SHREE DATTA MANGAL APARTMENT D AND E

by TARACHAND DEVISAHAY GUPTA · Village Aanandwali, Nashik

Possession date of SHREE DATTA MANGAL APARTMENT D AND E: 31 July 2027, moved from 31 March 2025 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600032962, and currently active. Its completion date has moved from March 2025 to July 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHREE DATTA MANGAL APARTMENT D AND E?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHREE DATTA MANGAL APARTMENT D AND E has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA03072501940)

    Reason the builder gave MahaRERA:
    “a. Workforce and Material Issues: • Labor Shortages: Availability of skilled manpower, especially in structural and MEP (Mechanical, Electrical & Plumbing) areas, was restricted due to migration and contractual disruptions, slowing down pro…” Read the full reason“a. Workforce and Material Issues: • Labor Shortages: Availability of skilled manpower, especially in structural and MEP (Mechanical, Electrical & Plumbing) areas, was restricted due to migration and contractual disruptions, slowing down project execution. • Supply Chain Disruptions: Escalation in raw material costs and delays in delivery of essential materials further extended the project timeline. b. Financial Constraints: • Due to market slowdown, the project faced liquidity constraints, delaying scheduled construction activities. c. Design Changes and Legal Issues: • Minor design alterat…”
  3. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SHREE DATTA MANGAL APARTMENT D AND E’s extension records on MahaRERA (P51600032962), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHREE DATTA MANGAL APARTMENT D AND E

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600032962
Status
Registered and active
Builder
TARACHAND DEVISAHAY GUPTA
Location
Village Aanandwali, Nashik · 422005
Project type
Residential / Group Housing
Registered on
2 Feb 2022
Completion date at registration
March 2025
Latest completion date
July 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
48
Sold or booked
4%
Towers
2
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of SHREE DATTA MANGAL APARTMENT D AND E, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE DATTA MANGAL APARTMENT D100%100%80%50%
SHREE DATTA MANGAL APPARTMENT E100%100%80%50%

Commencement certificate (CC), as filed on MahaRERA

  • SHREE DATTA MANGAL APARTMENT D: covers 7 floors
  • SHREE DATTA MANGAL APPARTMENT E: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE DATTA MANGAL APARTMENT D AND E every month.

SHREE DATTA MANGAL APARTMENT D AND E: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHREE DATTA MANGAL APARTMENT D (7 floors, 24 units) · SHREE DATTA MANGAL APPARTMENT E (7 floors, 24 units)
  • Car parking: 23 covered
  • Land: 1,210 sq m (about 0.3 acres) · sanctioned built-up 3,558 sq m
  • Boundaries filed include: 9 MT COLONY ROAD

The builder’s record and reviews

Tarachand Devisahay Gupta has 3 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 17 months late). No complaints on MahaRERA.

Read Google reviews of SHREE DATTA MANGAL APARTMENT D AND E →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHREE DATTA MANGAL APARTMENT D AND E: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHREE DATTA MANGAL APARTMENT D AND E

What is the possession date of SHREE DATTA MANGAL APARTMENT D AND E?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE DATTA MANGAL APARTMENT D AND E in Village Aanandwali, Nashik is 31 July 2027 — 24 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SHREE DATTA MANGAL APARTMENT D AND E?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE DATTA MANGAL APARTMENT D AND E's builder has filed on MahaRERA, the official one, is 31 July 2027, already 24 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHREE DATTA MANGAL APARTMENT D AND E extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE DATTA MANGAL APARTMENT D AND E's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "a. Workforce and Material Issues: • Labor Shortages: Availability of skilled manpower, especially in structural and MEP (Mechanical, Electrical & Plumbing) areas, was restricted due to migration and contractual disruptions, slowing down project execution. • Supply Chain Disruptions: Escalation in raw material costs and delays in delivery of essential materials further extended the project timeline. b. Financial Constraints: • Due to market slowdown, the project faced liquidity constraints, delaying scheduled construction activities. c. Design Changes and Legal Issues: • Minor design alterat…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SHREE DATTA MANGAL APARTMENT D AND E?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHREE DATTA MANGAL APARTMENT D AND E in Village Aanandwali, Nashik is P51600032962.

Is SHREE DATTA MANGAL APARTMENT D AND E registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE DATTA MANGAL APARTMENT D AND E is registered as P51600032962 and its status is "Registered and active".

What is the construction status of SHREE DATTA MANGAL APARTMENT D AND E?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE DATTA MANGAL APARTMENT D AND E's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does SHREE DATTA MANGAL APARTMENT D AND E have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SHREE DATTA MANGAL APARTMENT D AND E safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE DATTA MANGAL APARTMENT D AND E is registered on MahaRERA as P51600032962, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHREE DATTA MANGAL APARTMENT D AND E's possession date changes?

The latest dates are on SHREE DATTA MANGAL APARTMENT D AND E's MahaRERA page (P51600032962). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE DATTA MANGAL APARTMENT D AND E every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHREE DATTA MANGAL APARTMENT D AND E have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE DATTA MANGAL APARTMENT D AND E has 2 buildings filed: SHREE DATTA MANGAL APARTMENT D with 7 floors and 24 units; SHREE DATTA MANGAL APPARTMENT E with 7 floors and 24 units.

How much parking does SHREE DATTA MANGAL APARTMENT D AND E have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 23 covered car parking spaces for SHREE DATTA MANGAL APARTMENT D AND E.

How big is the land of SHREE DATTA MANGAL APARTMENT D AND E?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE DATTA MANGAL APARTMENT D AND E stands on 1,210 sq m of land (about 0.3 acres), with 3,558 sq m of sanctioned built-up area.

What is the track record of SHREE DATTA MANGAL APARTMENT D AND E's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Tarachand Devisahay Gupta has 3 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 17 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SHREE DATTA MANGAL APARTMENT D AND E?

Google Maps has reviews of SHREE DATTA MANGAL APARTMENT D AND E written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHREE DATTA MANGAL APARTMENT D AND E?

SHREE DATTA MANGAL APARTMENT D AND E by TARACHAND DEVISAHAY GUPTA is in Village Aanandwali, Nashik (pincode 422005), Maharashtra, and is registered on MahaRERA as P51600032962, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9 MT COLONY ROAD.

How many homes are in SHREE DATTA MANGAL APARTMENT D AND E?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE DATTA MANGAL APARTMENT D AND E has 48 homes in 2 towers registered on MahaRERA, and 4% of them are sold or booked.

When was SHREE DATTA MANGAL APARTMENT D AND E registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE DATTA MANGAL APARTMENT D AND E was registered on MahaRERA on 2 February 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on SHREE DATTA MANGAL APARTMENT D AND E?

1 court case is listed for SHREE DATTA MANGAL APARTMENT D AND E on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SHREE DATTA MANGAL APARTMENT D AND E?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TARACHAND DEVISAHAY GUPTA, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Nashik →

Other projects in Nashik

All 75 projects in H P T College (422005) →

Other projects by TARACHAND DEVISAHAY GUPTA

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.