HAVELI
by DEVRAM PARVATRAO SATHE · Anandwali, Nashik
Possession date of HAVELI: 27 February 2027, moved from 27 October 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600030214, and currently active. Its completion date has moved from October 2025 to February 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about HAVELI?
How the possession date of HAVELI has moved
27 October 2025
Completion date given when the project was registered
27 October 2026
Extended at the builder's request (MahaRERA application EA13102518094)
Reason the builder gave MahaRERA:
“(a) Unavailability/Shortage of Labour: Movement restrictions and safety concerns led to a scarcity of skilled and unskilled labourers essential for project execution. Many workers from northern states took time to relocate and resume work.…” Read the full reason
“(a) Unavailability/Shortage of Labour: Movement restrictions and safety concerns led to a scarcity of skilled and unskilled labourers essential for project execution. Many workers from northern states took time to relocate and resume work. (b) Slow Progress of certain activities: Social distancing protocols and safety measures have inevitably slowed down the pace of certain construction tasks. (c) Suspension of the works: temporary halts in construction activities due to government directive and safety precautions have interrupted the project’s continuity. (d) Delay in supply of material an…”27 February 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: HAVELI’s extension records on MahaRERA (P51600030214), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on HAVELI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the February 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600030214
- Status
- Registered and active
- Builder
- DEVRAM PARVATRAO SATHE
- Location
- Anandwali, Nashik · 422013
- Project type
- Residential / Group Housing
- Registered on
- 5 Aug 2021
- Completion date at registration
- October 2025
- Latest completion date
- February 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 50
- Sold or booked
- 92%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of HAVELI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| HAVELI | 100% | 100% | 90% | 40% |
Commencement certificate (CC), as filed on MahaRERA
- HAVELI: covers 30 floors
Latest CC order on MahaRERA: dated 24/12/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on HAVELI every month.
HAVELI: buildings, flats and land, as filed on MahaRERA
- Buildings: HAVELI (30 floors, 50 units)
- Car parking: 80 covered, 73 open
- Land: 5,012 sq m (about 1.2 acres) · sanctioned built-up 15,931 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of HAVELI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
HAVELI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about HAVELI
What is the possession date of HAVELI?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HAVELI in Anandwali, Nashik is 27 February 2027 — 12 months later than 27 October 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for HAVELI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date HAVELI's builder has filed on MahaRERA, the official one, is 27 February 2027, already 12 months later than the 27 October 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of HAVELI extended?
According to GharKundli's check of MahaRERA records (updated October 2026), HAVELI's builder applied to MahaRERA to extend the completion date once: to 27 October 2026, giving the reason "(a) Unavailability/Shortage of Labour: Movement restrictions and safety concerns led to a scarcity of skilled and unskilled labourers essential for project execution. Many workers from northern states took time to relocate and resume work. (b) Slow Progress of certain activities: Social distancing protocols and safety measures have inevitably slowed down the pace of certain construction tasks. (c) Suspension of the works: temporary halts in construction activities due to government directive and safety precautions have interrupted the project’s continuity. (d) Delay in supply of material an…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of HAVELI?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HAVELI in Anandwali, Nashik is P51600030214.
Is HAVELI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HAVELI is registered as P51600030214 and its status is "Registered and active".
What is the construction status of HAVELI?
According to GharKundli's check of MahaRERA records (updated October 2026), HAVELI's status on MahaRERA is "Registered and active". As filed by the builder, slab work on HAVELI is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does HAVELI have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is HAVELI safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), HAVELI is registered on MahaRERA as P51600030214, its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if HAVELI's possession date changes?
The latest dates are on HAVELI's MahaRERA page (P51600030214). GharKundli's Kundli Watch sends a free WhatsApp update on HAVELI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does HAVELI have?
According to GharKundli's check of MahaRERA records (updated October 2026), HAVELI has one building filed: HAVELI with 30 floors and 50 units.
How much parking does HAVELI have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 80 covered and 73 open car parking spaces for HAVELI.
How big is the land of HAVELI?
According to GharKundli's check of MahaRERA records (updated October 2026), HAVELI stands on 5,012 sq m of land (about 1.2 acres), with 15,931 sq m of sanctioned built-up area.
Where can I read reviews of HAVELI?
Google Maps has reviews of HAVELI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is HAVELI?
HAVELI by DEVRAM PARVATRAO SATHE is in Anandwali, Nashik (pincode 422013), Maharashtra, and is registered on MahaRERA as P51600030214, per GharKundli's check of MahaRERA records.
How many homes are in HAVELI?
According to GharKundli's check of MahaRERA records (updated October 2026), HAVELI has 50 homes in 1 tower registered on MahaRERA, and 92% of them are sold or booked.
When was HAVELI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HAVELI was registered on MahaRERA on 5 August 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on HAVELI?
1 court case is listed for HAVELI on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of HAVELI?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DEVRAM PARVATRAO SATHE.
Check it yourself on MahaRERA
- How to check the possession date of HAVELI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nashik →
Other projects in Nashik
- SAINATH HEIGHTS
- Fortunes Emerald Park
- Laxmi Commercial Complex
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- YUNUS RESIDENCY
- SHREE VISHVA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.