by M4 REALTY LLP · Girgaon, MumbaiAlso near Tardeo, Khetwadi, Grant Road

Possession date of M4 Aarambh: 25 April 2027, moved from 25 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900004211, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about M4 Aarambh?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of M4 Aarambh has moved

  1. 25 December 2024

    Completion date given when the project was registered

  2. 25 December 2026

    Extended at the builder's request (MahaRERA application EXT51900027627)

    Reason the builder gave MahaRERA: “Delay in basement work due to less plot size and depth of the basement and heavy traffic on road.”
  3. 25 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: M4 Aarambh’s extension records on MahaRERA (P51900004211), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on M4 Aarambh

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900004211
Status
Registered and active
Builder
M4 REALTY LLP
Location
Girgaon, Mumbai · 400004
Project type
Others
Registered on
9 Aug 2017
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of M4 Aarambh, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
M4 Aarambh1%18%50%65%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on M4 Aarambh every month.

M4 Aarambh: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of M4 Aarambh →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

M4 Aarambh: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about M4 Aarambh

What is the possession date of M4 Aarambh?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for M4 Aarambh in Girgaon, Mumbai is 25 April 2027 — 24 months later than 25 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for M4 Aarambh?

Builders and listing sites often quote an earlier "target" date for handover. The completion date M4 Aarambh's builder has filed on MahaRERA, the official one, is 25 April 2027, already 24 months later than the 25 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of M4 Aarambh extended?

According to GharKundli's check of MahaRERA records (updated October 2026), M4 Aarambh's builder applied to MahaRERA to extend the completion date once: to 25 December 2026, giving the reason "Delay in basement work due to less plot size and depth of the basement and heavy traffic on road.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of M4 Aarambh?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of M4 Aarambh in Girgaon, Mumbai is P51900004211.

Is M4 Aarambh registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), M4 Aarambh is registered as P51900004211 and its status is "Registered and active".

What is the construction status of M4 Aarambh?

According to GharKundli's check of MahaRERA records (updated October 2026), M4 Aarambh's status on MahaRERA is "Registered and active". As filed by the builder, slab work on M4 Aarambh is 18% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does M4 Aarambh have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is M4 Aarambh safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), M4 Aarambh is registered on MahaRERA as P51900004211, its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if M4 Aarambh's possession date changes?

The latest dates are on M4 Aarambh's MahaRERA page (P51900004211). GharKundli's Kundli Watch sends a free WhatsApp update on M4 Aarambh every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does M4 Aarambh have?

According to GharKundli's check of MahaRERA records (updated October 2026), M4 Aarambh has one building filed: M4 Aarambh with 20 floors.

How big is the land of M4 Aarambh?

According to GharKundli's check of MahaRERA records (updated October 2026), M4 Aarambh stands on 342 sq m of land (about 0.1 acres), with 2,559 sq m of sanctioned built-up area.

Where can I read reviews of M4 Aarambh?

Google Maps has reviews of M4 Aarambh written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is M4 Aarambh?

M4 Aarambh by M4 REALTY LLP is in Girgaon, Mumbai (pincode 400004), near Tardeo, Khetwadi, Grant Road, Maharashtra, and is registered on MahaRERA as P51900004211, per GharKundli's check of MahaRERA records. Its boundaries filed there include VITHALBHAI PATEL ROAD.

When was M4 Aarambh registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), M4 Aarambh was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on M4 Aarambh?

No court cases are listed for M4 Aarambh on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of M4 Aarambh?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M4 REALTY LLP.

All projects with possession due in 2027 in Mumbai City →

Other projects in pincode 400004

All 79 projects in Girgaon (400004) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.