Altavista - Phase 4

by SPENTA ENCLAVE PRIVATE LIMITED · Chembur, Mumbai 400071Also near Fort, Nehru Nagar, Fci

What’s in the report? →

Possession date of Altavista - Phase 4 (MahaRERA P51800026131): 30 April 2030, moved from 30 December 2024 (60 months later). It has 113 homes (2 BHK, 591–699 sq ft carpet), 17% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800026131, and currently active. Its completion date has moved from December 2024 to April 2030: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800026131, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Altavista - Phase 4?

MahaRERA ki red-flag list mein hai. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Altavista - Phase 4 has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 31 December 2029

    Extended at the builder's request (MahaRERA application EXT51800025508)

    Reason the builder gave MahaRERA:
    “The project was launched during Covid-19 pandemic. The restrictions implemented by the government during the pandemic delayed the construction activities at site. Once the pandemic situation eased out and the construction started at site, t…” Read the full reason“The project was launched during Covid-19 pandemic. The restrictions implemented by the government during the pandemic delayed the construction activities at site. Once the pandemic situation eased out and the construction started at site, the company got admitted into NCLT which again halted the construction. Now the Resolution Professional who is appointed by NCLT to run the company has availed interim finance and have started construction activities at site. The flat purchasers who are part of committee of creditors(COC) in the COC meeting held on 28/01/2025 have approved by E-voting the…”
  3. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Altavista - Phase 4’s extension records on MahaRERA (P51800026131), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Altavista - Phase 4

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800026131
Status
Registered and active
Builder
SPENTA ENCLAVE PRIVATE LIMITED
Location
Chembur, Mumbai · 400071
Project type
Residential / Group Housing
Registered on
21 Aug 2020
Completion date at registration
December 2024
Latest completion date
April 2030
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
113
Sold or booked
17%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Altavista - Phase 4, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing I0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing I: covers Plinth

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Altavista - Phase 4 every 1–2 months.

Altavista - Phase 4: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK591 – 699113

The builder’s record and reviews

Spenta Enclave has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 55 months); 5 still being built, 5 past the promised date (typically 12 months late). 33 complaints on MahaRERA across 5 projects.

Read Google reviews of Altavista - Phase 4 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Altavista - Phase 4: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Altavista - Phase 4

What is the possession date of Altavista - Phase 4?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Altavista - Phase 4 in Chembur, Mumbai is 30 April 2030 — 60 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 60 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Altavista - Phase 4?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Altavista - Phase 4's builder has filed on MahaRERA, the official one, is 30 April 2030, already 60 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Altavista - Phase 4 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 4's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "The project was launched during Covid-19 pandemic. The restrictions implemented by the government during the pandemic delayed the construction activities at site. Once the pandemic situation eased out and the construction started at site, the company got admitted into NCLT which again halted the construction. Now the Resolution Professional who is appointed by NCLT to run the company has availed interim finance and have started construction activities at site. The flat purchasers who are part of committee of creditors(COC) in the COC meeting held on 28/01/2025 have approved by E-voting the…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Altavista - Phase 4?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Altavista - Phase 4 in Chembur, Mumbai is P51800026131.

Is Altavista - Phase 4 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 4 is registered as P51800026131 and its status is "Registered and active". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the current construction status of Altavista - Phase 4? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 4's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing I is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Altavista - Phase 4 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Altavista - Phase 4 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 4 is registered on MahaRERA as P51800026131, its completion date has moved 60 months since registration, no complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Altavista - Phase 4?

Altavista - Phase 4 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Altavista - Phase 4 are 591 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Altavista - Phase 4?

For a flat in Altavista - Phase 4 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Altavista - Phase 4 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 4 is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Altavista - Phase 4 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Altavista - Phase 4 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Altavista - Phase 4 have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Altavista - Phase 1 (P51800001050, possession 31 Jul 2024); Altavista - Phase 2 (P51800000956, possession 30 Oct 2028); Altavista - Phase 3 (P51800021249, possession 30 Oct 2028). Check that your agreement names the registration of your own wing.

How can I get updates if Altavista - Phase 4's possession date changes?

The latest dates are on Altavista - Phase 4's MahaRERA page (P51800026131). GharKundli's Kundli Watch sends a free WhatsApp update on Altavista - Phase 4 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Altavista - Phase 4 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 4 has one building filed: Wing I with 29 floors and 113 units.

What are the flat sizes (carpet area) in Altavista - Phase 4?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Altavista - Phase 4: 2 BHK: 591 to 699 sq ft carpet (113 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Altavista - Phase 4?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 4 stands on 465 sq m of land (about 0.1 acres), with 568 sq m of sanctioned built-up area and 350 sq m of recreational open space.

What is the track record of Altavista - Phase 4's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Spenta Enclave has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 55 months); 5 still being built, 5 past the promised date (typically 12 months late). 33 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Altavista - Phase 4?

Google Maps has reviews of Altavista - Phase 4 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Altavista - Phase 4?

Altavista - Phase 4 by SPENTA ENCLAVE PRIVATE LIMITED is in Chembur, Mumbai, pincode 400071 (near Fort, Nehru Nagar, Fci), Maharashtra, and is registered on MahaRERA as P51800026131, per GharKundli's check of MahaRERA records. Its land is filed as 343 part. GharKundli lists all 318 MahaRERA projects in Chembur (400071).

How many flats are in Altavista - Phase 4, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 4 has 113 homes in 1 tower registered on MahaRERA, and 17% of them are sold or booked.

When was Altavista - Phase 4 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 4 was registered on MahaRERA on 21 August 2020. GharKundli did not find a title report on the land on file there.

Does Altavista - Phase 4 have any legal issues or court cases?

1 court case is listed for Altavista - Phase 4 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Altavista - Phase 4?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SPENTA ENCLAVE PRIVATE LIMITED, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2030 in Mumbai Suburban →

Other projects in Chembur (400071)

All 318 projects in Chembur (400071) →

Other projects by SPENTA ENCLAVE PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.