Babubhais Krishnakunj

by Vinod Dilipkumar Majithia · Near Pumping Station, Chavan Colony, NashikAlso near College road

Possession date of Babubhais Krishnakunj: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600052493, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Babubhais Krishnakunj?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Babubhais Krishnakunj has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Babubhais Krishnakunj’s extension records on MahaRERA (P51600052493), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Babubhais Krishnakunj

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600052493
Status
Registered and active
Builder
Vinod Dilipkumar Majithia
Location
Near Pumping Station, Chavan Colony, Nashik · 422013
Project type
Residential / Group Housing
Registered on
8 Sep 2023
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
21
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Babubhais Krishnakunj, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Babubhais Krishnakunj100%50%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Babubhais Krishnakunj every month.

Babubhais Krishnakunj: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Babubhais Krishnakunj →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Babubhais Krishnakunj: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Babubhais Krishnakunj

What is the possession date of Babubhais Krishnakunj?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Babubhais Krishnakunj in Near Pumping Station, Chavan Colony, Nashik is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Babubhais Krishnakunj?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Babubhais Krishnakunj's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Babubhais Krishnakunj?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Babubhais Krishnakunj in Near Pumping Station, Chavan Colony, Nashik is P51600052493.

Is Babubhais Krishnakunj registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Babubhais Krishnakunj is registered as P51600052493 and its status is "Registered and active".

What is the construction status of Babubhais Krishnakunj?

According to GharKundli's check of MahaRERA records (updated November 2026), Babubhais Krishnakunj's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Babubhais Krishnakunj is 50% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Babubhais Krishnakunj have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Babubhais Krishnakunj safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Babubhais Krishnakunj is registered on MahaRERA as P51600052493, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Babubhais Krishnakunj's possession date changes?

The latest dates are on Babubhais Krishnakunj's MahaRERA page (P51600052493). GharKundli's Kundli Watch sends a free WhatsApp update on Babubhais Krishnakunj every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Babubhais Krishnakunj have?

According to GharKundli's check of MahaRERA records (updated November 2026), Babubhais Krishnakunj has one building filed: Babubhais Krishnakunj with 9 floors.

How big is the land of Babubhais Krishnakunj?

According to GharKundli's check of MahaRERA records (updated November 2026), Babubhais Krishnakunj stands on 937 sq m of land (about 0.2 acres), with 2,987 sq m of sanctioned built-up area.

Where can I read reviews of Babubhais Krishnakunj?

Google Maps has reviews of Babubhais Krishnakunj written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Babubhais Krishnakunj?

Babubhais Krishnakunj by Vinod Dilipkumar Majithia is in Near Pumping Station, Chavan Colony, Nashik (pincode 422013), near College road, Maharashtra, and is registered on MahaRERA as P51600052493, per GharKundli's check of MahaRERA records.

How many homes are in Babubhais Krishnakunj?

According to GharKundli's check of MahaRERA records (updated November 2026), Babubhais Krishnakunj has 21 homes in 1 tower registered on MahaRERA.

When was Babubhais Krishnakunj registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Babubhais Krishnakunj was registered on MahaRERA on 8 September 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Babubhais Krishnakunj?

No court cases are listed for Babubhais Krishnakunj on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Babubhais Krishnakunj?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Vinod Dilipkumar Majithia.

All projects with possession due in 2027 in Nashik →

Other projects in Nashik

All 115 projects in Sawarkar Nagar (422013) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.