PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I

by GIRIRAJ ENTERPRISES · Santacruz East, MumbaiAlso near Andheri West, Ambivali West, Vile Parle East

Possession: PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800009344. Status: Completed. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the July 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800009344
Status
Completed
Builder
GIRIRAJ ENTERPRISES
Location
Santacruz East, Mumbai · 400053
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
July 2019
Homes
70
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I100%100%95%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I every month.

PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I: buildings, flats and land, as filed on MahaRERA

  • Buildings: PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I (19 floors)
  • Land: 2,277 sq m (about 0.6 acres) · sanctioned built-up 4,945 sq m · recreational space 187 sq m
  • Boundaries filed include: ANDHERI SPORTS COMPLEX
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Giriraj Enterprises (a group of 3 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, all within the promised date; 3 still being built, 2 past the promised date (typically 25 months late). 3 complaints on MahaRERA across 2 projects.

Read Google reviews of PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I

What is the possession date of PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I in Santacruz East, Mumbai is 25 July 2019.

Is the builder's possession date different from the MahaRERA date for PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I's builder has filed on MahaRERA, the official one, is 25 July 2019, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I in Santacruz East, Mumbai is P51800009344.

Is PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I is registered as P51800009344 and its status is "Completed".

What is the construction status of PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I?

According to GharKundli's check of MahaRERA records (updated November 2026), PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I's status on MahaRERA is "Completed". As filed by the builder, slab work on PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I is registered on MahaRERA as P51800009344, its MahaRERA status is "Completed", its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: PEARL RESIDENCY - WING-B, RESIDENTIAL PHASE - III (P51800006592, possession 1 Aug 2024). Check that your agreement names the registration of your own wing.

How can I get updates if PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I's possession date changes?

The latest dates are on PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I's MahaRERA page (P51800009344). GharKundli's Kundli Watch sends a free WhatsApp update on PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I have?

According to GharKundli's check of MahaRERA records (updated November 2026), PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I has one building filed: PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I with 19 floors.

How big is the land of PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I?

According to GharKundli's check of MahaRERA records (updated November 2026), PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I stands on 2,277 sq m of land (about 0.6 acres), with 4,945 sq m of sanctioned built-up area and 187 sq m of recreational open space.

What is the track record of PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Giriraj Enterprises (a group of 3 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, all within the promised date; 3 still being built, 2 past the promised date (typically 25 months late). 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I?

Google Maps has reviews of PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I?

PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I by GIRIRAJ ENTERPRISES is in Santacruz East, Mumbai (pincode 400053), near Andheri West, Ambivali West, Vile Parle East, Maharashtra, and is registered on MahaRERA as P51800009344, per GharKundli's check of MahaRERA records. Its boundaries filed there include ANDHERI SPORTS COMPLEX.

How many homes are in PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I?

According to GharKundli's check of MahaRERA records (updated November 2026), PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I has 70 homes in 1 tower registered on MahaRERA.

When was PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I?

No court cases are listed for PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GIRIRAJ ENTERPRISES, which has 5 other projects registered on MahaRERA.

Other projects in Santacruz East

All 161 projects in Andheri West (400053) →

Other projects by GIRIRAJ ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.