shivalayheights
by SHIVALAY CONSTRUCTION · behind sharadchandra pawar market yard, Nashik
Possession date of shivalayheights: 31 December 2026, moved from 31 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600034487, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about shivalayheights?
How the possession date of shivalayheights has moved
31 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51600027949)
Reason the builder gave MahaRERA: “FUND ISSUE.”
31 December 2026
Extended at the builder's request (MahaRERA application EA27012619592)
Reason the builder gave MahaRERA: “TECHNICAL ISSUE”
Source: shivalayheights’s extension records on MahaRERA (P51600034487), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on shivalayheights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600034487
- Status
- Registered and active
- Builder
- SHIVALAY CONSTRUCTION
- Location
- behind sharadchandra pawar market yard, Nashik · 422001
- Project type
- Residential / Group Housing
- Registered on
- 11 Apr 2022
- Completion date at registration
- December 2024
- Latest completion date
- December 2026
- Delay so far
- 24 months
- Homes
- 56
- Sold or booked
- 73%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of shivalayheights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shivalay Heights | 100% | 0% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- Shivalay Heights: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on shivalayheights every month.
shivalayheights: buildings, flats and land, as filed on MahaRERA
- Buildings: Shivalay Heights (9 floors, 60 units)
- Car parking: 56 covered
- Land: 1,100 sq m (about 0.3 acres) · sanctioned built-up 4,286 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of shivalayheights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
shivalayheights: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about shivalayheights
What is the possession date of shivalayheights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for shivalayheights in behind sharadchandra pawar market yard, Nashik is 31 December 2026 — 24 months later than 31 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for shivalayheights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date shivalayheights's builder has filed on MahaRERA, the official one, is 31 December 2026, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of shivalayheights extended?
According to GharKundli's check of MahaRERA records (updated October 2026), shivalayheights's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "FUND ISSUE."; to 31 December 2026, giving the reason "TECHNICAL ISSUE".
What is the RERA number of shivalayheights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of shivalayheights in behind sharadchandra pawar market yard, Nashik is P51600034487.
Is shivalayheights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), shivalayheights is registered as P51600034487 and its status is "Registered and active".
What is the construction status of shivalayheights?
According to GharKundli's check of MahaRERA records (updated October 2026), shivalayheights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Shivalay Heights is 0% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does shivalayheights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is shivalayheights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), shivalayheights is registered on MahaRERA as P51600034487, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if shivalayheights's possession date changes?
The latest dates are on shivalayheights's MahaRERA page (P51600034487). GharKundli's Kundli Watch sends a free WhatsApp update on shivalayheights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does shivalayheights have?
According to GharKundli's check of MahaRERA records (updated October 2026), shivalayheights has one building filed: Shivalay Heights with 9 floors and 60 units.
How much parking does shivalayheights have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 56 covered car parking spaces for shivalayheights.
How big is the land of shivalayheights?
According to GharKundli's check of MahaRERA records (updated October 2026), shivalayheights stands on 1,100 sq m of land (about 0.3 acres), with 4,286 sq m of sanctioned built-up area.
Where can I read reviews of shivalayheights?
Google Maps has reviews of shivalayheights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is shivalayheights?
shivalayheights by SHIVALAY CONSTRUCTION is in behind sharadchandra pawar market yard, Nashik (pincode 422001), Maharashtra, and is registered on MahaRERA as P51600034487, per GharKundli's check of MahaRERA records.
How many homes are in shivalayheights?
According to GharKundli's check of MahaRERA records (updated October 2026), shivalayheights has 56 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.
When was shivalayheights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), shivalayheights was registered on MahaRERA on 11 April 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on shivalayheights?
No court cases are listed for shivalayheights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of shivalayheights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHIVALAY CONSTRUCTION.
Check it yourself on MahaRERA
- How to check the possession date of shivalayheights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Nashik →
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- YUNUS RESIDENCY
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- SHREE VISHVA
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- SARA SERENITY APARTMENT
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.