Altavista - Phase 3

by SPENTA ENCLAVE PRIVATE LIMITED · Chembur, MumbaiAlso near Fort, Nehru Nagar, Fci

Possession date of Altavista - Phase 3: 30 October 2028, moved from 30 June 2025 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800021249, and currently active. Its completion date has moved from June 2025 to October 2028: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Altavista - Phase 3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Altavista - Phase 3 has moved

  1. 30 June 2025

    Completion date given when the project was registered

  2. 30 June 2028

    Extended at the builder's request (MahaRERA application EA20062501686)

    Reason the builder gave MahaRERA: “Refer explanatory statement for reason for delay”
  3. 30 October 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Altavista - Phase 3’s extension records on MahaRERA (P51800021249), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Altavista - Phase 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800021249
Status
Registered and active
Builder
SPENTA ENCLAVE PRIVATE LIMITED
Location
Chembur, Mumbai · 400071
Project type
Residential / Group Housing
Registered on
14 Jun 2019
Completion date at registration
June 2025
Latest completion date
October 2028
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
64
Sold or booked
55%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Altavista - Phase 3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing H100%100%8%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing H: covers 23 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Altavista - Phase 3 every month.

Altavista - Phase 3: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK62342
3 BHK1,04122

The builder’s record and reviews

Spenta Enclave has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 55 months); 5 still being built, 5 past the promised date (typically 12 months late). 33 complaints on MahaRERA across 5 projects.

Read Google reviews of Altavista - Phase 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Altavista - Phase 3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Altavista - Phase 3

What is the possession date of Altavista - Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Altavista - Phase 3 in Chembur, Mumbai is 30 October 2028 — 36 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Altavista - Phase 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Altavista - Phase 3's builder has filed on MahaRERA, the official one, is 30 October 2028, already 36 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Altavista - Phase 3 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 3's builder applied to MahaRERA to extend the completion date once: to 30 June 2028, giving the reason "Refer explanatory statement for reason for delay". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Altavista - Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Altavista - Phase 3 in Chembur, Mumbai is P51800021249.

Is Altavista - Phase 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 3 is registered as P51800021249 and its status is "Registered and active". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the construction status of Altavista - Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing H is 100% done and internal work 8%. GharKundli's full report compares construction progress with the deadline.

Does Altavista - Phase 3 have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Altavista - Phase 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 3 is registered on MahaRERA as P51800021249, its completion date has moved 36 months since registration, 1 complaint is listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Altavista - Phase 3 have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Altavista - Phase 1 (P51800001050, possession 31 Jul 2024); Altavista - Phase 2 (P51800000956, possession 30 Oct 2028); Altavista - Phase 4 (P51800026131, possession 30 Apr 2030). Check that your agreement names the registration of your own wing.

How can I get updates if Altavista - Phase 3's possession date changes?

The latest dates are on Altavista - Phase 3's MahaRERA page (P51800021249). GharKundli's Kundli Watch sends a free WhatsApp update on Altavista - Phase 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Altavista - Phase 3 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 3 has one building filed: Wing H with 29 floors and 64 units.

What are the flat sizes (carpet area) in Altavista - Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Altavista - Phase 3: 2 BHK: 623 sq ft carpet (42 homes); 3 BHK: 1041 sq ft carpet (22 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Altavista - Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 3 stands on 300 sq m of land (about 0.1 acres), with 5,456 sq m of sanctioned built-up area and 234 sq m of recreational open space.

What is the track record of Altavista - Phase 3's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Spenta Enclave has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 55 months); 5 still being built, 5 past the promised date (typically 12 months late). 33 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Altavista - Phase 3?

Google Maps has reviews of Altavista - Phase 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Altavista - Phase 3?

Altavista - Phase 3 by SPENTA ENCLAVE PRIVATE LIMITED is in Chembur, Mumbai (pincode 400071), near Fort, Nehru Nagar, Fci, Maharashtra, and is registered on MahaRERA as P51800021249, per GharKundli's check of MahaRERA records.

How many homes are in Altavista - Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 3 has 64 homes in 1 tower registered on MahaRERA, and 55% of them are sold or booked.

When was Altavista - Phase 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Altavista - Phase 3 was registered on MahaRERA on 14 June 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Altavista - Phase 3?

No court cases are listed for Altavista - Phase 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Altavista - Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SPENTA ENCLAVE PRIVATE LIMITED, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in pincode 400071

All 318 projects in Chembur (400071) →

Other projects by SPENTA ENCLAVE PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.