What’s in the report? →Possession date of Kshitij Villa (MahaRERA P51800011141): 30 April 2029, moved from 30 December 2021 (84 months later). It has 18 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800011141, and currently active. Its completion date has moved from December 2021 to April 2029: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800011141, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Kshitij Villa?
11 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Kshitij Villa has moved
30 December 2021
Completion date given when the project was registered
31 December 2028
Extended at the builder's request (MahaRERA application EXT51800018301)
Reason the builder gave MahaRERA: “As per the attachment”
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Kshitij Villa’s extension records on MahaRERA (P51800011141), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kshitij Villa
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 11 court cases, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800011141
- Status
- Registered and active
- Builder
- KESARI HARIDAS MALI
- Location
- Haridas Nagar, Mumbai · 400092
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- April 2029
- Delay so far
- 84 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 18
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 11
- Title report on file
- Not found
Construction progress of Kshitij Villa, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KSHITIJ VILLA | 100% | 69% | 37% | 47% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kshitij Villa every 1–2 months.
Kshitij Villa: buildings, flats and land, as filed on MahaRERA
- Buildings: KSHITIJ VILLA (12 floors)
- Land: 542 sq m (about 0.1 acres) · sanctioned built-up 589 sq m
- Boundaries filed include: 1ST ROAD TPS III, 7TH ROAD TPS III
- Land, as filed: 659
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Kshitij Villa →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kshitij Villa: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Kshitij Villa
What is the possession date of Kshitij Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kshitij Villa in Haridas Nagar, Mumbai is 30 April 2029 — 84 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 84 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Kshitij Villa?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kshitij Villa's builder has filed on MahaRERA, the official one, is 30 April 2029, already 84 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kshitij Villa extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Kshitij Villa's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "As per the attachment". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Kshitij Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kshitij Villa in Haridas Nagar, Mumbai is P51800011141.
Is Kshitij Villa registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kshitij Villa is registered as P51800011141 and its status is "Registered and active".
What is the current construction status of Kshitij Villa? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Kshitij Villa's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KSHITIJ VILLA is 69% done and internal work 37%. GharKundli's full report compares construction progress with the deadline.
Does Kshitij Villa have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Kshitij Villa safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kshitij Villa is registered on MahaRERA as P51800011141, its completion date has moved 84 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Kshitij Villa?
Kshitij Villa is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Kshitij Villa?
For a flat in Kshitij Villa (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Kshitij Villa received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kshitij Villa is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Kshitij Villa uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kshitij Villa was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Kshitij Villa's possession date changes?
The latest dates are on Kshitij Villa's MahaRERA page (P51800011141). GharKundli's Kundli Watch sends a free WhatsApp update on Kshitij Villa every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kshitij Villa have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kshitij Villa has one building filed: KSHITIJ VILLA with 12 floors.
How big is the land of Kshitij Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), Kshitij Villa stands on 542 sq m of land (about 0.1 acres), with 589 sq m of sanctioned built-up area.
What are the reviews of Kshitij Villa?
Google Maps has reviews of Kshitij Villa written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Kshitij Villa?
Kshitij Villa by KESARI HARIDAS MALI is in Haridas Nagar, Mumbai, pincode 400092 (near Borivali West, Lower Parel, Babhai Naka), Maharashtra, and is registered on MahaRERA as P51800011141, per GharKundli's check of MahaRERA records. Its boundaries filed there include 1ST ROAD TPS III, 7TH ROAD TPS III. Its land is filed as 659. GharKundli lists all 362 MahaRERA projects in Borivali West (400092).
How many flats are in Kshitij Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), Kshitij Villa has 18 homes in 1 tower registered on MahaRERA.
When was Kshitij Villa registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kshitij Villa was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Does Kshitij Villa have any legal issues or court cases?
11 court cases are listed for Kshitij Villa on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Kshitij Villa?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KESARI HARIDAS MALI.
Check it yourself on MahaRERA
- How to check the possession date of Kshitij Villa
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in Borivali
- Victory Arch
- Gokul Heights
- Saffronwoods CHSL
- Parshuram Heights
- L&T Realty Ahana Tower A
- L&T Realty Ahana Tower B
- Avirahi Elegance
- Rashmi Icon
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.