What’s in the report? →Possession date of Elite Residency (MahaRERA P51800048557): 30 June 2027, moved from 31 December 2025 (18 months later). It has 14 homes (1 BHK, 1 Room Kitchen and 2 BHK, 272–794 sq ft carpet), 33% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800048557, and currently active.
Source: MahaRERA website — records for P51800048557, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Elite Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Elite Residency has moved
31 December 2025
Completion date given when the project was registered
30 June 2027
Extended at the builder's request (MahaRERA application EA29122519099)
Reason the builder gave MahaRERA:
“The construction work of the project has been 50 Percent completed. The remaining works pertaining to balance floors , Internal walls, Sanitary fittings, Staircases, installation of lifts, water pumps, firefighting fittings, finishing work…” Read the full reason
“The construction work of the project has been 50 Percent completed. The remaining works pertaining to balance floors , Internal walls, Sanitary fittings, Staircases, installation of lifts, water pumps, firefighting fittings, finishing work and other related components are pending which we undertake to complete by 30/04/2027. Other miscellaneous works such as finishing, fire protection systems, water drainage systems, etc., will also be completed by 30/06/2027. After completing the above works, we will initiate the process for obtaining the requisite No Objection Certificates (NOCs) necessar…”
Source: Elite Residency’s extension records on MahaRERA (P51800048557), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Elite Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800048557
- Status
- Registered and active
- Builder
- Elite Construction Co.
- Location
- Kurla West, Mumbai · 400070
- Project type
- Residential / Group Housing
- Registered on
- 6 Jan 2023
- Completion date at registration
- December 2025
- Latest completion date
- June 2027
- Delay so far
- 18 months
- Homes
- 14
- Sold or booked
- 33%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Elite Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ELITE RESIDENCY | 100% | 80% | 65% | 10% |
Commencement certificate (CC), as filed on MahaRERA
- ELITE RESIDENCY: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Elite Residency every 1–2 months.
Elite Residency: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 413 – 546 | 6 |
| 1 BHK | 315 – 374 | 4 |
| 3 BHK | 684 – 794 | 3 |
| 1 Room Kitchen | 272 | 1 |
- Buildings: ELITE RESIDENCY (16 floors, 14 units)
- Land: 271 sq m (about 0.1 acres) · sanctioned built-up 1,310 sq m
- Boundaries filed include: PATANKAR MARG, MARKAZ MASJID, PIPE ROAD
- Land, as filed: 947
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Elite Construction (a group of 4 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 5 still being built, 2 past the promised date (typically 13 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Elite Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Elite Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Elite Residency
What is the possession date of Elite Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Elite Residency in Kurla West, Mumbai is 30 June 2027 — 18 months later than 31 December 2025, the date given at registration.
The date has already moved 18 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Elite Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Elite Residency's builder has filed on MahaRERA, the official one, is 30 June 2027, already 18 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Elite Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Residency's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "The construction work of the project has been 50 Percent completed. The remaining works pertaining to balance floors , Internal walls, Sanitary fittings, Staircases, installation of lifts, water pumps, firefighting fittings, finishing work and other related components are pending which we undertake to complete by 30/04/2027. Other miscellaneous works such as finishing, fire protection systems, water drainage systems, etc., will also be completed by 30/06/2027. After completing the above works, we will initiate the process for obtaining the requisite No Objection Certificates (NOCs) necessar…".
What is the RERA number of Elite Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Elite Residency in Kurla West, Mumbai is P51800048557.
Is Elite Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Residency is registered as P51800048557 and its status is "Registered and active".
What is the current construction status of Elite Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ELITE RESIDENCY is 80% done and internal work 65%. GharKundli's full report compares construction progress with the deadline.
Does Elite Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Elite Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Residency is registered on MahaRERA as P51800048557, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Elite Residency?
Elite Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Elite Residency are 272 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Elite Residency?
For a flat in Elite Residency (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Elite Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Elite Residency is still under construction, with 30 June 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Elite Residency a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Residency is a redevelopment: 5 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Elite Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Elite Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Elite Residency's possession date changes?
The latest dates are on Elite Residency's MahaRERA page (P51800048557). GharKundli's Kundli Watch sends a free WhatsApp update on Elite Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Elite Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Residency has one building filed: ELITE RESIDENCY with 16 floors and 14 units.
What are the flat sizes (carpet area) in Elite Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Elite Residency: 2 BHK: 413 to 546 sq ft carpet (6 homes); 1 BHK: 315 to 374 sq ft carpet (4 homes); 3 BHK: 684 to 794 sq ft carpet (3 homes); 1 Room Kitchen: 272 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Elite Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Residency stands on 271 sq m of land (about 0.1 acres), with 1,310 sq m of sanctioned built-up area.
What is the track record of Elite Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Construction (a group of 4 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 5 still being built, 2 past the promised date (typically 13 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Elite Residency?
Google Maps has reviews of Elite Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Elite Residency?
Elite Residency by Elite Construction Co. is in Kurla West, Mumbai, pincode 400070 (near Nehru Nagar, Kurla East, Andheri West), Maharashtra, and is registered on MahaRERA as P51800048557, per GharKundli's check of MahaRERA records. Its boundaries filed there include PATANKAR MARG, MARKAZ MASJID, PIPE ROAD. Its land is filed as 947. GharKundli lists all 92 MahaRERA projects in Kurla West (400070).
How many flats are in Elite Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Residency has 14 homes in 1 tower registered on MahaRERA, and 33% of them are sold or booked.
When was Elite Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Residency was registered on MahaRERA on 6 January 2023. GharKundli did not find a title report on the land on file there.
Does Elite Residency have any legal issues or court cases?
No court cases are listed for Elite Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Elite Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Elite Construction Co., which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Elite Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Kurla West (400070)
- Jai Shreeram Prasanna CHSL
- Dadamiya’s Man'souza Height
- Kalyan Kutir Co-operative Housing Society Limited
- Sanjary Apartments
- Taiba Residency
- Anupam Villa CHSL
- Sai Chamunda
- Deraiya Luxurio
Other projects by Elite Construction Co.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.