by Meghvarnam Realty Private Limited · Fort, Mumbai

Possession date of AMRUT TARA: 30 March 2027, moved from 31 December 2019 (83 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800009896, and currently active. Its completion date has moved from December 2019 to March 2027: 83 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AMRUT TARA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AMRUT TARA has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51800024701)

    Reason the builder gave MahaRERA: “Liquidity Management Issue”
  3. 30 November 2026

    Extended at the builder's request (MahaRERA application EA31082622424)

    Reason the builder gave MahaRERA:
    “We have already uploaded the Full Occupancy Certificate dated 28th April 2025 on the MahaRERA portal for your kind reference. However, the project is currently reflecting under the category of “Lapsed Projects.” In this regard, we request y…” Read the full reason“We have already uploaded the Full Occupancy Certificate dated 28th April 2025 on the MahaRERA portal for your kind reference. However, the project is currently reflecting under the category of “Lapsed Projects.” In this regard, we request you to kindly grant an extension upto 30th June 2026 for the above-mentioned project. The purpose of seeking this extension is to complete necessary corrections and updates, including alignment of BUA, Units, FSI, and other project details with the approved Full Occupancy Certificate plans”
  4. 30 March 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: AMRUT TARA’s extension records on MahaRERA (P51800009896), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AMRUT TARA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009896
Status
Registered and active
Builder
Meghvarnam Realty Private Limited
Location
Fort, Mumbai · 400061
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
December 2019
Latest completion date
March 2027
Delay so far
83 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
202
Sold or booked
98%
Towers
3
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of AMRUT TARA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AMRUT TARA A100%100%100%100%
AMRUT TARA B100%100%100%100%
AMRUT TARA C100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • AMRUT TARA A: covers 22 floors
  • AMRUT TARA B: covers 22 floors
  • AMRUT TARA C: covers 22 floors

Latest CC order on MahaRERA: dated 22/09/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AMRUT TARA every month.

AMRUT TARA: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK547 – 595102
3 BHK82368
1 BHK42232
  • Buildings: AMRUT TARA A (22 floors, 68 units) · AMRUT TARA B (22 floors, 66 units) · AMRUT TARA C (22 floors, 68 units)
  • Car parking: 210 covered
  • Land: 7,831 sq m (about 1.9 acres) · sanctioned built-up 13,829 sq m · recreational space 274 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of AMRUT TARA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AMRUT TARA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AMRUT TARA

What is the possession date of AMRUT TARA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AMRUT TARA in Fort, Mumbai is 30 March 2027 — 83 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for AMRUT TARA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AMRUT TARA's builder has filed on MahaRERA, the official one, is 30 March 2027, already 83 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AMRUT TARA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AMRUT TARA's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2025, giving the reason "Liquidity Management Issue"; to 30 November 2026, giving the reason "We have already uploaded the Full Occupancy Certificate dated 28th April 2025 on the MahaRERA portal for your kind reference. However, the project is currently reflecting under the category of “Lapsed Projects.” In this regard, we request you to kindly grant an extension upto 30th June 2026 for the above-mentioned project. The purpose of seeking this extension is to complete necessary corrections and updates, including alignment of BUA, Units, FSI, and other project details with the approved Full Occupancy Certificate plans". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of AMRUT TARA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AMRUT TARA in Fort, Mumbai is P51800009896.

Is AMRUT TARA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AMRUT TARA is registered as P51800009896 and its status is "Registered and active".

What is the construction status of AMRUT TARA?

According to GharKundli's check of MahaRERA records (updated October 2026), AMRUT TARA's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does AMRUT TARA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is AMRUT TARA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AMRUT TARA is registered on MahaRERA as P51800009896, its completion date has moved 83 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AMRUT TARA's possession date changes?

The latest dates are on AMRUT TARA's MahaRERA page (P51800009896). GharKundli's Kundli Watch sends a free WhatsApp update on AMRUT TARA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AMRUT TARA have?

According to GharKundli's check of MahaRERA records (updated October 2026), AMRUT TARA has 3 buildings filed: AMRUT TARA A with 22 floors and 68 units; AMRUT TARA B with 22 floors and 66 units; AMRUT TARA C with 22 floors and 68 units.

What are the flat sizes (carpet area) in AMRUT TARA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for AMRUT TARA: 2 BHK: 547 to 595 sq ft carpet (102 homes); 3 BHK: 823 sq ft carpet (68 homes); 1 BHK: 422 sq ft carpet (32 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does AMRUT TARA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 210 covered car parking spaces for AMRUT TARA.

How big is the land of AMRUT TARA?

According to GharKundli's check of MahaRERA records (updated October 2026), AMRUT TARA stands on 7,831 sq m of land (about 1.9 acres), with 13,829 sq m of sanctioned built-up area and 274 sq m of recreational open space.

Where can I read reviews of AMRUT TARA?

Google Maps has reviews of AMRUT TARA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AMRUT TARA?

AMRUT TARA by Meghvarnam Realty Private Limited is in Fort, Mumbai (pincode 400061), Maharashtra, and is registered on MahaRERA as P51800009896, per GharKundli's check of MahaRERA records.

How many homes are in AMRUT TARA?

According to GharKundli's check of MahaRERA records (updated October 2026), AMRUT TARA has 202 homes in 3 towers registered on MahaRERA, and 98% of them are sold or booked.

When was AMRUT TARA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AMRUT TARA was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on AMRUT TARA?

1 court case is listed for AMRUT TARA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of AMRUT TARA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Meghvarnam Realty Private Limited.

All projects with possession due in 2027 in Mumbai Suburban →