by Sudha Buildcon · Tidke Nagar, Untwadi, NashikAlso near Govind Nagar

Possession date of Sudha Heights: 30 April 2031. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1220002500297, and currently active. Its completion date is now April 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Sudha Heights?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sudha Heights has moved

  1. 31 December 2030

    Completion date given when the project was registered

  2. 30 April 2031

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Sudha Heights’s extension records on MahaRERA (PR1220002500297), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sudha Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1220002500297
Status
Registered and active
Builder
Sudha Buildcon
Location
Tidke Nagar, Untwadi, Nashik · 422008
Project type
Residential / Group Housing
Registered on
17 Jul 2025
Completion date at registration
December 2030
Latest completion date
April 2031
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
42
Sold or booked
7%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Sudha Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A100%100%30%0%
Wing B100%71%10%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing A: covers 7 floors
  • Wing B: covers 7 floors

Latest CC order on MahaRERA: dated 31/03/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sudha Heights every month.

Sudha Heights: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Sudha Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sudha Heights: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sudha Heights

What is the possession date of Sudha Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sudha Heights in Tidke Nagar, Untwadi, Nashik is 30 April 2031, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Sudha Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sudha Heights's builder has filed on MahaRERA, the official one, is 30 April 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Sudha Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sudha Heights in Tidke Nagar, Untwadi, Nashik is PR1220002500297.

Is Sudha Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sudha Heights is registered as PR1220002500297 and its status is "Registered and active".

What is the construction status of Sudha Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Sudha Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 71% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Sudha Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Sudha Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sudha Heights is registered on MahaRERA as PR1220002500297, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sudha Heights's possession date changes?

The latest dates are on Sudha Heights's MahaRERA page (PR1220002500297). GharKundli's Kundli Watch sends a free WhatsApp update on Sudha Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sudha Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sudha Heights has 2 buildings filed: Wing A with 7 floors and 18 units; Wing B with 7 floors and 24 units.

How much parking does Sudha Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 22 covered car parking spaces for Sudha Heights.

How big is the land of Sudha Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Sudha Heights stands on 1,137 sq m of land (about 0.3 acres), with 3,485 sq m of sanctioned built-up area.

Where can I read reviews of Sudha Heights?

Google Maps has reviews of Sudha Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sudha Heights?

Sudha Heights by Sudha Buildcon is in Tidke Nagar, Untwadi, Nashik (pincode 422008), near Govind Nagar, Maharashtra, and is registered on MahaRERA as PR1220002500297, per GharKundli's check of MahaRERA records.

How many homes are in Sudha Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Sudha Heights has 42 homes in 2 towers registered on MahaRERA, and 7% of them are sold or booked.

When was Sudha Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sudha Heights was registered on MahaRERA on 17 July 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on Sudha Heights?

No court cases are listed for Sudha Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Sudha Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sudha Buildcon.

All projects with possession due in 2031 in Nashik →

Other projects in Nashik

All 49 projects in Trimurti Chowk (422008) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.