Skip to content
GharKundli

SAMARTH PLAZA

by PATIL ASSOCIATES · Chetana Nagar Nashik, Nashik

Possession: SAMARTH PLAZA is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600045329. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SAMARTH PLAZA?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on SAMARTH PLAZA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600045329
Status
Completed
Builder
PATIL ASSOCIATES
Location
Chetana Nagar Nashik, Nashik · 422009
Project type
Residential / Group Housing
Registered on
12 May 2022
Completion date at registration
December 2024
Homes
10
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of SAMARTH PLAZA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PATIL ASSOCIATES100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAMARTH PLAZA every month.

SAMARTH PLAZA: buildings, flats and land, as filed on MahaRERA

  • Buildings: PATIL ASSOCIATES (6 floors)
  • Land: 321 sq m (about 0.1 acres) · sanctioned built-up 889 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SAMARTH PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAMARTH PLAZA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAMARTH PLAZA

What is the possession date of SAMARTH PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAMARTH PLAZA in Chetana Nagar Nashik, Nashik is 31 December 2024.

Is the builder's possession date different from the MahaRERA date for SAMARTH PLAZA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAMARTH PLAZA's builder has filed on MahaRERA, the official one, is 31 December 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SAMARTH PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAMARTH PLAZA in Chetana Nagar Nashik, Nashik is P51600045329.

Is SAMARTH PLAZA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA is registered as P51600045329 and its status is "Completed".

What is the construction status of SAMARTH PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA's status on MahaRERA is "Completed". As filed by the builder, slab work on PATIL ASSOCIATES is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SAMARTH PLAZA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SAMARTH PLAZA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA is registered on MahaRERA as P51600045329, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAMARTH PLAZA's possession date changes?

The latest dates are on SAMARTH PLAZA's MahaRERA page (P51600045329). GharKundli's Kundli Watch sends a free WhatsApp update on SAMARTH PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAMARTH PLAZA have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA has one building filed: PATIL ASSOCIATES with 6 floors.

How big is the land of SAMARTH PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA stands on 321 sq m of land (about 0.1 acres), with 889 sq m of sanctioned built-up area.

Where can I read reviews of SAMARTH PLAZA?

Google Maps has reviews of SAMARTH PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAMARTH PLAZA?

SAMARTH PLAZA by PATIL ASSOCIATES is in Chetana Nagar Nashik, Nashik (pincode 422009), Maharashtra, and is registered on MahaRERA as P51600045329, per GharKundli's check of MahaRERA records.

How many homes are in SAMARTH PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA has 10 homes in 1 tower registered on MahaRERA.

When was SAMARTH PLAZA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA was registered on MahaRERA on 12 May 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on SAMARTH PLAZA?

No court cases are listed for SAMARTH PLAZA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SAMARTH PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PATIL ASSOCIATES, which has 2 other projects registered on MahaRERA.

Other projects in Nashik

All 218 projects in CIDCO Colony (422009) →

Other projects by PATIL ASSOCIATES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.