Mangalam Royal Residency

by MANGALAM DEVELOPERS · Wadala, Nashik 422010Registered on MahaRERA as “ROYAL RESIDENCY”

What’s in the report? →

Possession date of Mangalam Royal Residency (MahaRERA P51600027515): 30 December 2023, and it has already passed. It has 52 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600027515. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51600027515, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about Mangalam Royal Residency?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Mangalam Royal Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600027515
Status
Lapsed (registration period ended)
Builder
MANGALAM DEVELOPERS
Location
Wadala, Nashik · 422010
Project type
Others
Registered on
14 Dec 2020
Completion date at registration
December 2023
Latest completion date
December 2023
Homes
52
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Mangalam Royal Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A WING0%0%0%0%
B WING0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mangalam Royal Residency every 1–2 months.

Mangalam Royal Residency: buildings, flats and land, as filed on MahaRERA

  • Buildings: A WING (6 floors) · B WING (6 floors)
  • Land: 967 sq m (about 0.2 acres) · sanctioned built-up 1,828 sq m
  • Map: Get directions

The builder’s record and reviews

Mangalam Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Mangalam Royal Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mangalam Royal Residency: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Mangalam Royal Residency

What is the possession date of Mangalam Royal Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mangalam Royal Residency in Wadala, Nashik is 30 December 2023. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Mangalam Royal Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mangalam Royal Residency's builder has filed on MahaRERA, the official one, is 30 December 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Mangalam Royal Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mangalam Royal Residency in Wadala, Nashik is P51600027515.

Is Mangalam Royal Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalam Royal Residency is registered as P51600027515 and its status is "Lapsed (registration period ended)".

What is the current construction status of Mangalam Royal Residency? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalam Royal Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Mangalam Royal Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Mangalam Royal Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalam Royal Residency is registered on MahaRERA as P51600027515, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Mangalam Royal Residency?

Mangalam Royal Residency isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Mangalam Royal Residency?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Mangalam Royal Residency: gharkundli.com/tools/property-cost-calculator

Has Mangalam Royal Residency received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Mangalam Royal Residency isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Mangalam Royal Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalam Royal Residency's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Mangalam Royal Residency uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Mangalam Royal Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Mangalam Royal Residency's possession date changes?

The latest dates are on Mangalam Royal Residency's MahaRERA page (P51600027515). GharKundli's Kundli Watch sends a free WhatsApp update on Mangalam Royal Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mangalam Royal Residency have?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalam Royal Residency has 2 buildings filed: A WING with 6 floors; B WING with 6 floors.

How big is the land of Mangalam Royal Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalam Royal Residency stands on 967 sq m of land (about 0.2 acres), with 1,828 sq m of sanctioned built-up area.

What is the track record of Mangalam Royal Residency's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalam Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Mangalam Royal Residency?

Google Maps has reviews of Mangalam Royal Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Mangalam Royal Residency?

Mangalam Royal Residency by MANGALAM DEVELOPERS is in Wadala, Nashik, pincode 422010, Maharashtra, and is registered on MahaRERA as P51600027515, per GharKundli's check of MahaRERA records. GharKundli lists all 462 MahaRERA projects in Ambad (422010).

How many flats are in Mangalam Royal Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalam Royal Residency has 52 homes in 2 towers registered on MahaRERA.

When was Mangalam Royal Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalam Royal Residency was registered on MahaRERA on 14 December 2020. GharKundli did not find a title report on the land on file there.

Does Mangalam Royal Residency have any legal issues or court cases?

No court cases are listed for Mangalam Royal Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Mangalam Royal Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MANGALAM DEVELOPERS, which has 2 other projects registered on MahaRERA.

Other projects in Ambad (422010)

All 462 projects in Ambad (422010) →

Other projects by MANGALAM DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.