SHREE HARIKRUSHNA HEIGHTS
by PARSHWANTH PROJECTS · Indra Nagar, Nashik
Possession date of SHREE HARIKRUSHNA HEIGHTS: 1 June 2027, moved from 31 August 2023 (42 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600026379, and currently active. Its completion date has moved from August 2023 to June 2027: 42 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SHREE HARIKRUSHNA HEIGHTS?
How the possession date of SHREE HARIKRUSHNA HEIGHTS has moved
31 August 2023
Completion date given when the project was registered
30 August 2024
Extended at the builder's request (MahaRERA application EXT51600009560)
Reason the builder gave MahaRERA: “DUE TO COVID19 WORK WILL BE COMPLETED BY DELAY”
1 February 2027
Extended at the builder's request (MahaRERA application EXT51600017995)
Reason the builder gave MahaRERA: “PROJECT EXPIRY DATE SHOWN 28/02/2025 THEREFORE THIS IS SUFFICENT TIME FOR COMPLETION OF THE PROJECT”
1 June 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHREE HARIKRUSHNA HEIGHTS’s extension records on MahaRERA (P51600026379), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHREE HARIKRUSHNA HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600026379
- Status
- Registered and active
- Builder
- PARSHWANTH PROJECTS
- Location
- Indra Nagar, Nashik · 422006
- Project type
- Residential / Group Housing
- Registered on
- 16 Sep 2020
- Completion date at registration
- August 2023
- Latest completion date
- June 2027
- Delay so far
- 42 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 299
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHREE HARIKRUSHNA HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING C RESIDENITAL | 100% | 100% | 100% | 85% |
| WING A RESIDENITAL AND COMMERICAL | 100% | 68% | 47% | 0% |
| WING B RESIDENITAL AND COMMERCIAL | 100% | 100% | 100% | 85% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE HARIKRUSHNA HEIGHTS every month.
SHREE HARIKRUSHNA HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: WING C RESIDENITAL (17 floors) · WING A RESIDENITAL AND COMMERICAL (21 floors) · WING B RESIDENITAL AND COMMERCIAL (17 floors)
- Land: 8,700 sq m (about 2.1 acres) · sanctioned built-up 8,700 sq m · recreational space 870 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHREE HARIKRUSHNA HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHREE HARIKRUSHNA HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHREE HARIKRUSHNA HEIGHTS
What is the possession date of SHREE HARIKRUSHNA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHREE HARIKRUSHNA HEIGHTS in Indra Nagar, Nashik is 1 June 2027 — 42 months later than 31 August 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHREE HARIKRUSHNA HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE HARIKRUSHNA HEIGHTS's builder has filed on MahaRERA, the official one, is 1 June 2027, already 42 months later than the 31 August 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHREE HARIKRUSHNA HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE HARIKRUSHNA HEIGHTS's builder applied to MahaRERA to extend the completion date 2 times: to 30 August 2024, giving the reason "DUE TO COVID19 WORK WILL BE COMPLETED BY DELAY"; to 1 February 2027, giving the reason "PROJECT EXPIRY DATE SHOWN 28/02/2025 THEREFORE THIS IS SUFFICENT TIME FOR COMPLETION OF THE PROJECT". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SHREE HARIKRUSHNA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHREE HARIKRUSHNA HEIGHTS in Indra Nagar, Nashik is P51600026379.
Is SHREE HARIKRUSHNA HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE HARIKRUSHNA HEIGHTS is registered as P51600026379 and its status is "Registered and active".
What is the construction status of SHREE HARIKRUSHNA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE HARIKRUSHNA HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 68% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does SHREE HARIKRUSHNA HEIGHTS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SHREE HARIKRUSHNA HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE HARIKRUSHNA HEIGHTS is registered on MahaRERA as P51600026379, its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHREE HARIKRUSHNA HEIGHTS's possession date changes?
The latest dates are on SHREE HARIKRUSHNA HEIGHTS's MahaRERA page (P51600026379). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE HARIKRUSHNA HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHREE HARIKRUSHNA HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE HARIKRUSHNA HEIGHTS has 3 buildings filed: WING C RESIDENITAL with 17 floors; WING A RESIDENITAL AND COMMERICAL with 21 floors; WING B RESIDENITAL AND COMMERCIAL with 17 floors.
How big is the land of SHREE HARIKRUSHNA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE HARIKRUSHNA HEIGHTS stands on 8,700 sq m of land (about 2.1 acres), with 8,700 sq m of sanctioned built-up area and 870 sq m of recreational open space.
Where can I read reviews of SHREE HARIKRUSHNA HEIGHTS?
Google Maps has reviews of SHREE HARIKRUSHNA HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHREE HARIKRUSHNA HEIGHTS?
SHREE HARIKRUSHNA HEIGHTS by PARSHWANTH PROJECTS is in Indra Nagar, Nashik (pincode 422006), Maharashtra, and is registered on MahaRERA as P51600026379, per GharKundli's check of MahaRERA records.
How many homes are in SHREE HARIKRUSHNA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE HARIKRUSHNA HEIGHTS has 299 homes in 3 towers registered on MahaRERA.
When was SHREE HARIKRUSHNA HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE HARIKRUSHNA HEIGHTS was registered on MahaRERA on 16 September 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on SHREE HARIKRUSHNA HEIGHTS?
No court cases are listed for SHREE HARIKRUSHNA HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SHREE HARIKRUSHNA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PARSHWANTH PROJECTS.
Check it yourself on MahaRERA
- How to check the possession date of SHREE HARIKRUSHNA HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nashik →
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- YUNUS RESIDENCY
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- SHREE VISHVA
- SARA SERENITY APARTMENT
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.