Yashoda Miracle
by Pawar Properties · Rathi Amrai, NashikAlso near Panchavati, Dwarka, Indira Nagar
Possession date of Yashoda Miracle: 25 March 2027, moved from 31 March 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600049152, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Yashoda Miracle?
How the possession date of Yashoda Miracle has moved
31 March 2026
Completion date given when the project was registered
25 March 2027
Extended at the builder's request (MahaRERA application EA30032620440)
Reason the builder gave MahaRERA: “Our Project is delayed due to slow regulatory approvals, labour shortages, and material price surges”
Source: Yashoda Miracle’s extension records on MahaRERA (P51600049152), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Yashoda Miracle
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600049152
- Status
- Registered and active
- Builder
- Pawar Properties
- Location
- Rathi Amrai, Nashik · 422013
- Project type
- Residential / Group Housing
- Registered on
- 1 Feb 2023
- Completion date at registration
- March 2026
- Latest completion date
- March 2027
- Delay so far
- 12 months
- Homes
- 13
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Yashoda Miracle, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Yashoda Miracle | 100% | 95% | 90% | 91% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Yashoda Miracle every month.
Yashoda Miracle: buildings, flats and land, as filed on MahaRERA
- Buildings: Yashoda Miracle (14 floors, 13 units)
- Car parking: 34 open
- Land: 789 sq m (about 0.2 acres) · sanctioned built-up 3,205 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Anubhooti Infrastructures (a group of 2 linked companies) has 5 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 3 months late). No complaints on MahaRERA.
Read Google reviews of Yashoda Miracle →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Yashoda Miracle: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Yashoda Miracle
What is the possession date of Yashoda Miracle?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Yashoda Miracle in Rathi Amrai, Nashik is 25 March 2027 — 12 months later than 31 March 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Yashoda Miracle?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Yashoda Miracle's builder has filed on MahaRERA, the official one, is 25 March 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Yashoda Miracle extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Yashoda Miracle's builder applied to MahaRERA to extend the completion date once: to 25 March 2027, giving the reason "Our Project is delayed due to slow regulatory approvals, labour shortages, and material price surges".
What is the RERA number of Yashoda Miracle?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Yashoda Miracle in Rathi Amrai, Nashik is P51600049152.
Is Yashoda Miracle registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Yashoda Miracle is registered as P51600049152 and its status is "Registered and active".
What is the construction status of Yashoda Miracle?
According to GharKundli's check of MahaRERA records (updated October 2026), Yashoda Miracle's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Yashoda Miracle is 95% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does Yashoda Miracle have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Yashoda Miracle safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Yashoda Miracle is registered on MahaRERA as P51600049152, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Yashoda Miracle's possession date changes?
The latest dates are on Yashoda Miracle's MahaRERA page (P51600049152). GharKundli's Kundli Watch sends a free WhatsApp update on Yashoda Miracle every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Yashoda Miracle have?
According to GharKundli's check of MahaRERA records (updated October 2026), Yashoda Miracle has one building filed: Yashoda Miracle with 14 floors and 13 units.
How much parking does Yashoda Miracle have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 34 open car parking spaces for Yashoda Miracle.
How big is the land of Yashoda Miracle?
According to GharKundli's check of MahaRERA records (updated October 2026), Yashoda Miracle stands on 789 sq m of land (about 0.2 acres), with 3,205 sq m of sanctioned built-up area.
What is the track record of Yashoda Miracle's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Anubhooti Infrastructures (a group of 2 linked companies) has 5 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 3 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Yashoda Miracle?
Google Maps has reviews of Yashoda Miracle written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Yashoda Miracle?
Yashoda Miracle by Pawar Properties is in Rathi Amrai, Nashik (pincode 422013), near Panchavati, Dwarka, Indira Nagar, Maharashtra, and is registered on MahaRERA as P51600049152, per GharKundli's check of MahaRERA records.
How many homes are in Yashoda Miracle?
According to GharKundli's check of MahaRERA records (updated October 2026), Yashoda Miracle has 13 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Yashoda Miracle registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Yashoda Miracle was registered on MahaRERA on 1 February 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Yashoda Miracle?
No court cases are listed for Yashoda Miracle on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Yashoda Miracle?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pawar Properties.
Check it yourself on MahaRERA
- How to check the possession date of Yashoda Miracle
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nashik →
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- YUNUS RESIDENCY
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- SHREE VISHVA
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- SARA SERENITY APARTMENT
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.