Sunrise Tower
by Akshay Vinod Tatiya And Pratik Prakash Badgujar · Ambad A.S., NashikAlso near Shirdi
Possession: Sunrise Tower is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600045705. Status: Completed.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Sunrise Tower?
How the possession date of Sunrise Tower has moved
31 December 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA05022619734)
Reason the builder gave MahaRERA:
“1) The excavation work took more than expected as there was hard rock and we were forced to do manual work along with small machines with due care in such a way that there should not be vibrations in the residential area around the site whi…” Read the full reason
“1) The excavation work took more than expected as there was hard rock and we were forced to do manual work along with small machines with due care in such a way that there should not be vibrations in the residential area around the site which takes considerably more time than the conventional methods. 2) While excavation and lowering of water level we were supposed to take care since the project land is already surrounded by residential premises and therefore this activity went slowly and took time. 3) The area is which project is to be constructed and completed is entirely a residential ar…”
Source: Sunrise Tower’s extension records on MahaRERA (P51600045705), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sunrise Tower
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600045705
- Status
- Completed
- Builder
- Akshay Vinod Tatiya And Pratik Prakash Badgujar
- Location
- Ambad A.S., Nashik · 422010
- Project type
- Others
- Registered on
- 6 Jun 2022
- Completion date at registration
- December 2025
- Latest completion date
- June 2026
- Delay so far
- 6 months
- Homes
- 21
- Sold or booked
- 45%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Sunrise Tower, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sunrise Tower | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Sunrise Tower: covers Basement Floor + Ground Floor + 7 Habitable Floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sunrise Tower every month.
Sunrise Tower: buildings, flats and land, as filed on MahaRERA
- Buildings: Sunrise Tower (9 floors, 22 units)
- Car parking: 16 covered
- Land: 686 sq m (about 0.2 acres) · sanctioned built-up 2,412 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Sunrise Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sunrise Tower: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sunrise Tower
What is the possession date of Sunrise Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sunrise Tower in Ambad A.S., Nashik is 30 June 2026 — 6 months later than 31 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Sunrise Tower?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sunrise Tower's builder has filed on MahaRERA, the official one, is 30 June 2026, already 6 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sunrise Tower extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Tower's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "1) The excavation work took more than expected as there was hard rock and we were forced to do manual work along with small machines with due care in such a way that there should not be vibrations in the residential area around the site which takes considerably more time than the conventional methods. 2) While excavation and lowering of water level we were supposed to take care since the project land is already surrounded by residential premises and therefore this activity went slowly and took time. 3) The area is which project is to be constructed and completed is entirely a residential ar…".
What is the RERA number of Sunrise Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sunrise Tower in Ambad A.S., Nashik is P51600045705.
Is Sunrise Tower registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Tower is registered as P51600045705 and its status is "Completed".
What is the construction status of Sunrise Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Tower's status on MahaRERA is "Completed". As filed by the builder, slab work on Sunrise Tower is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Sunrise Tower have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sunrise Tower safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Tower is registered on MahaRERA as P51600045705, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Sunrise Tower's possession date changes?
The latest dates are on Sunrise Tower's MahaRERA page (P51600045705). GharKundli's Kundli Watch sends a free WhatsApp update on Sunrise Tower every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sunrise Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Tower has one building filed: Sunrise Tower with 9 floors and 22 units.
How much parking does Sunrise Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 16 covered car parking spaces for Sunrise Tower.
How big is the land of Sunrise Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Tower stands on 686 sq m of land (about 0.2 acres), with 2,412 sq m of sanctioned built-up area.
Where can I read reviews of Sunrise Tower?
Google Maps has reviews of Sunrise Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sunrise Tower?
Sunrise Tower by Akshay Vinod Tatiya And Pratik Prakash Badgujar is in Ambad A.S., Nashik (pincode 422010), near Shirdi, Maharashtra, and is registered on MahaRERA as P51600045705, per GharKundli's check of MahaRERA records.
How many homes are in Sunrise Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Tower has 21 homes in 1 tower registered on MahaRERA, and 45% of them are sold or booked.
When was Sunrise Tower registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Tower was registered on MahaRERA on 6 June 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Sunrise Tower?
No court cases are listed for Sunrise Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Sunrise Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Akshay Vinod Tatiya And Pratik Prakash Badgujar.
Check it yourself on MahaRERA
- How to check the possession date of Sunrise Tower
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 422010
- NIMBUS BUSINESS CENTRE
- SAI CASTLE
- SHIVLEELA APARTMENT
- Shree Ganesh Heights
- Anuveena Heights
- Ananta Heights
- RAGHUNADAN HEIGHTS
- Avadh Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.