Skip to content
GharKundli

Shyam Aangan

by MAA BUILDWELL · Behind Market Committee, Nashik 422003

What’s in the report? →

Possession date of Shyam Aangan (MahaRERA P51600029963): 1 July 2024, and it has already passed. It has 33 homes, 86% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600029963. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51600029963, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (July 2024) has passed.

What do you want to know about Shyam Aangan?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Shyam Aangan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600029963
Status
Lapsed (registration period ended)
Builder
MAA BUILDWELL
Location
Behind Market Committee, Nashik · 422003
Project type
Residential / Group Housing
Registered on
18 Jul 2021
Completion date at registration
July 2024
Homes
33
Sold or booked
86%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Shyam Aangan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHYAM AANGAN0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • SHYAM AANGAN: covers 10 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shyam Aangan every 1–2 months.

Shyam Aangan: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHYAM AANGAN (10 floors, 42 units)
  • Land: 833 sq m (about 0.2 acres) · sanctioned built-up 2,956 sq m
  • Land, as filed: SURVEY NO 72/2/30 PLOT NO 30 NASHIK SHIWAR
  • Map: Get directions

The builder’s record and reviews

Maa Buildwell has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 39 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Shyam Aangan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shyam Aangan: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shyam Aangan

What is the possession date of Shyam Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shyam Aangan in Behind Market Committee, Nashik is 1 July 2024. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Shyam Aangan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shyam Aangan's builder has filed on MahaRERA, the official one, is 1 July 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shyam Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shyam Aangan in Behind Market Committee, Nashik is P51600029963.

Is Shyam Aangan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shyam Aangan is registered as P51600029963 and its status is "Lapsed (registration period ended)".

What is the current construction status of Shyam Aangan? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Shyam Aangan's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHYAM AANGAN is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Shyam Aangan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Shyam Aangan safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Shyam Aangan is registered on MahaRERA as P51600029963, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shyam Aangan?

Shyam Aangan isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shyam Aangan?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shyam Aangan: gharkundli.com/tools/property-cost-calculator

Has Shyam Aangan received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Shyam Aangan isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 1 July 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Shyam Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), Shyam Aangan's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (1 July 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Shyam Aangan uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Shyam Aangan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shyam Aangan's possession date changes?

The latest dates are on Shyam Aangan's MahaRERA page (P51600029963). GharKundli's Kundli Watch sends a free WhatsApp update on Shyam Aangan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shyam Aangan have?

According to GharKundli's check of MahaRERA records (updated November 2026), Shyam Aangan has one building filed: SHYAM AANGAN with 10 floors and 42 units.

How big is the land of Shyam Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), Shyam Aangan stands on 833 sq m of land (about 0.2 acres), with 2,956 sq m of sanctioned built-up area.

What is the track record of Shyam Aangan's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Maa Buildwell has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 39 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shyam Aangan?

Google Maps has reviews of Shyam Aangan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shyam Aangan?

Shyam Aangan by MAA BUILDWELL is in Behind Market Committee, Nashik, pincode 422003, Maharashtra, and is registered on MahaRERA as P51600029963, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 72/2/30 PLOT NO 30 NASHIK SHIWAR. GharKundli lists all 735 MahaRERA projects in Panchvati (422003).

How many flats are in Shyam Aangan, and how many are sold?

According to GharKundli's check of MahaRERA records (updated November 2026), Shyam Aangan has 33 homes in 1 tower registered on MahaRERA, and 86% of them are sold or booked.

When was Shyam Aangan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shyam Aangan was registered on MahaRERA on 18 July 2021. GharKundli did not find a title report on the land on file there.

Does Shyam Aangan have any legal issues or court cases?

No court cases are listed for Shyam Aangan on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Shyam Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAA BUILDWELL, which has 3 other projects registered on MahaRERA.

Other projects in Nashik

All 735 projects in Panchvati (422003) →

Other projects by MAA BUILDWELL

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.