BENCHMARK PLAZA

by BENCHMARK PROJECTS PVT LTD · Khar West, MumbaiAlso near Bandra West, Bandra East, Nirmal Nagar

Possession date of BENCHMARK PLAZA: 30 April 2027, moved from 31 December 2019 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800006237, and currently active. Its completion date has moved from December 2019 to April 2027: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 7 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about BENCHMARK PLAZA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of BENCHMARK PLAZA has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT51800005523)

    Reason the builder gave MahaRERA: “Conflict between DCR 1991 and DCR 2034. Previously consumed .20 fungible FSI. Now claiming additional .35 fungible. Need extension for constructing additional area.”
  3. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51800009915)

    Reason the builder gave MahaRERA:
    “Construction work had stopped due to COVID-19 restrictions, which resulted in delays in approvals and also shortage of labour. Approvals are now in place from the MCCGM. We need additional time to mobilise labour to finish construction.As p…” Read the full reason“Construction work had stopped due to COVID-19 restrictions, which resulted in delays in approvals and also shortage of labour. Approvals are now in place from the MCCGM. We need additional time to mobilise labour to finish construction.As per Circular 28, we had already uploaded the Consent of the Allottees (Form "B") on 30 June 2021. However, we received an email from the scrutiny department of MahaRERA asking us to submit Form B. We are once again uploading Form"B".”
  4. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51800013174)

    Reason the builder gave MahaRERA:
    “The amended plans have been approved by authority, we had constraints to fit a functional parking tower in our project and now we been able to finally accommodate a workable parking system. Since this is fully customized, it will take some…” Read the full reason“The amended plans have been approved by authority, we had constraints to fit a functional parking tower in our project and now we been able to finally accommodate a workable parking system. Since this is fully customized, it will take some months for production, delivery and installation, hence we request MahaRERA to provide us extension until December 30, 2023.”
  5. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800019412)

    Reason the builder gave MahaRERA: “Parking tower issues due to space constraints has caused the delay. We are working with our consultants on rectifying it.”
  6. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800027238)

    Reason the builder gave MahaRERA:
    “"The parking tower needs to be redesigned. The required number of parking spaces, combined with land space constraints, has led to significant revisions in the parking design, which has affected the project timeline. We are working to final…” Read the full reason“"The parking tower needs to be redesigned. The required number of parking spaces, combined with land space constraints, has led to significant revisions in the parking design, which has affected the project timeline. We are working to finalize the updated plans, and we kindly request your understanding and approval of an extension to accommodate these adjustments."”
  7. 31 December 2026

    Extended at the builder's request (MahaRERA application EA19012619504)

    Reason the builder gave MahaRERA:
    “During the detailed technical review, it was observed that the existing configuration of the parking tower does not fully comply with the statutory requirements for parking capacity and safety standards. Rectifying this issue requires the s…” Read the full reason“During the detailed technical review, it was observed that the existing configuration of the parking tower does not fully comply with the statutory requirements for parking capacity and safety standards. Rectifying this issue requires the selection of a new vendor with the capability to implement the revised design, ensuring compliance with all applicable regulatory and safety norms. We are actively evaluating and finalizing suitable vendors and expect to commence construction of the revised parking structure shortly after completion of the vendor selection process. This process has resulte…”
  8. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: BENCHMARK PLAZA’s extension records on MahaRERA (P51800006237), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on BENCHMARK PLAZA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 7 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800006237
Status
Registered and active
Builder
BENCHMARK PROJECTS PVT LTD
Location
Khar West, Mumbai · 400052
Project type
Commercial
Registered on
14 Aug 2017
Completion date at registration
December 2019
Latest completion date
April 2027
Delay so far
84 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
50%
Towers
1
Complaints on MahaRERA
7
Court cases listed
0
Title report on file
Not found

Construction progress of BENCHMARK PLAZA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BENCHMARK PLAZA100%88%98%81%

Commencement certificate (CC), as filed on MahaRERA

  • BENCHMARK PLAZA: covers Up to Top of 7th Floor (pt) Including LMR+ OHT

Want to know when this changes? Kundli Watch sends a free WhatsApp update on BENCHMARK PLAZA every month.

