SAISHRUSHTI

by JAY DEVELOPERS · Sawarkar Nagar, NashikAlso near Serene Meadows, Anandwali

Possession date of SAISHRUSHTI: 29 February 2028, moved from 30 June 2023 (52 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600008058, and currently active. Its completion date has moved from June 2023 to February 2028: 52 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SAISHRUSHTI?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAISHRUSHTI has moved

  1. 30 June 2023

    Completion date given when the project was registered

  2. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51600017087)

    Reason the builder gave MahaRERA: “Due to the slack of workers in karona the possession is delayed.”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51600024223)

    Reason the builder gave MahaRERA: “DUE TO LABOUR SHORTAGE”
  4. 30 June 2026

    Extended at the builder's request (MahaRERA application EA07072501962)

    Reason the builder gave MahaRERA: “due to some technical reasons unable to get oc.”
  5. 31 October 2027

    Extended at the builder's request (MahaRERA application EA18082622175)

    Reason the builder gave MahaRERA: “DUE TO SOME TECHNICAL REASONS UNABLE TO GET OC FROM DEPARTMENT”
  6. 29 February 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SAISHRUSHTI’s extension records on MahaRERA (P51600008058), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAISHRUSHTI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the February 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600008058
Status
Registered and active
Builder
JAY DEVELOPERS
Location
Sawarkar Nagar, Nashik · 422013
Project type
Others
Registered on
18 Aug 2017
Completion date at registration
June 2023
Latest completion date
February 2028
Delay so far
52 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
104
Sold or booked
89%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
18

Construction progress of SAISHRUSHTI, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAISHRUSHTI A WING100%100%100%100%
SAISHRUSHTI B WING100%100%100%99%

Commencement certificate (CC), as filed on MahaRERA

  • SAISHRUSHTI A WING: covers 16 floors
  • SAISHRUSHTI B WING: covers 16 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAISHRUSHTI every month.

SAISHRUSHTI: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAISHRUSHTI A WING (16 floors, 64 units) · SAISHRUSHTI B WING (16 floors, 52 units)
  • Car parking: 2 covered, 134 open
  • Land: 3,595 sq m (about 0.9 acres) · sanctioned built-up 3,976 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

JAY Developers has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 31 months); 3 still being built, 1 past the promised date (typically 24 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of SAISHRUSHTI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAISHRUSHTI: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAISHRUSHTI

What is the possession date of SAISHRUSHTI?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAISHRUSHTI in Sawarkar Nagar, Nashik is 29 February 2028 — 52 months later than 30 June 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SAISHRUSHTI?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAISHRUSHTI's builder has filed on MahaRERA, the official one, is 29 February 2028, already 52 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAISHRUSHTI extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SAISHRUSHTI's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2024, giving the reason "Due to the slack of workers in karona the possession is delayed."; to 30 June 2025, giving the reason "DUE TO LABOUR SHORTAGE"; to 30 June 2026, giving the reason "due to some technical reasons unable to get oc."; to 31 October 2027, giving the reason "DUE TO SOME TECHNICAL REASONS UNABLE TO GET OC FROM DEPARTMENT". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SAISHRUSHTI?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAISHRUSHTI in Sawarkar Nagar, Nashik is P51600008058.

Is SAISHRUSHTI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAISHRUSHTI is registered as P51600008058 and its status is "Registered and active".

What is the construction status of SAISHRUSHTI?

According to GharKundli's check of MahaRERA records (updated October 2026), SAISHRUSHTI's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does SAISHRUSHTI have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SAISHRUSHTI safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SAISHRUSHTI is registered on MahaRERA as P51600008058, its completion date has moved 52 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAISHRUSHTI's possession date changes?

The latest dates are on SAISHRUSHTI's MahaRERA page (P51600008058). GharKundli's Kundli Watch sends a free WhatsApp update on SAISHRUSHTI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAISHRUSHTI have?

According to GharKundli's check of MahaRERA records (updated October 2026), SAISHRUSHTI has 2 buildings filed: SAISHRUSHTI A WING with 16 floors and 64 units; SAISHRUSHTI B WING with 16 floors and 52 units.

How much parking does SAISHRUSHTI have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 2 covered and 134 open car parking spaces for SAISHRUSHTI.

How big is the land of SAISHRUSHTI?

According to GharKundli's check of MahaRERA records (updated October 2026), SAISHRUSHTI stands on 3,595 sq m of land (about 0.9 acres), with 3,976 sq m of sanctioned built-up area.

What is the track record of SAISHRUSHTI's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), JAY Developers has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 31 months); 3 still being built, 1 past the promised date (typically 24 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAISHRUSHTI?

Google Maps has reviews of SAISHRUSHTI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAISHRUSHTI?

SAISHRUSHTI by JAY DEVELOPERS is in Sawarkar Nagar, Nashik (pincode 422013), near Serene Meadows, Anandwali, Maharashtra, and is registered on MahaRERA as P51600008058, per GharKundli's check of MahaRERA records.

How many homes are in SAISHRUSHTI?

According to GharKundli's check of MahaRERA records (updated October 2026), SAISHRUSHTI has 104 homes in 2 towers registered on MahaRERA, and 89% of them are sold or booked.

When was SAISHRUSHTI registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAISHRUSHTI was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SAISHRUSHTI?

No court cases are listed for SAISHRUSHTI on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SAISHRUSHTI?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JAY DEVELOPERS, which has 18 other projects registered on MahaRERA.

All projects with possession due in 2028 in Nashik →

Other projects in pincode 422013

All 120 projects in Sawarkar Nagar (422013) →

Other projects by JAY DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.