AKSHAR NEST
by AKSHAR DEVELOPERS · Opp. Audumbar Lawns, Nashik
Possession: AKSHAR NEST is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600045473. Status: Completed. Its completion date is now July 2032, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about AKSHAR NEST?
How the possession date of AKSHAR NEST has moved
31 March 2032
Completion date given when the project was registered
31 July 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: AKSHAR NEST’s extension records on MahaRERA (P51600045473), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AKSHAR NEST
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600045473
- Status
- Completed
- Builder
- AKSHAR DEVELOPERS
- Location
- Opp. Audumbar Lawns, Nashik · 422003
- Project type
- Residential / Group Housing
- Registered on
- 19 May 2022
- Completion date at registration
- March 2032
- Latest completion date
- July 2032
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 56
- Sold or booked
- 52%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of AKSHAR NEST, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 100% | 100% | 100% |
| WING B | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers 8 floors
- WING B: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AKSHAR NEST every month.
AKSHAR NEST: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A (8 floors, 28 units) · WING B (8 floors, 28 units)
- Car parking: 34 covered
- Land: 1,416 sq m (about 0.4 acres) · sanctioned built-up 4,983 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of AKSHAR NEST →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AKSHAR NEST: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AKSHAR NEST
What is the possession date of AKSHAR NEST?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for AKSHAR NEST in Opp. Audumbar Lawns, Nashik is 31 July 2032, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for AKSHAR NEST?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AKSHAR NEST's builder has filed on MahaRERA, the official one, is 31 July 2032, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of AKSHAR NEST?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of AKSHAR NEST in Opp. Audumbar Lawns, Nashik is P51600045473.
Is AKSHAR NEST registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR NEST is registered as P51600045473 and its status is "Completed".
What is the construction status of AKSHAR NEST?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR NEST's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does AKSHAR NEST have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is AKSHAR NEST safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR NEST is registered on MahaRERA as P51600045473, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AKSHAR NEST's possession date changes?
The latest dates are on AKSHAR NEST's MahaRERA page (P51600045473). GharKundli's Kundli Watch sends a free WhatsApp update on AKSHAR NEST every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AKSHAR NEST have?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR NEST has 2 buildings filed: WING A with 8 floors and 28 units; WING B with 8 floors and 28 units.
How much parking does AKSHAR NEST have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 34 covered car parking spaces for AKSHAR NEST.
How big is the land of AKSHAR NEST?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR NEST stands on 1,416 sq m of land (about 0.4 acres), with 4,983 sq m of sanctioned built-up area.
Where can I read reviews of AKSHAR NEST?
Google Maps has reviews of AKSHAR NEST written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AKSHAR NEST?
AKSHAR NEST by AKSHAR DEVELOPERS is in Opp. Audumbar Lawns, Nashik (pincode 422003), Maharashtra, and is registered on MahaRERA as P51600045473, per GharKundli's check of MahaRERA records.
How many homes are in AKSHAR NEST?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR NEST has 56 homes in 2 towers registered on MahaRERA, and 52% of them are sold or booked.
When was AKSHAR NEST registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR NEST was registered on MahaRERA on 19 May 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on AKSHAR NEST?
No court cases are listed for AKSHAR NEST on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of AKSHAR NEST?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is AKSHAR DEVELOPERS, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of AKSHAR NEST
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- YUNUS RESIDENCY
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- SHREE VISHVA
- SARA SERENITY APARTMENT
Other projects by AKSHAR DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.