Nirmay Heights
by Nirmay Infra · Agartakli Shiwar, NashikAlso near Upnagar Nashik
Possession date of Nirmay Heights: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600034133, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Nirmay Heights?
How the possession date of Nirmay Heights has moved
31 December 2025
Completion date given when the project was registered
30 December 2026
Extended at the builder's request (MahaRERA application EA19122518771)
Reason the builder gave MahaRERA:
“The project is already completed, and the lift has also been installed. However, the lift certification is still pending due to a technical documentation process at the Lift Regulating Office. Once the certification is received, we will app…” Read the full reason
“The project is already completed, and the lift has also been installed. However, the lift certification is still pending due to a technical documentation process at the Lift Regulating Office. Once the certification is received, we will apply to the local authority for completion approval. All the required documents for this application have already been prepared.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Nirmay Heights’s extension records on MahaRERA (P51600034133), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Nirmay Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600034133
- Status
- Registered and active
- Builder
- Nirmay Infra
- Location
- Agartakli Shiwar, Nashik · 422006
- Project type
- Residential / Group Housing
- Registered on
- 24 Mar 2022
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 14
- Sold or booked
- 64%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Nirmay Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Nirmay Heights | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- Nirmay Heights: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nirmay Heights every month.
Nirmay Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: Nirmay Heights (6 floors, 14 units)
- Land: 346 sq m (about 0.1 acres) · sanctioned built-up 711 sq m
- Boundaries filed include: 9 Mtr Open Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Nirmay Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Nirmay Heights: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Nirmay Heights
What is the possession date of Nirmay Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Nirmay Heights in Agartakli Shiwar, Nashik is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Nirmay Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Nirmay Heights's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Nirmay Heights extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmay Heights's builder applied to MahaRERA to extend the completion date once: to 30 December 2026, giving the reason "The project is already completed, and the lift has also been installed. However, the lift certification is still pending due to a technical documentation process at the Lift Regulating Office. Once the certification is received, we will apply to the local authority for completion approval. All the required documents for this application have already been prepared.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Nirmay Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Nirmay Heights in Agartakli Shiwar, Nashik is P51600034133.
Is Nirmay Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmay Heights is registered as P51600034133 and its status is "Registered and active".
What is the construction status of Nirmay Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmay Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Nirmay Heights is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Nirmay Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Nirmay Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmay Heights is registered on MahaRERA as P51600034133, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Nirmay Heights's possession date changes?
The latest dates are on Nirmay Heights's MahaRERA page (P51600034133). GharKundli's Kundli Watch sends a free WhatsApp update on Nirmay Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Nirmay Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmay Heights has one building filed: Nirmay Heights with 6 floors and 14 units.
How big is the land of Nirmay Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmay Heights stands on 346 sq m of land (about 0.1 acres), with 711 sq m of sanctioned built-up area.
Where can I read reviews of Nirmay Heights?
Google Maps has reviews of Nirmay Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Nirmay Heights?
Nirmay Heights by Nirmay Infra is in Agartakli Shiwar, Nashik (pincode 422006), near Upnagar Nashik, Maharashtra, and is registered on MahaRERA as P51600034133, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9 Mtr Open Road.
How many homes are in Nirmay Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmay Heights has 14 homes in 1 tower registered on MahaRERA, and 64% of them are sold or booked.
When was Nirmay Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmay Heights was registered on MahaRERA on 24 March 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Nirmay Heights?
No court cases are listed for Nirmay Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Nirmay Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Nirmay Infra.
Check it yourself on MahaRERA
- How to check the possession date of Nirmay Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nashik →
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- Quillion Residencies at Quillion Park - Phase 2
- SHIV KUNJ
- YUNUS RESIDENCY
- SHREE VISHVA
- SARA SERENITY APARTMENT
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.