BENCHMARK PLAZA: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space270 – 56037
Shops791 – 8902
1 BHK3791

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of BENCHMARK PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

BENCHMARK PLAZA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about BENCHMARK PLAZA

What is the possession date of BENCHMARK PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BENCHMARK PLAZA in Khar West, Mumbai is 30 April 2027 — 84 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for BENCHMARK PLAZA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date BENCHMARK PLAZA's builder has filed on MahaRERA, the official one, is 30 April 2027, already 84 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of BENCHMARK PLAZA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), BENCHMARK PLAZA's builder applied to MahaRERA to extend the completion date 6 times: to 30 December 2020, giving the reason "Conflict between DCR 1991 and DCR 2034. Previously consumed .20 fungible FSI. Now claiming additional .35 fungible. Need extension for constructing additional area."; to 30 June 2022, giving the reason "Construction work had stopped due to COVID-19 restrictions, which resulted in delays in approvals and also shortage of labour. Approvals are now in place from the MCCGM. We need additional time to mobilise labour to finish construction.As per Circular 28, we had already uploaded the Consent of the Allottees (Form "B") on 30 June 2021. However, we received an email from the scrutiny department of MahaRERA asking us to submit Form B. We are once again uploading Form"B"."; to 30 December 2023, giving the reason "The amended plans have been approved by authority, we had constraints to fit a functional parking tower in our project and now we been able to finally accommodate a workable parking system. Since this is fully customized, it will take some months for production, delivery and installation, hence we request MahaRERA to provide us extension until December 30, 2023."; to 31 December 2024, giving the reason "Parking tower issues due to space constraints has caused the delay. We are working with our consultants on rectifying it."; to 31 December 2025, giving the reason ""The parking tower needs to be redesigned. The required number of parking spaces, combined with land space constraints, has led to significant revisions in the parking design, which has affected the project timeline. We are working to finalize the updated plans, and we kindly request your understanding and approval of an extension to accommodate these adjustments.""; to 31 December 2026, giving the reason "During the detailed technical review, it was observed that the existing configuration of the parking tower does not fully comply with the statutory requirements for parking capacity and safety standards. Rectifying this issue requires the selection of a new vendor with the capability to implement the revised design, ensuring compliance with all applicable regulatory and safety norms. We are actively evaluating and finalizing suitable vendors and expect to commence construction of the revised parking structure shortly after completion of the vendor selection process. This process has resulte…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of BENCHMARK PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of BENCHMARK PLAZA in Khar West, Mumbai is P51800006237.

Is BENCHMARK PLAZA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), BENCHMARK PLAZA is registered as P51800006237 and its status is "Registered and active".

What is the construction status of BENCHMARK PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), BENCHMARK PLAZA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BENCHMARK PLAZA is 88% done and internal work 98%. GharKundli's full report compares construction progress with the deadline.

Does BENCHMARK PLAZA have complaints on MahaRERA?

7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is BENCHMARK PLAZA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), BENCHMARK PLAZA is registered on MahaRERA as P51800006237, its completion date has moved 84 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if BENCHMARK PLAZA's possession date changes?

The latest dates are on BENCHMARK PLAZA's MahaRERA page (P51800006237). GharKundli's Kundli Watch sends a free WhatsApp update on BENCHMARK PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does BENCHMARK PLAZA have?

According to GharKundli's check of MahaRERA records (updated October 2026), BENCHMARK PLAZA has one building filed: BENCHMARK PLAZA with 9 floors and 40 units.

How much parking does BENCHMARK PLAZA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 8 open car parking spaces for BENCHMARK PLAZA.

How big is the land of BENCHMARK PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), BENCHMARK PLAZA stands on 669 sq m of land (about 0.2 acres), with 1,468 sq m of sanctioned built-up area.

Where can I read reviews of BENCHMARK PLAZA?

Google Maps has reviews of BENCHMARK PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is BENCHMARK PLAZA?

BENCHMARK PLAZA by BENCHMARK PROJECTS PVT LTD is in Khar West, Mumbai (pincode 400052), near Bandra West, Bandra East, Nirmal Nagar, Maharashtra, and is registered on MahaRERA as P51800006237, per GharKundli's check of MahaRERA records.

How many homes are in BENCHMARK PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), BENCHMARK PLAZA has 0 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.

When was BENCHMARK PLAZA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), BENCHMARK PLAZA was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on BENCHMARK PLAZA?

No court cases are listed for BENCHMARK PLAZA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of BENCHMARK PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BENCHMARK PROJECTS PVT LTD.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400052

All 129 projects in Khar West (400052) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.