SHREE SADGURU VINAYAK COMMERCIAL COMPLEX
by SHRI SADGURU ASSOCIATES · Ashok Stamb, NashikAlso near Gole Colony, M G Road, Gandhi Nagar (Nashik)
Possession date of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX: 31 March 2028, moved from 31 March 2026 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600077144, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHREE SADGURU VINAYAK COMMERCIAL COMPLEX?
How the possession date of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX has moved
31 March 2026
Completion date given when the project was registered
31 March 2028
Extended at the builder's request (MahaRERA application EA20052621023)
Reason the builder gave MahaRERA:
“The project registration extension is being sought because the project has experienced unavoidable delays due to circumstances beyond the promoter’s control, which have affected the planned schedule of completion. During the course of execu…” Read the full reason
“The project registration extension is being sought because the project has experienced unavoidable delays due to circumstances beyond the promoter’s control, which have affected the planned schedule of completion. During the course of execution, the project faced delays in obtaining certain approvals and clearances from the concerned authorities, shortage of labour, interruptions in the supply of construction materials, and site-level execution challenges that slowed down the pace of work. In addition, fluctuations in market conditions and increased construction costs affected the smooth fl…”
Source: SHREE SADGURU VINAYAK COMMERCIAL COMPLEX’s extension records on MahaRERA (P51600077144), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHREE SADGURU VINAYAK COMMERCIAL COMPLEX
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600077144
- Status
- Registered and active
- Builder
- SHRI SADGURU ASSOCIATES
- Location
- Ashok Stamb, Nashik · 422001
- Project type
- Commercial
- Registered on
- 23 Jul 2024
- Completion date at registration
- March 2026
- Latest completion date
- March 2028
- Delay so far
- 24 months
- Homes
- 0
- Sold or booked
- 11%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHREE SADGURU VINAYAK COMMERCIAL COMPLEX | 100% | 95% | 85% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- SHREE SADGURU VINAYAK COMMERCIAL COMPLEX: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE SADGURU VINAYAK COMMERCIAL COMPLEX every month.
SHREE SADGURU VINAYAK COMMERCIAL COMPLEX: buildings, flats and land, as filed on MahaRERA
- Buildings: SHREE SADGURU VINAYAK COMMERCIAL COMPLEX (6 floors, 96 units)
- Land: 658 sq m (about 0.2 acres) · sanctioned built-up 2,368 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Bharat Jethlal Thakkar (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 13 months); 2 still being built, 1 past the promised date (typically 3 months late). No complaints on MahaRERA.
Read Google reviews of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHREE SADGURU VINAYAK COMMERCIAL COMPLEX: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHREE SADGURU VINAYAK COMMERCIAL COMPLEX
What is the possession date of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE SADGURU VINAYAK COMMERCIAL COMPLEX in Ashok Stamb, Nashik is 31 March 2028 — 24 months later than 31 March 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SHREE SADGURU VINAYAK COMMERCIAL COMPLEX?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE SADGURU VINAYAK COMMERCIAL COMPLEX's builder has filed on MahaRERA, the official one, is 31 March 2028, already 24 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SADGURU VINAYAK COMMERCIAL COMPLEX's builder applied to MahaRERA to extend the completion date once: to 31 March 2028, giving the reason "The project registration extension is being sought because the project has experienced unavoidable delays due to circumstances beyond the promoter’s control, which have affected the planned schedule of completion. During the course of execution, the project faced delays in obtaining certain approvals and clearances from the concerned authorities, shortage of labour, interruptions in the supply of construction materials, and site-level execution challenges that slowed down the pace of work. In addition, fluctuations in market conditions and increased construction costs affected the smooth fl…".
What is the RERA number of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX in Ashok Stamb, Nashik is P51600077144.
Is SHREE SADGURU VINAYAK COMMERCIAL COMPLEX registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SADGURU VINAYAK COMMERCIAL COMPLEX is registered as P51600077144 and its status is "Registered and active".
What is the construction status of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SADGURU VINAYAK COMMERCIAL COMPLEX's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHREE SADGURU VINAYAK COMMERCIAL COMPLEX is 95% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.
Does SHREE SADGURU VINAYAK COMMERCIAL COMPLEX have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SHREE SADGURU VINAYAK COMMERCIAL COMPLEX safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SADGURU VINAYAK COMMERCIAL COMPLEX is registered on MahaRERA as P51600077144, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHREE SADGURU VINAYAK COMMERCIAL COMPLEX's possession date changes?
The latest dates are on SHREE SADGURU VINAYAK COMMERCIAL COMPLEX's MahaRERA page (P51600077144). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE SADGURU VINAYAK COMMERCIAL COMPLEX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHREE SADGURU VINAYAK COMMERCIAL COMPLEX have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SADGURU VINAYAK COMMERCIAL COMPLEX has one building filed: SHREE SADGURU VINAYAK COMMERCIAL COMPLEX with 6 floors and 96 units.
How big is the land of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SADGURU VINAYAK COMMERCIAL COMPLEX stands on 658 sq m of land (about 0.2 acres), with 2,368 sq m of sanctioned built-up area.
What is the track record of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Bharat Jethlal Thakkar (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 13 months); 2 still being built, 1 past the promised date (typically 3 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX?
Google Maps has reviews of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHREE SADGURU VINAYAK COMMERCIAL COMPLEX?
SHREE SADGURU VINAYAK COMMERCIAL COMPLEX by SHRI SADGURU ASSOCIATES is in Ashok Stamb, Nashik (pincode 422001), near Gole Colony, M G Road, Gandhi Nagar (Nashik), Maharashtra, and is registered on MahaRERA as P51600077144, per GharKundli's check of MahaRERA records.
How many homes are in SHREE SADGURU VINAYAK COMMERCIAL COMPLEX?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SADGURU VINAYAK COMMERCIAL COMPLEX has 0 homes in 1 tower registered on MahaRERA, and 11% of them are sold or booked.
When was SHREE SADGURU VINAYAK COMMERCIAL COMPLEX registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SADGURU VINAYAK COMMERCIAL COMPLEX was registered on MahaRERA on 23 July 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on SHREE SADGURU VINAYAK COMMERCIAL COMPLEX?
No court cases are listed for SHREE SADGURU VINAYAK COMMERCIAL COMPLEX on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHRI SADGURU ASSOCIATES, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SHREE SADGURU VINAYAK COMMERCIAL COMPLEX
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Nashik →
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- YUNUS RESIDENCY
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- SHREE VISHVA
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- SARA SERENITY APARTMENT
Other projects by SHRI SADGURU ASSOCIATES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.