Elite Tower
by Elite Construction Co. · Kajupada, Mumbai 400066Also near Borivali East, Borivali West, Daulat Nagar
What’s in the report? →Possession date of Elite Tower (MahaRERA P51800006103): 31 December 2027, moved from 31 July 2024 (41 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800006103, and currently active.
Source: MahaRERA website — records for P51800006103, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Elite Tower?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Elite Tower has moved
31 July 2024
Completion date given when the project was registered
31 July 2025
Extended at the builder's request (MahaRERA application EXT51800012875)
Reason the builder gave MahaRERA:
“New S.R. Sheme on plot bearing CTS No. 2220B/1/A(pt), village dahisar, Taluka Borivali, District MSD, Kajupada, Borivali (East ), Mumbai : 400016 with plot area admesuring 365.10sq.m. is amalgmated in Existing SR Scheme on plot bearing CTS…” Read the full reason
“New S.R. Sheme on plot bearing CTS No. 2220B/1/A(pt), village dahisar, Taluka Borivali, District MSD, Kajupada, Borivali (East ), Mumbai : 400016 with plot area admesuring 365.10sq.m. is amalgmated in Existing SR Scheme on plot bearing CTS 2220B/1/2 with plot admesuring 1739.0sq.m.”31 December 2027
Extended at the builder's request (MahaRERA application EA30032620446)
Reason the builder gave MahaRERA:
“1) We hereby state, declare and confirm that, we received Layout approval from the Slum Rehabilitation Authority dated. 19/07/2012 to Construct 2 Buildings and accordingly we had previously obtained RERA Registration for 2 Buildings. Detail…” Read the full reason
“1) We hereby state, declare and confirm that, we received Layout approval from the Slum Rehabilitation Authority dated. 19/07/2012 to Construct 2 Buildings and accordingly we had previously obtained RERA Registration for 2 Buildings. Details of the buildings are given below: i. Building 1 – Ground + 15 Floors ii. Building 2 – Ground + 20 Floors 2) Furthermore, we state that, we received fresh approval / permission from the Planning Authority dated. 24/11/2022 to Construct a third building, namely Building no. 3, having Ground + 10 Floors. 2a) In the same amendment, we received permission to…”
Source: Elite Tower’s extension records on MahaRERA (P51800006103), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Elite Tower
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800006103
- Status
- Registered and active
- Builder
- Elite Construction Co.
- Location
- Kajupada, Mumbai · 400066
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- July 2024
- Latest completion date
- December 2027
- Delay so far
- 41 months
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Elite Tower, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Rehab Bldg | 100% | 100% | 80% | 80% |
| Sale Building | 100% | 100% | 100% | 100% |
| Sai Sawli | 100% | 100% | 100% | 100% |
| Sidhivinayak | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Elite Tower every 1–2 months.
Elite Tower: buildings, flats and land, as filed on MahaRERA
- Buildings: Rehab Bldg (18 floors) · Sale Building (23 floors) · Sai Sawli (8 floors) · Sidhivinayak (8 floors)
- Land: 1,739 sq m (about 0.4 acres) · sanctioned built-up 4,962 sq m · recreational space 290 sq m
- Land, as filed: 2220B12
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Elite Construction (a group of 4 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 5 still being built, 2 past the promised date (typically 13 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Elite Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Elite Tower: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Elite Tower
What is the possession date of Elite Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Elite Tower in Kajupada, Mumbai is 31 December 2027 — 41 months later than 31 July 2024, the date given at registration.
The date has already moved 41 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Elite Tower?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Elite Tower's builder has filed on MahaRERA, the official one, is 31 December 2027, already 41 months later than the 31 July 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Elite Tower extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Tower's builder applied to MahaRERA to extend the completion date 2 times: to 31 July 2025, giving the reason "New S.R. Sheme on plot bearing CTS No. 2220B/1/A(pt), village dahisar, Taluka Borivali, District MSD, Kajupada, Borivali (East ), Mumbai : 400016 with plot area admesuring 365.10sq.m. is amalgmated in Existing SR Scheme on plot bearing CTS 2220B/1/2 with plot admesuring 1739.0sq.m."; to 31 December 2027, giving the reason "1) We hereby state, declare and confirm that, we received Layout approval from the Slum Rehabilitation Authority dated. 19/07/2012 to Construct 2 Buildings and accordingly we had previously obtained RERA Registration for 2 Buildings. Details of the buildings are given below: i. Building 1 – Ground + 15 Floors ii. Building 2 – Ground + 20 Floors 2) Furthermore, we state that, we received fresh approval / permission from the Planning Authority dated. 24/11/2022 to Construct a third building, namely Building no. 3, having Ground + 10 Floors. 2a) In the same amendment, we received permission to…".
What is the RERA number of Elite Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Elite Tower in Kajupada, Mumbai is P51800006103.
Is Elite Tower registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Tower is registered as P51800006103 and its status is "Registered and active".
What is the current construction status of Elite Tower? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Tower's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does Elite Tower have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Elite Tower safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Tower is registered on MahaRERA as P51800006103, its completion date has moved 41 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Elite Tower?
Elite Tower is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Elite Tower?
For a flat in Elite Tower (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Elite Tower received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Elite Tower is still under construction, with 31 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Elite Tower uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Elite Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Elite Tower's possession date changes?
The latest dates are on Elite Tower's MahaRERA page (P51800006103). GharKundli's Kundli Watch sends a free WhatsApp update on Elite Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Elite Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Tower has 4 buildings filed: Rehab Bldg with 18 floors; Sale Building with 23 floors; Sai Sawli with 8 floors; Sidhivinayak with 8 floors.
How big is the land of Elite Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Tower stands on 1,739 sq m of land (about 0.4 acres), with 4,962 sq m of sanctioned built-up area and 290 sq m of recreational open space.
What is the track record of Elite Tower's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Construction (a group of 4 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 5 still being built, 2 past the promised date (typically 13 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Elite Tower?
Google Maps has reviews of Elite Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Elite Tower?
Elite Tower by Elite Construction Co. is in Kajupada, Mumbai, pincode 400066 (near Borivali East, Borivali West, Daulat Nagar), Maharashtra, and is registered on MahaRERA as P51800006103, per GharKundli's check of MahaRERA records. Its land is filed as 2220B12. GharKundli lists all 228 MahaRERA projects in Borivali East (400066).
When was Elite Tower registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Tower was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Does Elite Tower have any legal issues or court cases?
No court cases are listed for Elite Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Elite Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Elite Construction Co., which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Elite Tower
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Borivali
- Saffronwoods CHSL
- L&T Realty Ahana Tower A
- Avirahi Elegance
- L&T Realty Ahana Tower B
- Parshuram Heights
- Maru Mansion
- LA SERENA Tower 5, Tower 6 and Tower 7
- Shraddha Skyline
Other projects by Elite Construction Co.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.