A.R AVENUE
by AIBANI ENTERPRISE · Azad Nagar S.O (Mumbai), MumbaiAlso near Jogeshwari WEst, Oshiwara, Andheri West
Possession date of A.R AVENUE: 15 December 2023, moved from 31 December 2019 (48 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800009415. Status: Lapsed (registration period ended). 31 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2023) has passed.
What do you want to know about A.R AVENUE?
How the possession date of A.R AVENUE has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51800001322)
Reason the builder gave MahaRERA: “SINCE MAY 2018, AS THERE IS NO CLARITY OF DCR 2034, HENCE NO FURTHER PERMISSION OF CONSTRUCTION AND FURTHER APPROVAL OF PLAN ARE BEING CONSIDERED BY M.C.G.M. THEREFORE THE PROJECT IS DELAYED.”
30 June 2022
Extended at the builder's request (MahaRERA application EXT51800010120)
Reason the builder gave MahaRERA:
“FURTHER DUE TO NO CLEARANCE FOR AMENITY SPACE IN DCPR 2034 , DUE TO WHICH THE PROJECT WAS STOPPED AS NO FURTHER PERMISSION WAS GIVEN , FURTHER FROM MARCH 2020 PANDEMIC SITUATION THE PROJECT GOT DELAYED FURTHER DUE TO PANDEMIC THERE IS SHORT…” Read the full reason
“FURTHER DUE TO NO CLEARANCE FOR AMENITY SPACE IN DCPR 2034 , DUE TO WHICH THE PROJECT WAS STOPPED AS NO FURTHER PERMISSION WAS GIVEN , FURTHER FROM MARCH 2020 PANDEMIC SITUATION THE PROJECT GOT DELAYED FURTHER DUE TO PANDEMIC THERE IS SHORTAGE OF LABOUR AND MATERIAL . FURTHER WE ARE TRYING OUR BEST TO FINISH PROJECT AS SOON AS POSSIBLE SO KINDLY PLEASE APPROVE OUR EXTENSION APPLICATION .”15 December 2023
Extended at the builder's request (MahaRERA application EXT51800013426)
Reason the builder gave MahaRERA:
“DEAR SIR AS THE EDIT OF THE ABOVE TABLE OF FLAT DETAILS IS NOT POSSIBLE DUE TO SOME TECHNICAL ERROR IN PAYMENT MODE SO PLEASE CONSIDER IT TOTAL NO. OF APARTMENT - 83 SOLD - 64 CONSENT OBTAINED - 34 PERCENTAGE OF CONSENT - 53%. DEAR SIR , WE…” Read the full reason
“DEAR SIR AS THE EDIT OF THE ABOVE TABLE OF FLAT DETAILS IS NOT POSSIBLE DUE TO SOME TECHNICAL ERROR IN PAYMENT MODE SO PLEASE CONSIDER IT TOTAL NO. OF APARTMENT - 83 SOLD - 64 CONSENT OBTAINED - 34 PERCENTAGE OF CONSENT - 53%. DEAR SIR , WE HAVE GOT ADDITIONAL FSI/FUNGIBLE IN THE SAME PROJECT A R AVENUE E WING WE HAVE TAKEN THE CONSENT FROM THE FLAT PURCHASERS WHO HAVE ALREADY PURCHASED FLATS IN THE SAME PROJECT , WE ASSURE THAT WE WILL COMPLETE THE PROJECT TILL DECEMBER 2023 , THE CONSENT FLAT PURCHASER IS AWARE OF THIS , IT IS A REQUEST TO EXTEND THE PROJECT COMPLETION DATE . THANKING YOU .”
Source: A.R AVENUE’s extension records on MahaRERA (P51800009415), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on A.R AVENUE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 31 complaints, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800009415
- Status
- Lapsed (registration period ended)
- Builder
- AIBANI ENTERPRISE
- Location
- Azad Nagar S.O (Mumbai), Mumbai · 400053
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2023
- Delay so far
- 48 months
- Homes
- 83
- Towers
- 1
- Complaints on MahaRERA
- 31
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- Title report on file
- Not found
Construction progress of A.R AVENUE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AR AVENUE E WING | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on A.R AVENUE every month.
A.R AVENUE: buildings, flats and land, as filed on MahaRERA
- Buildings: AR AVENUE E WING (26 floors)
- Land: 4,035 sq m (about 1.0 acres) · sanctioned built-up 7,000 sq m · recreational space 605 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of A.R AVENUE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
A.R AVENUE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about A.R AVENUE
What is the possession date of A.R AVENUE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for A.R AVENUE in Azad Nagar S.O (Mumbai), Mumbai is 15 December 2023 — 48 months later than 31 December 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for A.R AVENUE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date A.R AVENUE's builder has filed on MahaRERA, the official one, is 15 December 2023, already 48 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of A.R AVENUE extended?
