Sarvppratham Palm Hills
by SARVPPRATHAM DEVELOPERS PVT. LTD.. · Gonedumala, Nashik 422403Also near IgatpuriRegistered on MahaRERA as “PALM HILLS”
What’s in the report? →Possession date of Sarvppratham Palm Hills (MahaRERA P51600032143): 31 December 2024, and it has already passed. It has 16 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600032143. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51600032143, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about Sarvppratham Palm Hills?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on Sarvppratham Palm Hills
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Palm Hills 02P51600054597 · possession 30 Apr 2027
- Palm Hills 03P51600078869 · possession 30 Apr 2028
- MahaRERA registration
- P51600032143
- Status
- Lapsed (registration period ended)
- Builder
- SARVPPRATHAM DEVELOPERS PVT. LTD..
- Location
- Gonedumala, Nashik · 422403
- Project type
- Residential / Group Housing
- Registered on
- 14 Dec 2021
- Completion date at registration
- December 2024
- Homes
- 16
- Towers
- 16
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Sarvppratham Palm Hills, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PALM VILLA NO 1 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 2 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 3 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 4 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 5 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 6 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 7 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 8 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 9 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 10 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 11 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 12 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 13 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 14 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 15 | 100% | 100% | 100% | 100% |
| PALM VILLA NO 16 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sarvppratham Palm Hills every 1–2 months.
Sarvppratham Palm Hills: buildings, flats and land, as filed on MahaRERA
- Buildings: PALM VILLA NO 1 (2 floors) · PALM VILLA NO 2 (2 floors) · PALM VILLA NO 3 (2 floors) · PALM VILLA NO 4 (2 floors) · PALM VILLA NO 5 (2 floors) · PALM VILLA NO 6 (2 floors) · PALM VILLA NO 7 (2 floors) · PALM VILLA NO 8 (2 floors) · and 8 more
- Land: 8,470 sq m (about 2.1 acres) · sanctioned built-up 6,553 sq m
- Land, as filed: 607/2 629/PT PLOT NO 2, SEC II
- Map: Get directions
The builder’s record and reviews
Sarvppratham Developers has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of Sarvppratham Palm Hills →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sarvppratham Palm Hills: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sarvppratham Palm Hills
What is the possession date of Sarvppratham Palm Hills?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sarvppratham Palm Hills in Gonedumala, Nashik is 31 December 2024. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Sarvppratham Palm Hills?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sarvppratham Palm Hills's builder has filed on MahaRERA, the official one, is 31 December 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Sarvppratham Palm Hills?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sarvppratham Palm Hills in Gonedumala, Nashik is P51600032143.
Is Sarvppratham Palm Hills registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Sarvppratham Palm Hills is registered as P51600032143 and its status is "Lapsed (registration period ended)".
What is the current construction status of Sarvppratham Palm Hills? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Sarvppratham Palm Hills's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 16 towers. GharKundli's full report compares construction progress with the deadline.
Does Sarvppratham Palm Hills have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Sarvppratham Palm Hills safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Sarvppratham Palm Hills is registered on MahaRERA as P51600032143, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sarvppratham Palm Hills?
Sarvppratham Palm Hills isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sarvppratham Palm Hills?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Sarvppratham Palm Hills: gharkundli.com/tools/property-cost-calculator
Has Sarvppratham Palm Hills received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Sarvppratham Palm Hills isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Sarvppratham Palm Hills?
According to GharKundli's check of MahaRERA records (updated November 2026), Sarvppratham Palm Hills's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Sarvppratham Palm Hills uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Sarvppratham Palm Hills was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Sarvppratham Palm Hills have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Palm Hills 02 (P51600054597, possession 30 Apr 2027); Palm Hills 03 (P51600078869, possession 30 Apr 2028). Check that your agreement names the registration of your own wing.
How can I get updates if Sarvppratham Palm Hills's possession date changes?
The latest dates are on Sarvppratham Palm Hills's MahaRERA page (P51600032143). GharKundli's Kundli Watch sends a free WhatsApp update on Sarvppratham Palm Hills every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sarvppratham Palm Hills have?
According to GharKundli's check of MahaRERA records (updated November 2026), Sarvppratham Palm Hills has 16 buildings filed: PALM VILLA NO 1 with 2 floors; PALM VILLA NO 2 with 2 floors; PALM VILLA NO 3 with 2 floors; PALM VILLA NO 4 with 2 floors; PALM VILLA NO 5 with 2 floors; PALM VILLA NO 6 with 2 floors; and 10 more.
How big is the land of Sarvppratham Palm Hills?
According to GharKundli's check of MahaRERA records (updated November 2026), Sarvppratham Palm Hills stands on 8,470 sq m of land (about 2.1 acres), with 6,553 sq m of sanctioned built-up area.
What is the track record of Sarvppratham Palm Hills's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Sarvppratham Developers has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sarvppratham Palm Hills?
Google Maps has reviews of Sarvppratham Palm Hills written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sarvppratham Palm Hills?
Sarvppratham Palm Hills by SARVPPRATHAM DEVELOPERS PVT. LTD.. is in Gonedumala, Nashik, pincode 422403 (near Igatpuri), Maharashtra, and is registered on MahaRERA as P51600032143, per GharKundli's check of MahaRERA records. Its land is filed as 607/2 629/PT PLOT NO 2, SEC II. GharKundli lists all 47 MahaRERA projects in Igatpuri (422403).
How many flats are in Sarvppratham Palm Hills?
According to GharKundli's check of MahaRERA records (updated November 2026), Sarvppratham Palm Hills has 16 homes in 16 towers registered on MahaRERA.
When was Sarvppratham Palm Hills registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Sarvppratham Palm Hills was registered on MahaRERA on 14 December 2021. GharKundli did not find a title report on the land on file there.
Does Sarvppratham Palm Hills have any legal issues or court cases?
No court cases are listed for Sarvppratham Palm Hills on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Sarvppratham Palm Hills?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SARVPPRATHAM DEVELOPERS PVT. LTD.., which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sarvppratham Palm Hills
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Igatpuri (422403)
- Manomay Natures Paradize
- Park Bellagio
- Indo Asian Signature
- Rosewood - I J and K Wing
- Western Hills
- Mysty Heaven
- Anandvann Phase II
- United Infinity
Other projects by SARVPPRATHAM DEVELOPERS PVT. LTD..
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.