Ornata - Sapphire
by SPENTA ENCLAVE PRIVATE LIMITED · Chembur, MumbaiAlso near Fort, Nehru Nagar, Fci
Possession date of Ornata - Sapphire: 30 June 2028, moved from 30 June 2025 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800026905, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about Ornata - Sapphire?
How the possession date of Ornata - Sapphire has moved
30 June 2025
Completion date given when the project was registered
30 June 2028
Extended at the builder's request (MahaRERA application EA07072501965)
Reason the builder gave MahaRERA: “Refer Explanatory Statement & CPM/PERT chart for reason for delay and prayer for grant of extension upto 30 June 2028”
Source: Ornata - Sapphire’s extension records on MahaRERA (P51800026905), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Ornata - Sapphire
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the June 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800026905
- Status
- Registered and active
- Builder
- SPENTA ENCLAVE PRIVATE LIMITED
- Location
- Chembur, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 3 Nov 2020
- Completion date at registration
- June 2025
- Latest completion date
- June 2028
- Delay so far
- 36 months
- Homes
- 202
- Sold or booked
- 49%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Ornata - Sapphire, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sapphire | 50% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Sapphire: covers Plinth
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ornata - Sapphire every month.
Ornata - Sapphire: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 463 – 537 | 151 |
| 1 BHK | 308 – 362 | 51 |
- Buildings: Sapphire (32 floors, 202 units)
- Land: 548 sq m (about 0.1 acres) · sanctioned built-up 9,594 sq m · recreational space 335 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Spenta Enclave has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 55 months); 5 still being built, 5 past the promised date (typically 12 months late). 33 complaints on MahaRERA across 5 projects.
Read Google reviews of Ornata - Sapphire →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ornata - Sapphire: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Ornata - Sapphire
What is the possession date of Ornata - Sapphire?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ornata - Sapphire in Chembur, Mumbai is 30 June 2028 — 36 months later than 30 June 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Ornata - Sapphire?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ornata - Sapphire's builder has filed on MahaRERA, the official one, is 30 June 2028, already 36 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Ornata - Sapphire extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Ornata - Sapphire's builder applied to MahaRERA to extend the completion date once: to 30 June 2028, giving the reason "Refer Explanatory Statement & CPM/PERT chart for reason for delay and prayer for grant of extension upto 30 June 2028".
What is the RERA number of Ornata - Sapphire?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ornata - Sapphire in Chembur, Mumbai is P51800026905.
Is Ornata - Sapphire registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ornata - Sapphire is registered as P51800026905 and its status is "Registered and active". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the construction status of Ornata - Sapphire?
According to GharKundli's check of MahaRERA records (updated October 2026), Ornata - Sapphire's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sapphire is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Ornata - Sapphire have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Ornata - Sapphire safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Ornata - Sapphire is registered on MahaRERA as P51800026905, its completion date has moved 36 months since registration, 1 complaint is listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Ornata - Sapphire's possession date changes?
The latest dates are on Ornata - Sapphire's MahaRERA page (P51800026905). GharKundli's Kundli Watch sends a free WhatsApp update on Ornata - Sapphire every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Ornata - Sapphire have?
According to GharKundli's check of MahaRERA records (updated October 2026), Ornata - Sapphire has one building filed: Sapphire with 32 floors and 202 units.
What are the flat sizes (carpet area) in Ornata - Sapphire?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ornata - Sapphire: 2 BHK: 463 to 537 sq ft carpet (151 homes); 1 BHK: 308 to 362 sq ft carpet (51 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Ornata - Sapphire?
According to GharKundli's check of MahaRERA records (updated October 2026), Ornata - Sapphire stands on 548 sq m of land (about 0.1 acres), with 9,594 sq m of sanctioned built-up area and 335 sq m of recreational open space.
What is the track record of Ornata - Sapphire's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Spenta Enclave has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 55 months); 5 still being built, 5 past the promised date (typically 12 months late). 33 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Ornata - Sapphire?
Google Maps has reviews of Ornata - Sapphire written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Ornata - Sapphire?
Ornata - Sapphire by SPENTA ENCLAVE PRIVATE LIMITED is in Chembur, Mumbai (pincode 400071), near Fort, Nehru Nagar, Fci, Maharashtra, and is registered on MahaRERA as P51800026905, per GharKundli's check of MahaRERA records.
How many homes are in Ornata - Sapphire?
According to GharKundli's check of MahaRERA records (updated October 2026), Ornata - Sapphire has 202 homes in 1 tower registered on MahaRERA, and 49% of them are sold or booked.
When was Ornata - Sapphire registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ornata - Sapphire was registered on MahaRERA on 3 November 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on Ornata - Sapphire?
No court cases are listed for Ornata - Sapphire on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Ornata - Sapphire?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SPENTA ENCLAVE PRIVATE LIMITED, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Ornata - Sapphire
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400071
- SHREE SARASWATI CHS LTD PLOT 8B
- TULSI CHAMBER PHASE II
- SAMPOORNA
- QUEENS PARK
- ARHAM MOURYA
- 71 Pardis
- ICONS 71
- Viera Golf Greens
Other projects by SPENTA ENCLAVE PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.