved from 30 September 2022 (63 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600026532, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about TULASI BAUG?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of TULASI BAUG has moved

  1. 30 September 2022

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51600012649)

  3. 31 December 2027

    Extended at the builder's request (MahaRERA application EA03012619257)

    Reason the builder gave MahaRERA: “The construction work is complete and the application is submitted to corporation. However the completion is awaited due to the NOC of MHADA is not yet received. The application for MHADA NOC is submitted but the same is awaited.”

Source: TULASI BAUG’s extension records on MahaRERA (P51600026532), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TULASI BAUG

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600026532
Status
Registered and active
Builder
RISHIKESH BUILDERS AND DEVELOPERS
Location
Devlali, Nashik · 422401
Project type
Others
Registered on
30 Sep 2020
Completion date at registration
September 2022
Latest completion date
December 2027
Delay so far
63 months
Homes
56
Sold or booked
93%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of TULASI BAUG, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Tulsi Baug - Wing A100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Tulsi Baug - Wing A: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TULASI BAUG every month.

TULASI BAUG: buildings, flats and land, as filed on MahaRERA

  • Buildings: Tulsi Baug - Wing A (9 floors, 56 units)
  • Land: 1,258 sq m (about 0.3 acres) · sanctioned built-up 2,408 sq m
  • Boundaries filed include: Ekhara Road

The builder’s record and reviews

Rishikesh Builders & Developers has 4 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 31 months late). No complaints on MahaRERA.

Read Google reviews of TULASI BAUG →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TULASI BAUG: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TULASI BAUG

What is the possession date of TULASI BAUG?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TULASI BAUG in Devlali, Nashik is 31 December 2027 — 63 months later than 30 September 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for TULASI BAUG?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TULASI BAUG's builder has filed on MahaRERA, the official one, is 31 December 2027, already 63 months later than the 30 September 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of TULASI BAUG extended?

According to GharKundli's check of MahaRERA records (updated October 2026), TULASI BAUG's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025; to 31 December 2027, giving the reason "The construction work is complete and the application is submitted to corporation. However the completion is awaited due to the NOC of MHADA is not yet received. The application for MHADA NOC is submitted but the same is awaited.".

What is the RERA number of TULASI BAUG?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TULASI BAUG in Devlali, Nashik is P51600026532.

Is TULASI BAUG registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TULASI BAUG is registered as P51600026532 and its status is "Registered and active".

What is the construction status of TULASI BAUG?

According to GharKundli's check of MahaRERA records (updated October 2026), TULASI BAUG's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Tulsi Baug - Wing A is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does TULASI BAUG have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is TULASI BAUG safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), TULASI BAUG is registered on MahaRERA as P51600026532, its completion date has moved 63 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if TULASI BAUG's possession date changes?

The latest dates are on TULASI BAUG's MahaRERA page (P51600026532). GharKundli's Kundli Watch sends a free WhatsApp update on TULASI BAUG every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TULASI BAUG have?

According to GharKundli's check of MahaRERA records (updated October 2026), TULASI BAUG has one building filed: Tulsi Baug - Wing A with 9 floors and 56 units.

How big is the land of TULASI BAUG?

According to GharKundli's check of MahaRERA records (updated October 2026), TULASI BAUG stands on 1,258 sq m of land (about 0.3 acres), with 2,408 sq m of sanctioned built-up area.

What is the track record of TULASI BAUG's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Rishikesh Builders & Developers has 4 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 31 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of TULASI BAUG?

Google Maps has reviews of TULASI BAUG written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TULASI BAUG?

TULASI BAUG by RISHIKESH BUILDERS AND DEVELOPERS is in Devlali, Nashik (pincode 422401), Maharashtra, and is registered on MahaRERA as P51600026532, per GharKundli's check of MahaRERA records. Its boundaries filed there include Ekhara Road.

How many homes are in TULASI BAUG?

According to GharKundli's check of MahaRERA records (updated October 2026), TULASI BAUG has 56 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.

When was TULASI BAUG registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TULASI BAUG was registered on MahaRERA on 30 September 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on TULASI BAUG?

No court cases are listed for TULASI BAUG on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of TULASI BAUG?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RISHIKESH BUILDERS AND DEVELOPERS, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Nashik →

Other projects in pincode 422401

All 38 projects in Devlali (422401) →

Other projects by RISHIKESH BUILDERS AND DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.