Possession date of MOONGIPA ARCADE: 30 April 2029, moved from 30 December 2023 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800007285, and currently active. Its completion date has moved from December 2023 to April 2029: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 24 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about MOONGIPA ARCADE?
GharKundli’s full report on MOONGIPA ARCADE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 24 complaints, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800007285
- Status
- Registered and active
- Builder
- MOONGIPA REALTY PRIVATE LIMITED
- Location
- Azad Nagar S.O (Mumbai), Mumbai · 400053
- Project type
- Others
- Registered on
- 17 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- April 2029
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 355
- Sold or booked
- 75%
- Towers
- 9
- Complaints on MahaRERA
- 24
- Court cases listed
- 0
- Appeals at the tribunal
- 6
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of MOONGIPA ARCADE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 100% | 100% | 100% | 95% |
| B | 100% | 100% | 100% | 95% |
| C | 100% | 100% | 100% | 95% |
| D | 100% | 100% | 100% | 95% |
| E | 100% | 100% | 100% | 95% |
| F | 100% | 100% | 100% | 95% |
| G1 AND G2 | 0% | 0% | 0% | 0% |
| I 1 AND I 2 | 0% | 0% | 0% | 0% |
| H | 100% | 90% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- A: covers 14 floors
- B: covers 14 floors
- C: covers 14 floors
- D: covers 14 floors
- E: covers 14 floors
- F: covers 14 floors
- G1 AND G2: covers 15 floors
- I 1 AND I 2: covers Plinth level
- H: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MOONGIPA ARCADE every month.
MOONGIPA ARCADE: buildings, flats and land, as filed on MahaRERA
- Buildings: A (16 floors, 40 units) · B (16 floors, 173 units) · C (16 floors, 40 units) · D (16 floors, 164 units) · E (16 floors, 40 units) · F (16 floors, 186 units) · G1 AND G2 (17 floors, 163 units) · I 1 AND I 2 (18 floors, 161 units) · and 1 more
- Land: 10,278 sq m (about 2.5 acres) · sanctioned built-up 24,379 sq m · recreational space 527 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of MOONGIPA ARCADE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MOONGIPA ARCADE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MOONGIPA ARCADE
What is the possession date of MOONGIPA ARCADE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MOONGIPA ARCADE in Azad Nagar S.O (Mumbai), Mumbai is 30 April 2029 — 60 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for MOONGIPA ARCADE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MOONGIPA ARCADE's builder has filed on MahaRERA, the official one, is 30 April 2029, already 60 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of MOONGIPA ARCADE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MOONGIPA ARCADE in Azad Nagar S.O (Mumbai), Mumbai is P51800007285.
Is MOONGIPA ARCADE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MOONGIPA ARCADE is registered as P51800007285 and its status is "Registered and active".
What is the construction status of MOONGIPA ARCADE?
According to GharKundli's check of MahaRERA records (updated November 2026), MOONGIPA ARCADE's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 9 towers. GharKundli's full report compares construction progress with the deadline.
Does MOONGIPA ARCADE have complaints on MahaRERA?
24 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is MOONGIPA ARCADE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), MOONGIPA ARCADE is registered on MahaRERA as P51800007285, its completion date has moved 60 months since registration and 24 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MOONGIPA ARCADE's possession date changes?
The latest dates are on MOONGIPA ARCADE's MahaRERA page (P51800007285). GharKundli's Kundli Watch sends a free WhatsApp update on MOONGIPA ARCADE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MOONGIPA ARCADE have?
According to GharKundli's check of MahaRERA records (updated November 2026), MOONGIPA ARCADE has 9 buildings filed: A with 16 floors and 40 units; B with 16 floors and 173 units; C with 16 floors and 40 units; D with 16 floors and 164 units; E with 16 floors and 40 units; F with 16 floors and 186 units; and 3 more.
How big is the land of MOONGIPA ARCADE?
According to GharKundli's check of MahaRERA records (updated November 2026), MOONGIPA ARCADE stands on 10,278 sq m of land (about 2.5 acres), with 24,379 sq m of sanctioned built-up area and 527 sq m of recreational open space.
Where can I read reviews of MOONGIPA ARCADE?
Google Maps has reviews of MOONGIPA ARCADE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 24 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MOONGIPA ARCADE?
MOONGIPA ARCADE by MOONGIPA REALTY PRIVATE LIMITED is in Azad Nagar S.O (Mumbai), Mumbai (pincode 400053), near Andheri West, D. N. Nagar, Vile Parle East, Maharashtra, and is registered on MahaRERA as P51800007285, per GharKundli's check of MahaRERA records.
How many homes are in MOONGIPA ARCADE?
According to GharKundli's check of MahaRERA records (updated November 2026), MOONGIPA ARCADE has 355 homes in 9 towers registered on MahaRERA, and 75% of them are sold or booked.
When was MOONGIPA ARCADE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MOONGIPA ARCADE was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MOONGIPA ARCADE?
No court cases are listed for MOONGIPA ARCADE on MahaRERA, and 6 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of MOONGIPA ARCADE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MOONGIPA REALTY PRIVATE LIMITED, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of MOONGIPA ARCADE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in pincode 400053
All 161 projects in Andheri West (400053) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.