According to GharKundli's check of MahaRERA records (updated November 2026), A.R AVENUE's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "SINCE MAY 2018, AS THERE IS NO CLARITY OF DCR 2034, HENCE NO FURTHER PERMISSION OF CONSTRUCTION AND FURTHER APPROVAL OF PLAN ARE BEING CONSIDERED BY M.C.G.M. THEREFORE THE PROJECT IS DELAYED."; to 30 June 2022, giving the reason "FURTHER DUE TO NO CLEARANCE FOR AMENITY SPACE IN DCPR 2034 , DUE TO WHICH THE PROJECT WAS STOPPED AS NO FURTHER PERMISSION WAS GIVEN , FURTHER FROM MARCH 2020 PANDEMIC SITUATION THE PROJECT GOT DELAYED FURTHER DUE TO PANDEMIC THERE IS SHORTAGE OF LABOUR AND MATERIAL . FURTHER WE ARE TRYING OUR BEST TO FINISH PROJECT AS SOON AS POSSIBLE SO KINDLY PLEASE APPROVE OUR EXTENSION APPLICATION ."; to 15 December 2023, giving the reason "DEAR SIR AS THE EDIT OF THE ABOVE TABLE OF FLAT DETAILS IS NOT POSSIBLE DUE TO SOME TECHNICAL ERROR IN PAYMENT MODE SO PLEASE CONSIDER IT TOTAL NO. OF APARTMENT - 83 SOLD - 64 CONSENT OBTAINED - 34 PERCENTAGE OF CONSENT - 53%. DEAR SIR , WE HAVE GOT ADDITIONAL FSI/FUNGIBLE IN THE SAME PROJECT A R AVENUE E WING WE HAVE TAKEN THE CONSENT FROM THE FLAT PURCHASERS WHO HAVE ALREADY PURCHASED FLATS IN THE SAME PROJECT , WE ASSURE THAT WE WILL COMPLETE THE PROJECT TILL DECEMBER 2023 , THE CONSENT FLAT PURCHASER IS AWARE OF THIS , IT IS A REQUEST TO EXTEND THE PROJECT COMPLETION DATE . THANKING YOU .".
What is the RERA number of A.R AVENUE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of A.R AVENUE in Azad Nagar S.O (Mumbai), Mumbai is P51800009415.
Is A.R AVENUE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), A.R AVENUE is registered as P51800009415 and its status is "Lapsed (registration period ended)".
What is the construction status of A.R AVENUE?
According to GharKundli's check of MahaRERA records (updated November 2026), A.R AVENUE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on AR AVENUE E WING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does A.R AVENUE have complaints on MahaRERA?
31 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is A.R AVENUE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), A.R AVENUE is registered on MahaRERA as P51800009415, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 48 months since registration and 31 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if A.R AVENUE's possession date changes?
The latest dates are on A.R AVENUE's MahaRERA page (P51800009415). GharKundli's Kundli Watch sends a free WhatsApp update on A.R AVENUE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does A.R AVENUE have?
According to GharKundli's check of MahaRERA records (updated November 2026), A.R AVENUE has one building filed: AR AVENUE E WING with 26 floors.
How big is the land of A.R AVENUE?
According to GharKundli's check of MahaRERA records (updated November 2026), A.R AVENUE stands on 4,035 sq m of land (about 1.0 acres), with 7,000 sq m of sanctioned built-up area and 605 sq m of recreational open space.
Where can I read reviews of A.R AVENUE?
Google Maps has reviews of A.R AVENUE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 31 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is A.R AVENUE?
A.R AVENUE by AIBANI ENTERPRISE is in Azad Nagar S.O (Mumbai), Mumbai (pincode 400053), near Jogeshwari WEst, Oshiwara, Andheri West, Maharashtra, and is registered on MahaRERA as P51800009415, per GharKundli's check of MahaRERA records.
How many homes are in A.R AVENUE?
According to GharKundli's check of MahaRERA records (updated November 2026), A.R AVENUE has 83 homes in 1 tower registered on MahaRERA.
When was A.R AVENUE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), A.R AVENUE was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on A.R AVENUE?
No court cases are listed for A.R AVENUE on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of A.R AVENUE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is AIBANI ENTERPRISE.
Check it yourself on MahaRERA
- How to check the possession date of A.R AVENUE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400053
- Parinee i
- Sunbeam Heights
- Tru Gardenia
- Gayatri Enclave
- ESTO ARKIS
- Naman Fifty Eight
- AMAHA SUNFLOWER
- FAME GARDEN
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.