SHREEJI ELEVATE
by SHREEJI LIFE SPACE · Rajiv Nagar, Nashik
Possession date of SHREEJI ELEVATE: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600053196, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SHREEJI ELEVATE?
How the possession date of SHREEJI ELEVATE has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHREEJI ELEVATE’s extension records on MahaRERA (P51600053196), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHREEJI ELEVATE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600053196
- Status
- Registered and active
- Builder
- SHREEJI LIFE SPACE
- Location
- Rajiv Nagar, Nashik · 422009
- Project type
- Others
- Registered on
- 17 Oct 2023
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 176
- Sold or booked
- 68%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 9
Construction progress of SHREEJI ELEVATE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 100% | 70% | 50% |
| WING B | 100% | 100% | 70% | 50% |
| WING C | 100% | 100% | 70% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers 17 floors
- WING B: covers 16 floors
- WING C: covers 17 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREEJI ELEVATE every month.
SHREEJI ELEVATE: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A (17 floors, 66 units) · WING B (16 floors, 56 units) · WING C (17 floors, 60 units)
- Car parking: 237 covered
- Land: 3,999 sq m (about 1.0 acres) · sanctioned built-up 16,738 sq m · recreational space 400 sq m
The builder’s record and reviews
Shreeji Life Space (a group of 3 linked companies) has 16 projects on MahaRERA since 2020, this one included. Of the 13 GharKundli has checked: 5 finished, 4 within the promised date and 1 needed more time (typically 1 months); 8 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of SHREEJI ELEVATE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHREEJI ELEVATE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHREEJI ELEVATE
What is the possession date of SHREEJI ELEVATE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHREEJI ELEVATE in Rajiv Nagar, Nashik is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHREEJI ELEVATE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREEJI ELEVATE's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SHREEJI ELEVATE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHREEJI ELEVATE in Rajiv Nagar, Nashik is P51600053196.
Is SHREEJI ELEVATE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEJI ELEVATE is registered as P51600053196 and its status is "Registered and active".
What is the construction status of SHREEJI ELEVATE?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEJI ELEVATE's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does SHREEJI ELEVATE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SHREEJI ELEVATE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEJI ELEVATE is registered on MahaRERA as P51600053196, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHREEJI ELEVATE's possession date changes?
The latest dates are on SHREEJI ELEVATE's MahaRERA page (P51600053196). GharKundli's Kundli Watch sends a free WhatsApp update on SHREEJI ELEVATE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHREEJI ELEVATE have?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEJI ELEVATE has 3 buildings filed: WING A with 17 floors and 66 units; WING B with 16 floors and 56 units; WING C with 17 floors and 60 units.
How much parking does SHREEJI ELEVATE have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 237 covered car parking spaces for SHREEJI ELEVATE.
How big is the land of SHREEJI ELEVATE?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEJI ELEVATE stands on 3,999 sq m of land (about 1.0 acres), with 16,738 sq m of sanctioned built-up area and 400 sq m of recreational open space.
What is the track record of SHREEJI ELEVATE's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Shreeji Life Space (a group of 3 linked companies) has 16 projects on MahaRERA since 2020, this one included. Of the 13 GharKundli has checked: 5 finished, 4 within the promised date and 1 needed more time (typically 1 months); 8 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHREEJI ELEVATE?
Google Maps has reviews of SHREEJI ELEVATE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHREEJI ELEVATE?
SHREEJI ELEVATE by SHREEJI LIFE SPACE is in Rajiv Nagar, Nashik (pincode 422009), Maharashtra, and is registered on MahaRERA as P51600053196, per GharKundli's check of MahaRERA records.
How many homes are in SHREEJI ELEVATE?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEJI ELEVATE has 176 homes in 3 towers registered on MahaRERA, and 68% of them are sold or booked.
When was SHREEJI ELEVATE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEJI ELEVATE was registered on MahaRERA on 17 October 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SHREEJI ELEVATE?
No court cases are listed for SHREEJI ELEVATE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SHREEJI ELEVATE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREEJI LIFE SPACE, which has 9 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SHREEJI ELEVATE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Nashik →
Other projects in Nashik
- PEARL RESIDENCY
- Fortunes Emerald Park
- Laxmi Commercial Complex
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- SHIV KUNJ
- YUNUS RESIDENCY
- Quillion Residencies at Quillion Park - Phase 2
- SHREE VISHVA
Other projects by SHREEJI LIFE SPACE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.