Possession date of SKYLINE PLAZA: 15 February 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600046920, and currently active. Its completion date is now February 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SKYLINE PLAZA?
How the possession date of SKYLINE PLAZA has moved
15 October 2027
Completion date given when the project was registered
15 February 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SKYLINE PLAZA’s extension records on MahaRERA (P51600046920), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SKYLINE PLAZA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the February 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600046920
- Status
- Registered and active
- Builder
- SKYLINE BUILDERS AND DEVELOPERS
- Location
- Nr Ashwini Hospital, Govind Nagar, Nashik · 422009
- Project type
- Others
- Registered on
- 20 Sep 2022
- Completion date at registration
- October 2027
- Latest completion date
- February 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 15
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of SKYLINE PLAZA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SKYLINE PLAZA | 100% | 45% | 5% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SKYLINE PLAZA every month.
SKYLINE PLAZA: buildings, flats and land, as filed on MahaRERA
- Buildings: SKYLINE PLAZA (7 floors)
- Land: 398 sq m (about 0.1 acres) · sanctioned built-up 1,282 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SKYLINE PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SKYLINE PLAZA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SKYLINE PLAZA
What is the possession date of SKYLINE PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SKYLINE PLAZA in Nr Ashwini Hospital, Govind Nagar, Nashik is 15 February 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SKYLINE PLAZA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SKYLINE PLAZA's builder has filed on MahaRERA, the official one, is 15 February 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SKYLINE PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SKYLINE PLAZA in Nr Ashwini Hospital, Govind Nagar, Nashik is P51600046920.
Is SKYLINE PLAZA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SKYLINE PLAZA is registered as P51600046920 and its status is "Registered and active".
What is the construction status of SKYLINE PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), SKYLINE PLAZA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SKYLINE PLAZA is 45% done and internal work 5%. GharKundli's full report compares construction progress with the deadline.
Does SKYLINE PLAZA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SKYLINE PLAZA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SKYLINE PLAZA is registered on MahaRERA as P51600046920, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SKYLINE PLAZA's possession date changes?
The latest dates are on SKYLINE PLAZA's MahaRERA page (P51600046920). GharKundli's Kundli Watch sends a free WhatsApp update on SKYLINE PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SKYLINE PLAZA have?
According to GharKundli's check of MahaRERA records (updated November 2026), SKYLINE PLAZA has one building filed: SKYLINE PLAZA with 7 floors.
How big is the land of SKYLINE PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), SKYLINE PLAZA stands on 398 sq m of land (about 0.1 acres), with 1,282 sq m of sanctioned built-up area.
Where can I read reviews of SKYLINE PLAZA?
Google Maps has reviews of SKYLINE PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SKYLINE PLAZA?
SKYLINE PLAZA by SKYLINE BUILDERS AND DEVELOPERS is in Nr Ashwini Hospital, Govind Nagar, Nashik (pincode 422009), Maharashtra, and is registered on MahaRERA as P51600046920, per GharKundli's check of MahaRERA records.
How many homes are in SKYLINE PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), SKYLINE PLAZA has 15 homes in 1 tower registered on MahaRERA.
When was SKYLINE PLAZA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SKYLINE PLAZA was registered on MahaRERA on 20 September 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on SKYLINE PLAZA?
No court cases are listed for SKYLINE PLAZA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SKYLINE PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SKYLINE BUILDERS AND DEVELOPERS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SKYLINE PLAZA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Nashik →
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- YUNUS RESIDENCY
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- SHREE VISHVA
- SARA SERENITY APARTMENT
Other projects by SKYLINE BUILDERS AND DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.