SAI PARK
by Jay Developers · Vihitgaon Deolali, Nashik
Possession date of SAI PARK: 30 December 2026, moved from 30 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600022232, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAI PARK?
How the possession date of SAI PARK has moved
30 December 2025
Completion date given when the project was registered
30 December 2026
Extended at the builder's request (MahaRERA application EA26012619581)
Reason the builder gave MahaRERA: “LABOUR SHORTAGE”
Source: SAI PARK’s extension records on MahaRERA (P51600022232), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI PARK
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600022232
- Status
- Registered and active
- Builder
- Jay Developers
- Location
- Vihitgaon Deolali, Nashik · 422401
- Project type
- Residential / Group Housing
- Registered on
- 5 Sep 2019
- Completion date at registration
- December 2025
- Latest completion date
- December 2026
- Delay so far
- 12 months
- Homes
- 168
- Sold or booked
- 66%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 18
Construction progress of SAI PARK, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAI PARK-A | 100% | 100% | 100% | 100% |
| SAI PARK-B | 100% | 100% | 100% | 100% |
| SAI PARK-C | 100% | 100% | 100% | 90% |
| SAI PARK-D | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- SAI PARK-A: covers 7 floors
- SAI PARK-B: covers 7 floors
- SAI PARK-C: covers 7 floors
- SAI PARK-D: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI PARK every month.
SAI PARK: buildings, flats and land, as filed on MahaRERA
- Buildings: SAI PARK-A (7 floors, 42 units) · SAI PARK-B (7 floors, 42 units) · SAI PARK-C (7 floors, 42 units) · SAI PARK-D (8 floors, 42 units)
- Land: 5,200 sq m (about 1.3 acres) · sanctioned built-up 6,936 sq m · recreational space 426 sq m
- Boundaries filed include: VIHITGAON VADNERE ROAD
The builder’s record and reviews
Jay Developers (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 4 still being built, 2 past the promised date (typically 12 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of SAI PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI PARK: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI PARK
What is the possession date of SAI PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI PARK in Vihitgaon Deolali, Nashik is 30 December 2026 — 12 months later than 30 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SAI PARK?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI PARK's builder has filed on MahaRERA, the official one, is 30 December 2026, already 12 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAI PARK extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PARK's builder applied to MahaRERA to extend the completion date once: to 30 December 2026, giving the reason "LABOUR SHORTAGE".
What is the RERA number of SAI PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI PARK in Vihitgaon Deolali, Nashik is P51600022232.
Is SAI PARK registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PARK is registered as P51600022232 and its status is "Registered and active".
What is the construction status of SAI PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PARK's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does SAI PARK have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SAI PARK safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PARK is registered on MahaRERA as P51600022232, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAI PARK's possession date changes?
The latest dates are on SAI PARK's MahaRERA page (P51600022232). GharKundli's Kundli Watch sends a free WhatsApp update on SAI PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI PARK have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PARK has 4 buildings filed: SAI PARK-A with 7 floors and 42 units; SAI PARK-B with 7 floors and 42 units; SAI PARK-C with 7 floors and 42 units; SAI PARK-D with 8 floors and 42 units.
How big is the land of SAI PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PARK stands on 5,200 sq m of land (about 1.3 acres), with 6,936 sq m of sanctioned built-up area and 426 sq m of recreational open space.
What is the track record of SAI PARK's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Jay Developers (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 4 still being built, 2 past the promised date (typically 12 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SAI PARK?
Google Maps has reviews of SAI PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI PARK?
SAI PARK by Jay Developers is in Vihitgaon Deolali, Nashik (pincode 422401), Maharashtra, and is registered on MahaRERA as P51600022232, per GharKundli's check of MahaRERA records. Its boundaries filed there include VIHITGAON VADNERE ROAD.
How many homes are in SAI PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PARK has 168 homes in 4 towers registered on MahaRERA, and 66% of them are sold or booked.
When was SAI PARK registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PARK was registered on MahaRERA on 5 September 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI PARK?
No court cases are listed for SAI PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SAI PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Jay Developers, which has 18 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAI PARK
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Nashik →
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- YUNUS RESIDENCY
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- SHREE VISHVA
- SARA SERENITY APARTMENT
Other projects by Jay Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.