by Ravindra Developers Private Limited · Kulkarni Garden, NashikAlso near Gole Colony, Sawarkar Nagar, Gandhi Nagar (Nashik)

Possession: Yogesh Co-Operative Housing Society is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600048451. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Yogesh Co-Operative Housing Society?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Yogesh Co-Operative Housing Society

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600048451
Status
Completed
Builder
Ravindra Developers Private Limited
Location
Kulkarni Garden, Nashik · 422002
Project type
Residential / Group Housing
Registered on
3 Jan 2023
Completion date at registration
December 2025
Homes
44
Sold or booked
100%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Yogesh Co-Operative Housing Society, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Yogesh Co-Operative Housing Society100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Yogesh Co-Operative Housing Society: covers 14 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Yogesh Co-Operative Housing Society every month.

Yogesh Co-Operative Housing Society: buildings, flats and land, as filed on MahaRERA

  • Buildings: Yogesh Co-Operative Housing Society (14 floors, 44 units)
  • Car parking: 104 covered, 134 open
  • Land: 2,324 sq m (about 0.6 acres) · sanctioned built-up 5,619 sq m
  • Boundaries filed include: Colony Road and Kulkarni Garden
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Ravindra Developers has 6 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA.

Read Google reviews of Yogesh Co-Operative Housing Society →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Yogesh Co-Operative Housing Society: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Yogesh Co-Operative Housing Society

What is the possession date of Yogesh Co-Operative Housing Society?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Yogesh Co-Operative Housing Society in Kulkarni Garden, Nashik is 31 December 2025.

Is the builder's possession date different from the MahaRERA date for Yogesh Co-Operative Housing Society?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Yogesh Co-Operative Housing Society's builder has filed on MahaRERA, the official one, is 31 December 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Yogesh Co-Operative Housing Society?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Yogesh Co-Operative Housing Society in Kulkarni Garden, Nashik is P51600048451.

Is Yogesh Co-Operative Housing Society registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Yogesh Co-Operative Housing Society is registered as P51600048451 and its status is "Completed".

What is the construction status of Yogesh Co-Operative Housing Society?

According to GharKundli's check of MahaRERA records (updated November 2026), Yogesh Co-Operative Housing Society's status on MahaRERA is "Completed". As filed by the builder, slab work on Yogesh Co-Operative Housing Society is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Yogesh Co-Operative Housing Society have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Yogesh Co-Operative Housing Society safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Yogesh Co-Operative Housing Society is registered on MahaRERA as P51600048451, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Yogesh Co-Operative Housing Society's possession date changes?

The latest dates are on Yogesh Co-Operative Housing Society's MahaRERA page (P51600048451). GharKundli's Kundli Watch sends a free WhatsApp update on Yogesh Co-Operative Housing Society every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Yogesh Co-Operative Housing Society have?

According to GharKundli's check of MahaRERA records (updated November 2026), Yogesh Co-Operative Housing Society has one building filed: Yogesh Co-Operative Housing Society with 14 floors and 44 units.

How much parking does Yogesh Co-Operative Housing Society have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 104 covered and 134 open car parking spaces for Yogesh Co-Operative Housing Society.

How big is the land of Yogesh Co-Operative Housing Society?

According to GharKundli's check of MahaRERA records (updated November 2026), Yogesh Co-Operative Housing Society stands on 2,324 sq m of land (about 0.6 acres), with 5,619 sq m of sanctioned built-up area.

What is the track record of Yogesh Co-Operative Housing Society's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Ravindra Developers has 6 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Yogesh Co-Operative Housing Society?

Google Maps has reviews of Yogesh Co-Operative Housing Society written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Yogesh Co-Operative Housing Society?

Yogesh Co-Operative Housing Society by Ravindra Developers Private Limited is in Kulkarni Garden, Nashik (pincode 422002), near Gole Colony, Sawarkar Nagar, Gandhi Nagar (Nashik), Maharashtra, and is registered on MahaRERA as P51600048451, per GharKundli's check of MahaRERA records. Its boundaries filed there include Colony Road and Kulkarni Garden.

How many homes are in Yogesh Co-Operative Housing Society?

According to GharKundli's check of MahaRERA records (updated November 2026), Yogesh Co-Operative Housing Society has 44 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was Yogesh Co-Operative Housing Society registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Yogesh Co-Operative Housing Society was registered on MahaRERA on 3 January 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Yogesh Co-Operative Housing Society?

No court cases are listed for Yogesh Co-Operative Housing Society on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Yogesh Co-Operative Housing Society?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Ravindra Developers Private Limited, which has 2 other projects registered on MahaRERA.

Other projects in Nashik

All 54 projects in Gole Colony (422002) →

Other projects by Ravindra Developers Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.