Altavista - Phase 2

by SPENTA ENCLAVE PRIVATE LIMITED · Fort, MumbaiAlso near Chembur, Nehru Nagar, Fci

Possession date of Altavista - Phase 2: 30 October 2028, moved from 30 June 2021 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800000956, and currently active. Its completion date has moved from June 2021 to October 2028: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 12 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Altavista - Phase 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Altavista - Phase 2 has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51800009861)

    Reason the builder gave MahaRERA:
    “Due to the COVID-19 pandemic, we faced severe shortage of labour. Prior to the pandemic, we had nearly 400 labourers at our site. Due to stoppage of work, nearly all labours left site for their villages. Also, prior to the pandemic, many of…” Read the full reason“Due to the COVID-19 pandemic, we faced severe shortage of labour. Prior to the pandemic, we had nearly 400 labourers at our site. Due to stoppage of work, nearly all labours left site for their villages. Also, prior to the pandemic, many of these labours were living in external labour camps close to the project site and travelled to the site for work daily. This was due to lack of space at the project site to physically fit labour camps to accommodate all labourers required. Since the lockdowns in March 2020, labour strength has been on the lower side as now we are able to work with only la…”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800013323)

    Reason the builder gave MahaRERA:
    “As has been disclosed on the MahaRERA portal at the time of Registration of the project, we have secured funding from JM Financial Credit Solutions (“JM”) and Motilal Oswal Real Estate (“Motilal”). As part of the funding arrangement, IDBI T…” Read the full reason“As has been disclosed on the MahaRERA portal at the time of Registration of the project, we have secured funding from JM Financial Credit Solutions (“JM”) and Motilal Oswal Real Estate (“Motilal”). As part of the funding arrangement, IDBI Trusteeship Services Ltd. (“IDBI”), acting on the instructions of both lenders has control over the escrow account in which all receivables from flat purchasers are deposited through our RERA Escrow account. Over the last few years, at various times JM and Motilal have swept the said escrow account for amounts exceeding 30%, as mandated by law in order to…”
  4. 30 June 2028

    Extended at the builder's request (MahaRERA application EA27052501265)

    Reason the builder gave MahaRERA: “Refer Explanatory statement for reason for delay”
  5. 30 October 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Altavista - Phase 2’s extension records on MahaRERA (P51800000956), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Altavista - Phase 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 12 complaints, and how it ended
  • Construction pace against the October 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800000956
Status
Registered and active
Builder
SPENTA ENCLAVE PRIVATE LIMITED
Location
Fort, Mumbai · 400071
Project type
Residential / Group Housing
Registered on
25 Jul 2017
Completion date at registration
June 2021
Latest completion date
October 2028
Delay so far
84 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
169
Sold or booked
92%
Towers
2
Complaints on MahaRERA
12
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Altavista - Phase 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing E100%100%100%50%
Wing F100%100%75%25%

Commencement certificate (CC), as filed on MahaRERA

  • Wing E: covers 23 floors
  • Wing F: covers 23 floors

Latest CC order on MahaRERA: dated 23/04/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Altavista - Phase 2 every month.

Altavista - Phase 2: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK956 – 96288
2 BHK662 – 77081
  • Buildings: Wing E (29 floors, 45 units) · Wing F (29 floors, 124 units)
  • Land: 2,912 sq m (about 0.7 acres) · sanctioned built-up 15,168 sq m · recreational space 2,248 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Spenta Enclave has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 55 months); 5 still being built, 5 past the promised date (typically 12 months late). 33 complaints on MahaRERA across 5 projects.

Read Google reviews of Altavista - Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Altavista - Phase 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Altavista - Phase 2

What is the possession date of Altavista - Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Altavista - Phase 2 in Fort, Mumbai is 30 October 2028 — 84 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Altavista - Phase 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Altavista - Phase 2's builder has filed on MahaRERA, the official one, is 30 October 2028, already 84 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Altavista - Phase 2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 2's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "Due to the COVID-19 pandemic, we faced severe shortage of labour. Prior to the pandemic, we had nearly 400 labourers at our site. Due to stoppage of work, nearly all labours left site for their villages. Also, prior to the pandemic, many of these labours were living in external labour camps close to the project site and travelled to the site for work daily. This was due to lack of space at the project site to physically fit labour camps to accommodate all labourers required. Since the lockdowns in March 2020, labour strength has been on the lower side as now we are able to work with only la…"; to 30 June 2025, giving the reason "As has been disclosed on the MahaRERA portal at the time of Registration of the project, we have secured funding from JM Financial Credit Solutions (“JM”) and Motilal Oswal Real Estate (“Motilal”). As part of the funding arrangement, IDBI Trusteeship Services Ltd. (“IDBI”), acting on the instructions of both lenders has control over the escrow account in which all receivables from flat purchasers are deposited through our RERA Escrow account. Over the last few years, at various times JM and Motilal have swept the said escrow account for amounts exceeding 30%, as mandated by law in order to…"; to 30 June 2028, giving the reason "Refer Explanatory statement for reason for delay". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Altavista - Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Altavista - Phase 2 in Fort, Mumbai is P51800000956.

Is Altavista - Phase 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 2 is registered as P51800000956 and its status is "Registered and active". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the construction status of Altavista - Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Altavista - Phase 2 have complaints on MahaRERA?

12 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Altavista - Phase 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 2 is registered on MahaRERA as P51800000956, its completion date has moved 84 months since registration, 12 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Altavista - Phase 2 have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Altavista - Phase 1 (P51800001050, possession 31 Jul 2024); Altavista - Phase 3 (P51800021249, possession 30 Oct 2028); Altavista - Phase 4 (P51800026131, possession 30 Apr 2030). Check that your agreement names the registration of your own wing.

How can I get updates if Altavista - Phase 2's possession date changes?

The latest dates are on Altavista - Phase 2's MahaRERA page (P51800000956). GharKundli's Kundli Watch sends a free WhatsApp update on Altavista - Phase 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Altavista - Phase 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 2 has 2 buildings filed: Wing E with 29 floors and 45 units; Wing F with 29 floors and 124 units.

What are the flat sizes (carpet area) in Altavista - Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Altavista - Phase 2: 3 BHK: 956 to 962 sq ft carpet (88 homes); 2 BHK: 662 to 770 sq ft carpet (81 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Altavista - Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 2 stands on 2,912 sq m of land (about 0.7 acres), with 15,168 sq m of sanctioned built-up area and 2,248 sq m of recreational open space.

What is the track record of Altavista - Phase 2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Spenta Enclave has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 55 months); 5 still being built, 5 past the promised date (typically 12 months late). 33 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Altavista - Phase 2?

Google Maps has reviews of Altavista - Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 12 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Altavista - Phase 2?

Altavista - Phase 2 by SPENTA ENCLAVE PRIVATE LIMITED is in Fort, Mumbai (pincode 400071), near Chembur, Nehru Nagar, Fci, Maharashtra, and is registered on MahaRERA as P51800000956, per GharKundli's check of MahaRERA records.

How many homes are in Altavista - Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 2 has 169 homes in 2 towers registered on MahaRERA, and 92% of them are sold or booked.

When was Altavista - Phase 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 2 was registered on MahaRERA on 25 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Altavista - Phase 2?

No court cases are listed for Altavista - Phase 2 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Altavista - Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SPENTA ENCLAVE PRIVATE LIMITED, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Fort

All 318 projects in Chembur (400071) →

Other projects by SPENTA ENCLAVE PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.