by STANDARD REALTORS PRIVATE LIMITED · Deolali Camp, Nashik

Possession: NAKSHATRA is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600034117. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about NAKSHATRA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NAKSHATRA has moved

  1. 31 March 2024

    Completion date given when the project was registered

  2. 5 June 2025

    Extended at the builder's request (MahaRERA application EA19082622224)

    Reason the builder gave MahaRERA:
    “The Project “Nakshatra”, bearing MahaRERA Registration No. P51600034117, was registered with the proposed completion date of 31 March 2024. The Promoter had applied for the Full Occupancy Certificate from the respective Competent Authority…” Read the full reason“The Project “Nakshatra”, bearing MahaRERA Registration No. P51600034117, was registered with the proposed completion date of 31 March 2024. The Promoter had applied for the Full Occupancy Certificate from the respective Competent Authority within the requisite time. However, due to procedural delays and completion of the necessary legal and administrative formalities at the level of the Competent Authority, the Full Occupancy Certificate could not be issued before the originally proposed completion date. The Full Occupancy Certificate was ultimately received on 05 June 2025. Accordingly, th…”

Source: NAKSHATRA’s extension records on MahaRERA (P51600034117), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NAKSHATRA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600034117
Status
Completed
Builder
STANDARD REALTORS PRIVATE LIMITED
Location
Deolali Camp, Nashik · 422101
Project type
Residential / Group Housing
Registered on
24 Mar 2022
Completion date at registration
March 2024
Latest completion date
June 2025
Delay so far
15 months
Homes
37
Sold or booked
43%
Towers
5
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of NAKSHATRA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NAKSHATRA A - 6100%100%100%100%
NAKSHATRA A-7100%100%100%100%
NAKSHATRA A - 8100%100%100%100%
NAKSHATRA ROW HOUSE100%100%100%100%
NAKSHATRA CLUB HOUSE100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • NAKSHATRA A - 6: covers 5 floors
  • NAKSHATRA A-7: covers 5 floors
  • NAKSHATRA A - 8: covers 5 floors
  • NAKSHATRA ROW HOUSE: covers 2 floors
  • NAKSHATRA CLUB HOUSE: covers 2 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NAKSHATRA every month.

NAKSHATRA: buildings, flats and land, as filed on MahaRERA

  • Buildings: NAKSHATRA A - 6 (5 floors, 12 units) · NAKSHATRA A-7 (5 floors, 12 units) · NAKSHATRA A - 8 (5 floors, 12 units) · NAKSHATRA ROW HOUSE (2 floors, 1 units) · NAKSHATRA CLUB HOUSE (2 floors)
  • Car parking: 12 covered, 25 open
  • Land: 7,175 sq m (about 1.8 acres) · sanctioned built-up 3,462 sq m
  • Boundaries filed include: APPROACH ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of NAKSHATRA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NAKSHATRA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NAKSHATRA

What is the possession date of NAKSHATRA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NAKSHATRA in Deolali Camp, Nashik is 5 June 2025 — 15 months later than 31 March 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for NAKSHATRA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NAKSHATRA's builder has filed on MahaRERA, the official one, is 5 June 2025, already 15 months later than the 31 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NAKSHATRA extended?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA's builder applied to MahaRERA to extend the completion date once: to 5 June 2025, giving the reason "The Project “Nakshatra”, bearing MahaRERA Registration No. P51600034117, was registered with the proposed completion date of 31 March 2024. The Promoter had applied for the Full Occupancy Certificate from the respective Competent Authority within the requisite time. However, due to procedural delays and completion of the necessary legal and administrative formalities at the level of the Competent Authority, the Full Occupancy Certificate could not be issued before the originally proposed completion date. The Full Occupancy Certificate was ultimately received on 05 June 2025. Accordingly, th…".

What is the RERA number of NAKSHATRA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NAKSHATRA in Deolali Camp, Nashik is P51600034117.

Is NAKSHATRA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA is registered as P51600034117 and its status is "Completed".

What is the construction status of NAKSHATRA?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does NAKSHATRA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is NAKSHATRA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA is registered on MahaRERA as P51600034117, its MahaRERA status is "Completed", its completion date has moved 15 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NAKSHATRA's possession date changes?

The latest dates are on NAKSHATRA's MahaRERA page (P51600034117). GharKundli's Kundli Watch sends a free WhatsApp update on NAKSHATRA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NAKSHATRA have?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA has 5 buildings filed: NAKSHATRA A - 6 with 5 floors and 12 units; NAKSHATRA A-7 with 5 floors and 12 units; NAKSHATRA A - 8 with 5 floors and 12 units; NAKSHATRA ROW HOUSE with 2 floors and 1 units; NAKSHATRA CLUB HOUSE with 2 floors.

How much parking does NAKSHATRA have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 12 covered and 25 open car parking spaces for NAKSHATRA.

How big is the land of NAKSHATRA?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA stands on 7,175 sq m of land (about 1.8 acres), with 3,462 sq m of sanctioned built-up area.

Where can I read reviews of NAKSHATRA?

Google Maps has reviews of NAKSHATRA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NAKSHATRA?

NAKSHATRA by STANDARD REALTORS PRIVATE LIMITED is in Deolali Camp, Nashik (pincode 422101), Maharashtra, and is registered on MahaRERA as P51600034117, per GharKundli's check of MahaRERA records. Its boundaries filed there include APPROACH ROAD.

How many homes are in NAKSHATRA?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA has 37 homes in 5 towers registered on MahaRERA, and 43% of them are sold or booked.

When was NAKSHATRA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA was registered on MahaRERA on 24 March 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on NAKSHATRA?

No court cases are listed for NAKSHATRA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of NAKSHATRA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is STANDARD REALTORS PRIVATE LIMITED.

Other projects in Nashik

All 178 projects in Nashik Road (422101) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.