ALPINE
by PUSHPRIT REALTY · Panchavati, Nashik
Possession date of ALPINE: 31 July 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600051628, and currently active. Its completion date is now July 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ALPINE?
How the possession date of ALPINE has moved
31 March 2028
Completion date given when the project was registered
31 July 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ALPINE’s extension records on MahaRERA (P51600051628), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ALPINE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600051628
- Status
- Registered and active
- Builder
- PUSHPRIT REALTY
- Location
- Panchavati, Nashik · 422003
- Project type
- Others
- Registered on
- 27 Jun 2023
- Completion date at registration
- March 2028
- Latest completion date
- July 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 144
- Sold or booked
- 80%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ALPINE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING B | 100% | 100% | 100% | 20% |
| BUILDING A | 100% | 100% | 97% | 90% |
| BUILDING C | 100% | 30% | 10% | 0% |
| BUILDING D | 100% | 30% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING B: covers 8 floors
- BUILDING A: covers 8 floors
- BUILDING C: covers 8 floors
- BUILDING D: covers 8 floors
Latest CC order on MahaRERA: dated 28/03/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ALPINE every month.
ALPINE: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING B (8 floors, 56 units) · BUILDING A (8 floors, 66 units) · BUILDING C (8 floors, 36 units) · BUILDING D (8 floors, 24 units)
- Car parking: 144 covered
- Land: 4,585 sq m (about 1.1 acres) · sanctioned built-up 13,660 sq m
- Boundaries filed include: 9 MTRS COLONY ROAD
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ALPINE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ALPINE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ALPINE
What is the possession date of ALPINE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ALPINE in Panchavati, Nashik is 31 July 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ALPINE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ALPINE's builder has filed on MahaRERA, the official one, is 31 July 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of ALPINE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ALPINE in Panchavati, Nashik is P51600051628.
Is ALPINE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ALPINE is registered as P51600051628 and its status is "Registered and active".
What is the construction status of ALPINE?
According to GharKundli's check of MahaRERA records (updated October 2026), ALPINE's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 30% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does ALPINE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is ALPINE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ALPINE is registered on MahaRERA as P51600051628, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ALPINE's possession date changes?
The latest dates are on ALPINE's MahaRERA page (P51600051628). GharKundli's Kundli Watch sends a free WhatsApp update on ALPINE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ALPINE have?
According to GharKundli's check of MahaRERA records (updated October 2026), ALPINE has 4 buildings filed: BUILDING B with 8 floors and 56 units; BUILDING A with 8 floors and 66 units; BUILDING C with 8 floors and 36 units; BUILDING D with 8 floors and 24 units.
How much parking does ALPINE have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 144 covered car parking spaces for ALPINE.
How big is the land of ALPINE?
According to GharKundli's check of MahaRERA records (updated October 2026), ALPINE stands on 4,585 sq m of land (about 1.1 acres), with 13,660 sq m of sanctioned built-up area.
Where can I read reviews of ALPINE?
Google Maps has reviews of ALPINE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ALPINE?
ALPINE by PUSHPRIT REALTY is in Panchavati, Nashik (pincode 422003), Maharashtra, and is registered on MahaRERA as P51600051628, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9 MTRS COLONY ROAD.
How many homes are in ALPINE?
According to GharKundli's check of MahaRERA records (updated October 2026), ALPINE has 144 homes in 4 towers registered on MahaRERA, and 80% of them are sold or booked.
When was ALPINE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ALPINE was registered on MahaRERA on 27 June 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on ALPINE?
No court cases are listed for ALPINE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ALPINE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PUSHPRIT REALTY.
Check it yourself on MahaRERA
- How to check the possession date of ALPINE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Nashik →
Other projects in pincode 422003
- Vastu Shilp
- SHIVSUNDAR HEIGHTS
- SHREE HARIHAR GALAXY
- PADMASHREE PARK
- Saubhagya Pride
- SAMARTH DATTAKRUPA
- Amber Co. Op. Hsg. Soc.
- AKSHAR GARDEN
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.