SAI LAXMI CHSL

by SHREEJANI DEVELOPERS · Ckp Colony, MumbaiAlso near Borivali West, Shimpoli, Eksar Village

Possession date of SAI LAXMI CHSL: 31 December 2018, moved from 31 December 2017 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800013373. Status: Lapsed (registration period ended). 5 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2018) has passed.

What do you want to know about SAI LAXMI CHSL?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on SAI LAXMI CHSL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 complaints, and how it ended
  • Construction pace against the December 2018 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800013373
Status
Lapsed (registration period ended)
Builder
SHREEJANI DEVELOPERS
Location
Ckp Colony, Mumbai · 400092
Project type
Residential / Group Housing
Registered on
26 Sep 2017
Completion date at registration
December 2017
Latest completion date
December 2018
Delay so far
12 months
Homes
12
Towers
1
Complaints on MahaRERA
5
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of SAI LAXMI CHSL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI LAXMI1%0%100%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI LAXMI CHSL every month.

SAI LAXMI CHSL: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SAI LAXMI CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI LAXMI CHSL: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI LAXMI CHSL

What is the possession date of SAI LAXMI CHSL?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI LAXMI CHSL in Ckp Colony, Mumbai is 31 December 2018 — 12 months later than 31 December 2017, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SAI LAXMI CHSL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI LAXMI CHSL's builder has filed on MahaRERA, the official one, is 31 December 2018, already 12 months later than the 31 December 2017 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SAI LAXMI CHSL?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI LAXMI CHSL in Ckp Colony, Mumbai is P51800013373.

Is SAI LAXMI CHSL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI LAXMI CHSL is registered as P51800013373 and its status is "Lapsed (registration period ended)".

What is the construction status of SAI LAXMI CHSL?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI LAXMI CHSL's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAI LAXMI is 0% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SAI LAXMI CHSL have complaints on MahaRERA?

5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SAI LAXMI CHSL safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI LAXMI CHSL is registered on MahaRERA as P51800013373, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI LAXMI CHSL's possession date changes?

The latest dates are on SAI LAXMI CHSL's MahaRERA page (P51800013373). GharKundli's Kundli Watch sends a free WhatsApp update on SAI LAXMI CHSL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI LAXMI CHSL have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI LAXMI CHSL has one building filed: SAI LAXMI with 9 floors.

How big is the land of SAI LAXMI CHSL?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI LAXMI CHSL stands on 286 sq m of land (about 0.1 acres), with 710 sq m of sanctioned built-up area.

Where can I read reviews of SAI LAXMI CHSL?

Google Maps has reviews of SAI LAXMI CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI LAXMI CHSL?

SAI LAXMI CHSL by SHREEJANI DEVELOPERS is in Ckp Colony, Mumbai (pincode 400092), near Borivali West, Shimpoli, Eksar Village, Maharashtra, and is registered on MahaRERA as P51800013373, per GharKundli's check of MahaRERA records.

How many homes are in SAI LAXMI CHSL?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI LAXMI CHSL has 12 homes in 1 tower registered on MahaRERA.

When was SAI LAXMI CHSL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI LAXMI CHSL was registered on MahaRERA on 26 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI LAXMI CHSL?

No court cases are listed for SAI LAXMI CHSL on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SAI LAXMI CHSL?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREEJANI DEVELOPERS.

All projects in Borivali West (400092) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.