SWASTIK MANGAL APARTMENT
by SHREEMANGAL CONSTRUCTION · Kamatwade, Nashik
Possession date of SWASTIK MANGAL APARTMENT: 31 July 2027, moved from 31 March 2025 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600051953, and currently active. Its completion date has moved from March 2025 to July 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SWASTIK MANGAL APARTMENT?
How the possession date of SWASTIK MANGAL APARTMENT has moved
31 March 2025
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA09052501019)
Reason the builder gave MahaRERA:
“Workforce and Material Issues: • Labor Shortages: Availability of skilled manpower, especially in structural and MEP (Mechanical, Electrical & Plumbing) areas, was restricted due to migration and contractual disruptions, slowing down projec…” Read the full reason
“Workforce and Material Issues: • Labor Shortages: Availability of skilled manpower, especially in structural and MEP (Mechanical, Electrical & Plumbing) areas, was restricted due to migration and contractual disruptions, slowing down project execution. • Supply Chain Disruptions: Escalation in raw material costs and delays in delivery of essential materials further extended the project timeline. b. Financial Constraints: • Due to market slowdown, the project faced liquidity constraints, delaying scheduled construction activities. c. Design Changes and Legal Issues: • Minor design alteration…”31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SWASTIK MANGAL APARTMENT’s extension records on MahaRERA (P51600051953), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SWASTIK MANGAL APARTMENT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600051953
- Status
- Registered and active
- Builder
- SHREEMANGAL CONSTRUCTION
- Location
- Kamatwade, Nashik · 422010
- Project type
- Others
- Registered on
- 13 Jul 2023
- Completion date at registration
- March 2025
- Latest completion date
- July 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 203
- Sold or booked
- 62%
- Towers
- 2
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SWASTIK MANGAL APARTMENT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SWASTIK MANGAL APARTMENT -A WING | 100% | 100% | 100% | 90% |
| SWASTIK MANGAL APARTMENT -B WING | 100% | 100% | 90% | 80% |
Commencement certificate (CC), as filed on MahaRERA
Latest CC order on MahaRERA: dated 13/06/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SWASTIK MANGAL APARTMENT every month.
SWASTIK MANGAL APARTMENT: buildings, flats and land, as filed on MahaRERA
- Buildings: SWASTIK MANGAL APARTMENT -A WING (14 floors, 120 units) · SWASTIK MANGAL APARTMENT -B WING (13 floors, 98 units)
- Car parking: 58 covered
- Land: 2,394 sq m (about 0.6 acres) · sanctioned built-up 11,439 sq m
- Boundaries filed include: AMBAD KAMATWADE ROAD
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SWASTIK MANGAL APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SWASTIK MANGAL APARTMENT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SWASTIK MANGAL APARTMENT
What is the possession date of SWASTIK MANGAL APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SWASTIK MANGAL APARTMENT in Kamatwade, Nashik is 31 July 2027 — 24 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SWASTIK MANGAL APARTMENT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SWASTIK MANGAL APARTMENT's builder has filed on MahaRERA, the official one, is 31 July 2027, already 24 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SWASTIK MANGAL APARTMENT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SWASTIK MANGAL APARTMENT's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "Workforce and Material Issues: • Labor Shortages: Availability of skilled manpower, especially in structural and MEP (Mechanical, Electrical & Plumbing) areas, was restricted due to migration and contractual disruptions, slowing down project execution. • Supply Chain Disruptions: Escalation in raw material costs and delays in delivery of essential materials further extended the project timeline. b. Financial Constraints: • Due to market slowdown, the project faced liquidity constraints, delaying scheduled construction activities. c. Design Changes and Legal Issues: • Minor design alteration…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SWASTIK MANGAL APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SWASTIK MANGAL APARTMENT in Kamatwade, Nashik is P51600051953.
Is SWASTIK MANGAL APARTMENT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SWASTIK MANGAL APARTMENT is registered as P51600051953 and its status is "Registered and active".
What is the construction status of SWASTIK MANGAL APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), SWASTIK MANGAL APARTMENT's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does SWASTIK MANGAL APARTMENT have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SWASTIK MANGAL APARTMENT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SWASTIK MANGAL APARTMENT is registered on MahaRERA as P51600051953, its completion date has moved 24 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SWASTIK MANGAL APARTMENT's possession date changes?
The latest dates are on SWASTIK MANGAL APARTMENT's MahaRERA page (P51600051953). GharKundli's Kundli Watch sends a free WhatsApp update on SWASTIK MANGAL APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SWASTIK MANGAL APARTMENT have?
According to GharKundli's check of MahaRERA records (updated October 2026), SWASTIK MANGAL APARTMENT has 2 buildings filed: SWASTIK MANGAL APARTMENT -A WING with 14 floors and 120 units; SWASTIK MANGAL APARTMENT -B WING with 13 floors and 98 units.
How much parking does SWASTIK MANGAL APARTMENT have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 58 covered car parking spaces for SWASTIK MANGAL APARTMENT.
How big is the land of SWASTIK MANGAL APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), SWASTIK MANGAL APARTMENT stands on 2,394 sq m of land (about 0.6 acres), with 11,439 sq m of sanctioned built-up area.
Where can I read reviews of SWASTIK MANGAL APARTMENT?
Google Maps has reviews of SWASTIK MANGAL APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SWASTIK MANGAL APARTMENT?
SWASTIK MANGAL APARTMENT by SHREEMANGAL CONSTRUCTION is in Kamatwade, Nashik (pincode 422010), Maharashtra, and is registered on MahaRERA as P51600051953, per GharKundli's check of MahaRERA records. Its boundaries filed there include AMBAD KAMATWADE ROAD.
How many homes are in SWASTIK MANGAL APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), SWASTIK MANGAL APARTMENT has 203 homes in 2 towers registered on MahaRERA, and 62% of them are sold or booked.
When was SWASTIK MANGAL APARTMENT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SWASTIK MANGAL APARTMENT was registered on MahaRERA on 13 July 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SWASTIK MANGAL APARTMENT?
No court cases are listed for SWASTIK MANGAL APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SWASTIK MANGAL APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREEMANGAL CONSTRUCTION.
Check it yourself on MahaRERA
- How to check the possession date of SWASTIK MANGAL APARTMENT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nashik →
Other projects in Nashik
- RAJASHREE SIDDHIVINAYAK
- SOLARIS PARK
- NISHIGANDH APARTMENT
- Fortunes Emerald Park
- Laxmi Commercial Complex
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- YUNUS RESIDENCY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.