ABH CAPITAL PHASE II

by TANU REALITY LLP · Tilakwadi, Nashik

Possession: ABH CAPITAL PHASE II is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600028514. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about ABH CAPITAL PHASE II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ABH CAPITAL PHASE II has moved

  1. 30 March 2023

    Completion date given when the project was registered

  2. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51600016520)

    Reason the builder gave MahaRERA: “The extended rains, that made it difficult to carry out and interrupted construction activities, caused a significant delay in completion of our project.”

Source: ABH CAPITAL PHASE II’s extension records on MahaRERA (P51600028514), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ABH CAPITAL PHASE II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51600028514
Status
Completed
Builder
TANU REALITY LLP
Location
Tilakwadi, Nashik · 422002
Project type
Commercial
Registered on
8 Mar 2021
Completion date at registration
March 2023
Latest completion date
December 2023
Delay so far
9 months
Homes
56
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of ABH CAPITAL PHASE II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING B100%100%70%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ABH CAPITAL PHASE II every month.

ABH CAPITAL PHASE II: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING B (10 floors)
  • Land: 635 sq m (about 0.2 acres) · sanctioned built-up 3,357 sq m

The builder’s record and reviews

ABH Developers (a group of 2 linked companies) has 14 projects on MahaRERA since 2020, this one included. Of the 8 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 6 months); 2 still being built, 2 past the promised date (typically 12 months late); 1 lapsed. 4 complaints on MahaRERA across 2 projects.

Read Google reviews of ABH CAPITAL PHASE II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ABH CAPITAL PHASE II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ABH CAPITAL PHASE II

What is the possession date of ABH CAPITAL PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ABH CAPITAL PHASE II in Tilakwadi, Nashik is 31 December 2023 — 9 months later than 30 March 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for ABH CAPITAL PHASE II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ABH CAPITAL PHASE II's builder has filed on MahaRERA, the official one, is 31 December 2023, already 9 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ABH CAPITAL PHASE II extended?

According to GharKundli's check of MahaRERA records (updated November 2026), ABH CAPITAL PHASE II's builder applied to MahaRERA to extend the completion date once: to 31 December 2023, giving the reason "The extended rains, that made it difficult to carry out and interrupted construction activities, caused a significant delay in completion of our project.".

What is the RERA number of ABH CAPITAL PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ABH CAPITAL PHASE II in Tilakwadi, Nashik is P51600028514.

Is ABH CAPITAL PHASE II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ABH CAPITAL PHASE II is registered as P51600028514 and its status is "Completed".

What is the construction status of ABH CAPITAL PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), ABH CAPITAL PHASE II's status on MahaRERA is "Completed". As filed by the builder, slab work on WING B is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does ABH CAPITAL PHASE II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is ABH CAPITAL PHASE II safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), ABH CAPITAL PHASE II is registered on MahaRERA as P51600028514, its MahaRERA status is "Completed", its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does ABH CAPITAL PHASE II have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: ABH CAPITAL PHASE I (P51600027827). Check that your agreement names the registration of your own wing.

How can I get updates if ABH CAPITAL PHASE II's possession date changes?

The latest dates are on ABH CAPITAL PHASE II's MahaRERA page (P51600028514). GharKundli's Kundli Watch sends a free WhatsApp update on ABH CAPITAL PHASE II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ABH CAPITAL PHASE II have?

According to GharKundli's check of MahaRERA records (updated November 2026), ABH CAPITAL PHASE II has one building filed: WING B with 10 floors.

How big is the land of ABH CAPITAL PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), ABH CAPITAL PHASE II stands on 635 sq m of land (about 0.2 acres), with 3,357 sq m of sanctioned built-up area.

What is the track record of ABH CAPITAL PHASE II's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), ABH Developers (a group of 2 linked companies) has 14 projects on MahaRERA since 2020, this one included. Of the 8 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 6 months); 2 still being built, 2 past the promised date (typically 12 months late); 1 lapsed. 4 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ABH CAPITAL PHASE II?

Google Maps has reviews of ABH CAPITAL PHASE II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ABH CAPITAL PHASE II?

ABH CAPITAL PHASE II by TANU REALITY LLP is in Tilakwadi, Nashik (pincode 422002), Maharashtra, and is registered on MahaRERA as P51600028514, per GharKundli's check of MahaRERA records.

How many homes are in ABH CAPITAL PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), ABH CAPITAL PHASE II has 56 homes in 1 tower registered on MahaRERA.

When was ABH CAPITAL PHASE II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ABH CAPITAL PHASE II was registered on MahaRERA on 8 March 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on ABH CAPITAL PHASE II?

No court cases are listed for ABH CAPITAL PHASE II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of ABH CAPITAL PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is TANU REALITY LLP, which has 6 other projects registered on MahaRERA.

Other projects in Nashik

All 53 projects in Gole Colony (422002) →

Other projects by TANU REALITY LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.