SHIVLEELA APARTMENT
by SHREE SADASHIV REALTORS · Pathardi Shiwar, NashikAlso near Ambad A.S, Shirdi
Possession date of SHIVLEELA APARTMENT: 31 July 2027, moved from 31 March 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600051904, and currently active. Its completion date has moved from March 2026 to July 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHIVLEELA APARTMENT?
How the possession date of SHIVLEELA APARTMENT has moved
31 March 2026
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA27032620406)
Reason the builder gave MahaRERA: “Procedural delay in Construction Work due to slow-market scenarios and an environment of fear due to International War in the potential home buyers”
31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHIVLEELA APARTMENT’s extension records on MahaRERA (P51600051904), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHIVLEELA APARTMENT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600051904
- Status
- Registered and active
- Builder
- SHREE SADASHIV REALTORS
- Location
- Pathardi Shiwar, Nashik · 422010
- Project type
- Residential / Group Housing
- Registered on
- 7 Jul 2023
- Completion date at registration
- March 2026
- Latest completion date
- July 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 47
- Sold or booked
- 43%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHIVLEELA APARTMENT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHIVLEELA APARTMENT | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SHIVLEELA APARTMENT: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHIVLEELA APARTMENT every month.
SHIVLEELA APARTMENT: buildings, flats and land, as filed on MahaRERA
- Buildings: SHIVLEELA APARTMENT (7 floors, 47 units)
- Land: 705 sq m (about 0.2 acres) · sanctioned built-up 2,009 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHIVLEELA APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHIVLEELA APARTMENT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHIVLEELA APARTMENT
What is the possession date of SHIVLEELA APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHIVLEELA APARTMENT in Pathardi Shiwar, Nashik is 31 July 2027 — 12 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHIVLEELA APARTMENT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHIVLEELA APARTMENT's builder has filed on MahaRERA, the official one, is 31 July 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHIVLEELA APARTMENT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVLEELA APARTMENT's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "Procedural delay in Construction Work due to slow-market scenarios and an environment of fear due to International War in the potential home buyers". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SHIVLEELA APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHIVLEELA APARTMENT in Pathardi Shiwar, Nashik is P51600051904.
Is SHIVLEELA APARTMENT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVLEELA APARTMENT is registered as P51600051904 and its status is "Registered and active".
What is the construction status of SHIVLEELA APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVLEELA APARTMENT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHIVLEELA APARTMENT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SHIVLEELA APARTMENT have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SHIVLEELA APARTMENT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVLEELA APARTMENT is registered on MahaRERA as P51600051904, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHIVLEELA APARTMENT's possession date changes?
The latest dates are on SHIVLEELA APARTMENT's MahaRERA page (P51600051904). GharKundli's Kundli Watch sends a free WhatsApp update on SHIVLEELA APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHIVLEELA APARTMENT have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVLEELA APARTMENT has one building filed: SHIVLEELA APARTMENT with 7 floors and 47 units.
How big is the land of SHIVLEELA APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVLEELA APARTMENT stands on 705 sq m of land (about 0.2 acres), with 2,009 sq m of sanctioned built-up area.
Where can I read reviews of SHIVLEELA APARTMENT?
Google Maps has reviews of SHIVLEELA APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHIVLEELA APARTMENT?
SHIVLEELA APARTMENT by SHREE SADASHIV REALTORS is in Pathardi Shiwar, Nashik (pincode 422010), near Ambad A.S, Shirdi, Maharashtra, and is registered on MahaRERA as P51600051904, per GharKundli's check of MahaRERA records.
How many homes are in SHIVLEELA APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVLEELA APARTMENT has 47 homes in 1 tower registered on MahaRERA, and 43% of them are sold or booked.
When was SHIVLEELA APARTMENT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVLEELA APARTMENT was registered on MahaRERA on 7 July 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SHIVLEELA APARTMENT?
No court cases are listed for SHIVLEELA APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SHIVLEELA APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE SADASHIV REALTORS.
Check it yourself on MahaRERA
- How to check the possession date of SHIVLEELA APARTMENT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nashik →
Other projects in pincode 422010
- NIMBUS BUSINESS CENTRE
- Sunrise Tower
- SAI CASTLE
- Shree Ganesh Heights
- Anuveena Heights
- Ananta Heights
- RAGHUNADAN HEIGHTS
- Avadh Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.